You are on page 1of 14

Minerals Engineering 18 (2005) 811–824

This article is also available online at:


www.elsevier.com/locate/mineng

A practical guide to re-treatment of gold processing residues


A. Muir, J. Mitchell, S.R. Flatman *, C. Sabbagha
AngloGold Ashanti Ergo Operations, Vlakfontein Road, Brakpan, South Africa

Received 3 December 2004; accepted 12 January 2005

Abstract

Re-processing of ‘‘old’’ residue tailings has proved to be a profitable business for several operations, usually when incorporated
into an existing facility to supplement declining ore arisings. These resources often prove to be a source of ‘‘cheap gold’’ since the
high mining and feed preparation costs have already been incurred and only ‘‘variable’’ treatment costs are incurred in addition to
the relatively low reclamation costs.
Advances in processing technology, together with a degree of gold release through ageing of the ore over many years, often pro-
vide gold recovery in the range 50–60% (headgrade around 0.4–0.5 g/t), which is sufficient to cover the low processing costs and
make a positive contribution to the profitability of an operation.
Additional benefits such as releasing land for urban development or reducing environmental liabilities may also flow from this
type of exercise.
The paper covers key practical aspects of developing and implementing a residue re-treatment project beginning with evaluation
of the resource, through the implementation phase and into final closure.
 2005 Published by Elsevier Ltd.

Keywords: Gold ores reclamation; Sampling

1. Introduction applicable to the recovery of other minerals. For the


purpose of this paper, gold mining residues with a par-
This paper presents an overview of the various meth- ticle size of approximately 70–80% finer than 74 lm
odologies used in the re-treatment of gold residue depos- are defined as slime and residues grading 10–20% finer
its (excluding waste rock) from the initial evaluation than 74 lm as sand.
phase to the final process plant design. Whilst aimed
at providing a generic overview of the subject, it is 1.1. Evaluation phase
strongly influenced by the authorsÕ experience in the
processing of sand and slimes dumps at the AngloGold The first phase of the re-treatment process is to ob-
Ashanti Ergo operation in South Africa. It is therefore tain credible information with the sampling programme
specifically aimed at gold recovery from a mixture of (and the subsequent metallurgical testwork) a function
sulphide and non-sulphide bearing residues, which arose of several factors including the complexity of the re-
from mining activities on the Witwatersrand from the source and the degree of risk involved in the project.
early 1900s until the mid 1960s. Accepting this, many
of the reclamation and processing techniques may be 1.2. Scouting

*
Corresponding author. Tel.: +27 11 742 2610; fax: +27 11 742
This first step in evaluation is normally a preliminary
1817. screen to establish whether a resource has any potential
E-mail address: sflatman@anglogoldashanti.com (S.R. Flatman). or can be eliminated without any significant expenditure

0892-6875/$ - see front matter  2005 Published by Elsevier Ltd.


doi:10.1016/j.mineng.2005.01.027
812 A. Muir et al. / Minerals Engineering 18 (2005) 811–824

being undertaken. Sampling would normally comprise The X and Y co-ordinates of each point as well as the
simple grab sampling with reasonable care being taken collar elevation are measured and recorded. Every sam-
to ensure appropriate coverage of the deposit. The ple point is plotted on the survey map and is given a
objective of this stage is to quantify the potential of consecutive number which is matched to a sample num-
the deposit and it will not produce any concrete findings ber and hence to a gold and sulphur grade. From the
as to the financial viability of processing the material. collar elevation and the depth of the slime to ground
The required outcome from this stage will be a recom- level the contour of the underlying ground can be
mendation either to proceed to a more detailed evalua- determined.
tion stage or to abandon the project. A hand auger can be used on material with a depth of
Metallurgical testwork for this stage would be limited less than 2 m with deeper holes requiring a hydraulically
to assaying for gold and sulphur, as well as leaching for driven sleeved-auger which normally drills a 50 mm
18 h at excess cyanide levels (up to 2 kg/ton to ensure diameter hole. The borehole is drilled and sampled in
complete dissolution) of composite samples after pre- 1.5 m increments to provide suitable information on
aeration. It is preferable to conduct two sets of tests with grade variation throughout the height of the dump.
and without carbon (30 g/l) present to establish the pres- Due to the fact that sleeved-auger drilled boreholes
ence and effect of preg-robbers and the response to CIL are not lined, the depth of the hole may be affected by
conditions. the sand/slime stability at depth, however holes as deep
as 35–40 m may be achieved in favourable conditions.
1.3. Pre-feasibility study The moisture content and particle size are the two fac-
tors which influence the stability of the material being
The next level of evaluation will be introduced only if drilled.
justified by the scouting testwork. The pre-feasibility Sand, being coarser than slime, is more likely to col-
study requires a more detailed level of information lapse and close the hole at depths exceeding 25–30 m.
and hence specific sampling and testwork procedures Similarly, very wet slime (+30% moisture) will not sup-
need to be developed for this stage of the project. port itself and the hole will close as the auger is with-
drawn. Because the moisture content of the slime
1.4. Sampling and metallurgical testwork within the same dam may vary greatly, one borehole
may reach ground level where an adjacent hole will not.
The sampling programme must be developed with When sampling down to ground level of a deposit
due consideration being given to the characteristics of cannot be achieved due to drilling constraints, the calcu-
the site and the resource material. The normal sampling lated grade of the dump may be lower than the actual in
grid for large slimes dams is 200 m spacing, however this situ grade due to incomplete sampling of the bottom of
may be increased or decreased according to the size and the dump which often has an enriched base layer, with
detail of the dam. this particularly so in the case of sand dumps. It is also
The grid must be of a size and orientation which will important to collect the first 0.5 m of soil as a separate
not place an excessive number of sampling points on the sample for grade analysis to determine whether gold
walls of the dam or next to historical feed points as expe- has migrated into the underlying surface.
rience has shown these to be a potential source of bias Dams containing rock or other physical entrainments
since they can represent areas of concentration which are very difficult to sample down to ground level. Gen-
arise during the dam construction process. A further erally however on a clean slimes dam 85% of the bore-
‘‘wall effect’’ relates to the oxidation of the outer 2– holes will reach ground with relative ease.
3 m of slimes in a dam, with a resultant loss of sulphide Other sampling techniques that may be used for sam-
sulphur. On a high sulphur grade dam the overall sul- pling shallow sand/slime, which is contaminated with
phur grade may be biased downwards as a result of this rock, rubble or refuse include digging of trenches or pits.
effect. The sampling programme must therefore sample
the walls in proportion to the total tonnage contained 1.5. Sample preparation
in the walls compared to the total resource tonnage. Iso-
lated pockets of slime, toe walls, toe paddocks, marshy The first stage of sample preparation is to thoroughly
areas and run-off slimes are sampled on a smaller grid mix each incremental sample to ensure homogeneity. A
than the main dam. sub-sample taken from each incremental sample is sub-
Sand dumps, due to their structural shape, are sam- mitted for gold and sulphur determination and other
pled on a smaller grid than slimes dams and, as sand analysis as required. The remainder of each incremental
generally has a lower sulphur grade, the ‘‘wall effect’’ sample is split into two portions with one portion being
can be ignored. retained in reserve and the other portion being com-
The sample points are set out and marked on the bined with all the other incremental portions to make
slimes dam by a land surveyor using a GPS system. a single borehole composite sample. A sub-sample, pro-
A. Muir et al. / Minerals Engineering 18 (2005) 811–824 813

portional in size to the depth of each borehole, is taken tests from this list depending on the most likely process-
and combined with the other sub-samples to make a sin- ing scenario.
gle dam composite sample representative of the entire Samples should not be dried in an oven as this has
dam. The remainder of the original borehole composite been shown to enhance gold leach recovery and material
samples are kept in reserve. The dam composite sample for leach testwork is therefore not dried but kept as a
is sub-sampled for gold, sulphur and other relevant moist filter cake. Marshy material, which has a high or-
analyses as well as for metallurgical testwork. The soil ganic content and residue material from a plant operat-
samples from each borehole are separately mixed and ing a carbon circuit, must also be tested for potential
assayed for gold and sulphur. preg robbing.
The preparation steps described above will result in The following tests should be considered when
borehole and dam composite samples which are repre- designing the testwork programme:
sentative of the material on a vertical plane. Composites
can also be prepared to provide a horizontal representa- • Scouting tests to determine lime, cyanide and oxygen
tion if required. Likewise composites can be generated requirements.
for groups of boreholes representing different areas of • Kinetic tests to establish residual cyanide and lime
a dam (high grade areas, sand/slime areas, specific cross levels.
section areas etc), depending on the complexity of the • Direct leach (lime, cyanide and dissolved oxygen
deposit. > = 8 ppm).
The samples should be stored in their naturally aris- • Direct leach (no oxygen addition).
ing damp condition in sealed bags/containers to prevent • Direct leach (2 h pre-aeration).
exposure to air as these materials frequently have high • CIL (at optimum reagent additions with 30 g/l car-
oxygen demand and can start to oxidise on exposure bon addition).
to air. Stored samples have a finite shelf life of ±3 • Extraction rate (for optimum route determination).
months by which time they have oxidised to the point • Mixed feed ratio tests where a number of sites will be
where they are no longer suitable for testwork and are reclaimed.
thus discarded. The storage of samples under nitrogen • Settling tests.
or inert gas should be considered if oxygen demand is • Size distribution and gold deportment.
anticipated to be high. • Presence of Ôpreg robbingÕ species.
• Viscosity of the resultant slurry (may cause floating
1.6. Assaying of carbon in the circuit).
• Flotation testwork, gold leach on pyrite concentrate
As described, incremental and borehole samples are and flotation tails.
assayed for gold and sulphur. The overall dam compos- • Roasting of pyrite and calcine gold leach.
ite sample is assayed for gold, sulphur and other ele-
ments of interest. Where a slime deposit interfaces It should be noted that deportment of gold in residue
with a sand deposit, the incremental samples, which con- deposits often contains significant amounts of surface
tain both sand and slime, can be screened and the gold precipitated auricyanide which will dissolve easily. Thus
grade of both the sand and slime fractions determined. in all testwork, gold in solution must be determined and
Assaying must be done at a reputable laboratory and combined with gold on solids to give the total gold
should include duplicates, blanks and known standards grade.
to monitor the analytical accuracy and possibility of
sample tampering.
2. Evaluation
1.7. Metallurgical testwork
2.1. Flowsheet development
The testwork programme should be designed to allow
the most economically effective treatment route to be se- Once the testwork results are known, a formal flow-
lected. A variety of metallurgical testwork is done on sheet can be developed based on the unit processes re-
slimes/sand samples including direct gold leach; sand quired, the scale of the operation, expected reagent
milling; cyanide, lime and oxygen demand; in situ mois- requirements and so on. The key aspects for flowsheet
ture content and pH; settling characteristics and size design are liable to be the method of reclamation to be
analysis. A high sulphur grade dam would be subjected employed (hydraulic or mechanical) the need for mill-
to flotation testwork which would include flotation ing; the necessity to incorporate a flotation step, with
recovery of gold and sulphur; roasting; flotation tailings subsequent pyrite treatment (leach, or roast and leach
gold leach and calcine gold leach. The testwork pro- calcine) and flotation tails leach and type of gold circuit
gramme has to be designed to incorporate the relevant e.g. CIL.
814 A. Muir et al. / Minerals Engineering 18 (2005) 811–824

The design also needs to take cognisance of any minimal dilution under normal reclamation operations
existing underutilised or redundant plant available but this may rise to as much as 30% when conducting fi-
through which the material could be processed. The nal floor clean-up operations.
location and size of the resource may impact on the
process route to be evaluated. The reduction of infra- 2.3. Size distribution
structure costs to achieve economic optimum may be
achieved by utilising the existing infrastructure of the As previously noted, the testwork includes size dis-
nearest plant, even if this does not provide the maxi- tribution of the resource. This enables identification
mum recovery factor. of the material as slime, sand or a mixture and this will
Operating costs can now be predicted to a greater de- influence the reclamation method and treatment route.
gree of accuracy and used in the financial evaluation It is normally accepted that the slime pumping, piping
which is incorporated into the feasibility study. and treatment facilities can tolerate up to 10% sand in
slime, but this needs to be carefully controlled to en-
2.2. Tonnage and grade calculation sure excessive amounts of sand are not slugged into
the system.
The tonnage of the resource is calculated using sim- The bottom level of a slimes dam will tend to be more
ple volume and in situ density information. Surface coarse than the average for the dam with this effect com-
areas may be surveyed, measured from a scale map/ pounded by the coarseness of the underlying ground
aerial photograph or measured with a measuring material. This size segregation and ground coarseness
wheel. The depth of the slime/sand is calculated from will impact on the ability to reclaim the bottom slime
the borehole depths/ground contour. Typical slime- level and on final clean-up activities due to rapid settling
dry in situ density is 1.473 t/m3 and sand is normally of coarse particles in the launders in a hydraulic recla-
1.40 t/m3. mation system.
It is important that the entire footprint of a slime/ Sand will normally require some degree of milling
sand deposit is identified and delineated. The footprint, prior to either direct treatment or combination with
which includes run-off material and other areas of slime either reclaimed slimes or ore.
associated with the main deposit, is used for tonnage
calculations and the setting out of permit boundaries. 2.4. General observations
Aerial or satellite scaled photographs are an excellent
means of determining the footprint of a deposit. In addition to the formal testwork it is important to
Gold and sulphur grades are determined from the include additional observations made on site which
borehole drilling grades that are always weighted to en- may influence the final flowsheet and financial model
sure an accurate calculation. An extrapolated grade can which are incorporated into the evaluation report.
be calculated for those boreholes that do not reach Of particular importance here is the presence of
ground level provided there are values from other holes contamination within the resource which may hamper
in the proximity. Grade extrapolation must however be reclamation operations or impact on the efficiency of
the exception rather than the rule and should be used the treatment process. The presence of rock (possibly
conservatively. from previous cladding or buttressing efforts) in or
Grade dilution and its possible effect on profitability on the dam will interfere with the sample drilling, will
and measurement must be considered at this stage. impede hydraulic reclamation (and reduce daily ton-
Grade dilution occurs when high-grade material is nage), and will involve additional costs for removal
blended with low grade or barren material to such an ex- of the rock.
tent that the overall feed grade to a metallurgical plant is Dams which have been used as mine, municipal or
reduced and the processed tonnage increased. This dilu- industrial waste disposal sites will require special atten-
tion can occur during the mining operation when so tion as this foreign material in the dam will also impede
called ‘‘undercutting’’ takes place during hydraulic and sampling and involve removal and disposal costs.
mechanical reclamation. The degree to which this affects Chemical and organic waste (including sewage and
the grade is largely influenced by the nature of the animal/abattoir waste) can lead to accelerated pipe
sub-base material and the ‘‘cleanliness’’ of the mining and equipment corrosion, high oxygen, lime and cyanide
techniques involved. Ergo recently introduced a more demand, and surface coating of particles leading to low
mobile monitor gun (the excavator gun) to avoid dilu- recovery. The identification of contaminants during the
tion caused during bulldozing and other mechanical resource evaluation stage is therefore extremely impor-
floor clean-up operations. An estimate of this dilution tant as these may render processing of the resource eco-
effect must be allowed for in the financial model and it nomically unattractive. Furthermore the contaminants
should be noted that this becomes more of a problem to- will involve a removal cost and possibly represent an
wards the end of life of the operation. There is typically environmental problem.
A. Muir et al. / Minerals Engineering 18 (2005) 811–824 815

2.5. Financial evaluation 3. Operational phase

All of the collected information (together with 3.1. Reclamation methods overview
assumptions on revenue prices, future escalation etc) is
then fed into a financial model covering the life of the There are three main methods of reclaiming the mate-
resource. This model will calculate the Net Present Va- rial from the resource namely hydraulic re-mining using
lue (NPV) and rates of return which the project will gen- high pressure water monitor guns, mechanical reclama-
erate. If these meet the required investment criteria, the tion, and dredging.
project will proceed to implementation although a full Hydraulic re-mining is generally best suited to slime
feasibility study may be required depending on the scale reclamation and is not as well suited to sand reclamation
of the capital outlay and the necessity for external fund- due to the tendency of sand to settle out in the launders
ing. All costs associated with the project including from the face to the pumpstation.
acquisition costs, capital expenditure for infrastructure Mechanical reclamation is conversely better suited to
and operational costs including rehabilitation/closure sand reclamation and is an expensive option for slime
have to be included in the financial model. due to its tendency to choke up transfer points on a
mechanical reclamation system.
2.6. Infrastructure requirements Dredging is generally very expensive and only used in
specialised applications where hydraulic or mechanical
An optimum flowsheet will have been determined via re-mining is not possible. An example of this would be
the metallurgical testwork and, in order to size the reclamation from a water logged marsh area where
equipment correctly the required throughput must be drainage to facilitate mechanical or hydraulic mining
determined. The optimum throughput for the operation is not feasible.
will be influenced by the size and grade of reserves as It should be noted that potential reclamation chal-
well as the impact of throughput rate on project life, lenges which may exist must be identified and considered
capital cost and the effect of ‘‘economy of scale’’ on during the evaluation phase when identifying the pre-
operating costs. It is generally accepted that these low- ferred reclamation method. These challenges could in-
grade operations need to be volume driven in order to clude high, low or variable in situ density; presence of
generate acceptable returns. A number of different solid contaminants such as rocks or scrap; flat or very
throughputs have to be tested via the financial model steep topography and the presence of watercourses.
in order to establish which throughput rate gives the These factors can impact directly on the reclamation
best balance of capital input, operating cost and return. process and must be properly identified, quantified and
In preparing preliminary cost estimates it is normal to considered during the evaluation phase as they directly
source information from operations with a similar pro- influence the capital and treatment costs of the project.
cess and technology. Sensitivity calculations evaluating The advantages and disadvantages of the various rec-
the financial impact of variations in revenue and costs lamation techniques are summarised in Fig. 1.
will also assist the decision making process. Other Mechanical reclamation involves earth-moving
important considerations that influence the infrastruc- equipment such as bulldozers, front-end loaders and
tural requirements include the availability of services trucks, which load and haul or convey the material to
such as water, power, and access roads; the selected rec- a screening and re-pulping system. Bucket wheel
lamation strategy (hydraulic versus mechanical); the reclaimers with conveyor transfer systems have been
physical location of resources with regard to their prox- used on several operations with varying degrees of suc-
imity to each other and their proximity to existing treat- cess. Front-end loader and trucking would only be con-
ment facilities. sidered for very small deposits which could not carry the
capital cost of a more substantial installation.
2.7. Operating costs Dredging (underwater reclamation) is expensive due
to the high cost of the equipment required to carry out
The foregoing work would conclude in a formal pre- this work. It is also more challenging from an environ-
feasibility study report covering all aspects of the pro- mental perspective although it may be preferable to
ject. If the pre-feasibility study shows acceptable Net other options such as river diversions.
Present Value (NPV) and rate of return, it is then a man- Drainage of the site (during a dry season if possible)
agement decision as to whether, a further stage of feasi- is the preferred option due to cost and ‘‘manageability’’
bility is justified or necessary regarding proceeding or issues with dredging only being a recommended ap-
terminating the project. The subsequent feasibility study proach where drainage is not possible.
would be developed through a process of more detailed After draining, a decision to monitor or truck the
engineering drawings, specific equipment lists, tender material would be dependent on a site-specific evalua-
prices and so on. tion. If there is a favourable face height then monitoring
816 A. Muir et al. / Minerals Engineering 18 (2005) 811–824

Hydraulic Re-Mining
Advantages Disadvantages
Comparatively low operating cost. Inability to reclaim all material due to
uneven floor profile. Some degree of
mechanical reclamation will be required for
final clean up.
Ability to control pulp density and flow by Requires extensive trench and launder
varying the number of guns operating and excavations.
nozzle size.
Uses gravity to flow to pumpstation Satellite pumpstations will be required in
reducing energy costs. low-lying areas of the floor.
Simple, low-tech processing systems Significant impact of rainfall on operation
i.e. screening, pumping and pipelines. due to dilution at site.
More difficult to separate non-pay material
from pay material.

Mechanical Reclamation
Advantages Disadvantages
Clean up to ground floor possible. Comparatively high reclamation cost.
Can segregate non-payable material to be Firm ground surface required to support
left in situ. earthmoving machinery.
Higher recovered grades are required to
make this cost effective.

Dredging
Advantages Disadvantages
No major changes to water reticulation or High site establishment and de-
elimination of water inflows to the site to establishment costs for equipment.
be reclaimed.
Reclamation can be done with no impact Not all material will be reclaimed due to
of seasonal changes i.e. rainfall and the mechanical action of the dredger,
stormwater control. which causes material to “fluff up” and be
missed by the dredger.
Minimise water disturbance and Contract normally volume based.
consumption.
Best suited to reclamation of material Dredger inlet choking due to vegetation on
beneath swamps or lakes. site.
Effective in areas or poor bearing capacity Low reclaimed density compared to other
where mechanical equipment would sink. methods.
High total cost of reclamation.

Fig. 1. Advantages and disadvantages of various reclamation techniques.

should be the preferred option. The underfoot condi- guns at the reclamation sites. These guns direct high-
tions should be examined carefully to prevent the sink- pressure water jets at the slimes dam face. The resultant
ing of expensive machinery. slurry gravitates via earth launders, with finger screens
It is worth noting that estimating the tonnage re- installed to trap coarse trash and vegetation, to a trans-
claimed from underwater reclamation is often difficult fer pumpstation adjacent to each dam.
and, as a consequence, the efficiency of the operation The pumpstation is located at the lowest point on
may be difficult to evaluate. Due to the soft underfoot the perimeter of the dam allowing as much as possible
condition of a water filled dam, a clean separation be- of the dam material to gravitate to the screening and
tween slime and base material is unlikely. This can lead pumping station. In-dam satellite stations may be re-
to grade dilution of up to 30% with an equivalent ton- quired to reclaim any remaining slime in low-lying
nage and operating cost increase. areas.
After screening to remove coarse trash (typically
+2 mm), the slurry is pumped to the treatment complex
3.2. Slime reclamation by hydraulic remaining with the assistance of booster pumpstations where
pumping distances are long. The screen oversize which
Essentially this involves re-cycling water from the consists mainly of vegetation and hard lumps of slime
treatment complex to booster pumpstations from where is deposited on nearby sites where the stockpile can be
it is delivered at high pressure directly to the monitor rehabilitated at closure.
A. Muir et al. / Minerals Engineering 18 (2005) 811–824 817

3.3. Starting a reclamation operation and a better control of slurry density can be achieved
through the use of a programmed washing pattern
An area of the dam wall next to a pumpstation is (which is more reliable than manual control). Due to
mechanically excavated to serve as a catchment area. large gun and pipe sizes involved with full-face reclama-
The dam wall is re-instituted with two piped outlets tion these units would be moved by mechanical means.
through the wall for movement of slurry (lower outlet) As the full face of the dam is being reclaimed, the
and rainwater (upper outlet). gold grade will tend to be less variable than with a ben-
These are valved to avoid uncontrolled flood release, ching technique where isolated low-grade layers may be
which can be held in the catchment. Normal reclamation exposed for a period. In a full-face operation due to the
then begins from the selected start point with the slurry face height involved it is important to create a safe face-
flowing via the catchment area, through the slurry con- working angle to prevent damaging and hazardous face
trol valve to the pumpstation. slides. This is achieved by using the guns from ground
level, in a step cutting procedure whereby the top of
3.4. Reclamation technique the dam face is cut down to remove the top of the face.
The top quarter and second quarters are progressively
Where possible, dams should be reclaimed in a down cut away before cutting the bottom levels.
slope manner starting from a point furthest from the The benching technique essentially removes the dam
pumpstation and advancing down the slope until the re- in layers progressively from the top level working down
source is exhausted. Experience has shown that a slope with the layers being up to 5 m in height. The guns thus
of 1 in 150 will provide adequate slime flow without set- are located on the top surface of the dam and moved to
tling of coarse particles. the lower bench levels as the reclamation proceeds.
Well-cut launders prevent the slime from ‘‘meander- The benching technique, which uses lighter piping
ing’’ which creates slime build up which can become a (easily joined) and hand manoeuvrable guns, is more la-
future clean-up requirement. These measures, together bour intensive and has poorer working conditions com-
with ongoing ground clean-up (i.e. while reclamation pared to the full-face operation. Grade may also be
is underway) to the required closure standard have been more variable due different layers of the dam having dif-
shown to minimise final site rehabilitation costs. ferent grades. On the benching system there will tend to
This ongoing clean-up approach also ensures that the be more faces in operation at any given time compared
low density stream associated with clean-up activities to a site operating on full-face which makes manage-
can be carried by the main dam reclamation tonnage, ment, planning and storm water control more compli-
thus minimising adverse production impact towards cated. Benching tends to progressively reduce the
the end of the operation. Should this ongoing clean-up overall height of the resource whereas full-face opera-
philosophy not be followed, then final clean-up will in- tions progressively reduce the area of the resource.
volve either low density/tonnage reclamation which Ground clean-up activities, which rely on the release
may be inconsistent with the pump/piping capacity or of cleared land, are therefore more easily managed in
mechanical scraping and piling of material into sizable a full-face reclamation operation. Benching will result
reclamation piles both of which are costly exercises. in a low face/large area operation at the end of the pro-
Other advantages are that equipment can be removed ject life, which can impact on both production and costs.
for re-use installation at other sites (it does not have A further consideration in reclamation methodology
to be left behind for future clean-up) and that rain water is whether stability problems exist on the dam. If the
falling on a cleaned site can be allowed to run naturally dam has stability problems full-face monitoring may
off site with no adverse affect on production. prove to be too hazardous and the benching technique
Rain water falling on an operating site will be classi- should then be employed. In all other cases full-face rec-
fied as process water and hence not suitable for release lamation is the preferred reclamation method.
into the surrounding environment and attempts should
be made to contain this in paddocked areas for evapora-
tion or controlled release to minimise its effect on 4. Reclamation process flow
production.
Two hydraulic reclamation methods are commonly 4.1. Monitor guns
used, namely full-face or step cutting (benching). Full-
face reclamation employs guns remotely operated from The guns deliver a high-pressure water jet which is di-
a cabin distant from the gun position. Benching uses rected at this working slimes dam face. The guns are up
guns manually operated by a person standing at the to 150 mm diameter fitted with 40–60 mm nozzles and
gun who directs the stream of water. the guns operate at a pressure of 20–30 Bar. The nozzle
On full-face reclamation, use of remotely controlled diameter may be adjusted as appropriate for the mate-
guns can result in labour savings compared to benching rial and tonnage being reclaimed.
818 A. Muir et al. / Minerals Engineering 18 (2005) 811–824

4.2. Screening of the concrete in areas where the lining application is


uneven). At 1.9 m/s pumping velocity, 10 mm thick mild
Finger screens are installed in the earth launders to steel should provide a life of up to 15 years depending on
entrap and remove refuse, vegetation and other trash the size distribution and abrasiveness of the material
up to 50 mm in size. Where possible these should be in- being pumped. The life of a rubberlined pipe is approx-
stalled in line with the flow in such a way as to introduce imately three times the life of a steel pipe if pumping
a degree of self-cleaning. The slurry also flows over slime in a similar situation. When pumping slime con-
vibrating screens to remove +2 mm material at the taining more than 10% sand a rubber lined pipe must
pumpstation (it may be necessary to pump onto this be used. The cost of rubberlined pipeline is typically
screen). This removes coarse material which may dam- 50% higher for a 25 bar duty pipe and 37% more for
age the pumps, pipes and valves in the slurry delivery 10 bar duty pipe when compared to steel pipe.
system. As much surface vegetation, refuse and physical Rubber lined pipes should also be used in situations
contaminants as possible should be mechanically re- where the pH of the reclaimed slime is below 5, where
moved prior to reclamation monitoring to avoid launder metals capable of precipitating and forming micro gal-
chokes and screen overloading. vanic cells on the pipe wall exist or if sulphur reducing
bacteria could be a problem.
4.3. Pumpstations Pipes should not be placed on steel or concrete
plinths since movement of the pipe on the plinth (due
The transfer pumpstation at the reclamation site will to expansion and contraction) causes abrasion wear at
involve multi-stage slurry pumps, which pump the slurry the plinth to pipe contact point resulting in failure. If
to the treatment plant via an overland delivery pipeline. plinths must be used, timber or some other soft surface
Intermediate booster pumpstations may be required if should be used although it is recommended that pipes
the distance to the plant is very long. should just be placed on the ground where possible.
These pumpstations also incorporate the water Pipes crossing sensitive areas such as roads, railway
pumps, which supply the high-pressure water for moni- lines, power lines, other pipes such as gas or potable
toring use. The pumpstations normally have an operat- water, water courses, wetlands, parks and so on should
ing set and standby set of both slurry and water pumps. be rubber lined to minimise the potential for failure. In
Satellite pumpstations may be required to remove such areas it is also recommended that provision be
material from areas on the dam, which are lower than made for easy removal of the pipe and space provided
the transfer pumpstation. These could be located ‘‘in- for standby piping so that minimum production inter-
dam’’ or on the perimeter depending on the topography ruption is caused by any pipe failures. Pipes crossing
of the site. The operation of the satellite station involves or running parallel to railway lines or marshy or wet
the creation of a small pumping sump, which simply areas have to be protected against stray electrical cur-
transfers the slurry to the main pumpstation. rents by electrical bonding and cathodic protection
As with the main pumpstation, it is normal to install systems.
static screens in the feed launders to minimise the chok- Pipelines should have test sections fitted in them,
ing of pipelines and pumps from the satellite to the main which can be periodically removed for inspection for
pumpstation. Whilst satellite stations are effective in signs of corrosion, erosion and scaling. Ultrasonic thick-
removing small amounts of material from difficult areas ness testing should be regularly conducted to ensure pipe
at low capital cost it is generally labour intensive. integrity is being maintained.
A vertical spindle pump is the preferred choice for sa- Although pipe lengths are normally welded together
tellite pumping as it is simple to install and can handle rather than flanged, occasional flanging is necessary on
large volumes of solids. A tank satellite where the pump- bends and at isolation points. When a pipe is opened
ing system is placed inside a tank which is then placed in at flanges on a long pipeline section it will spring apart
the catchment is an option which has proved successful due to the inherent stress in the pipe. The provision of
over the years at Ergo. distance pieces of various lengths with flanges will facil-
itate the reconnection of opened pipes.
4.4. Pipelines Pressure control and pressure release valves should be
installed in the pumpstations on monitor water pipelines
Slime should be pumped at a velocity of 1.9 m/s or when high pressure (potential energy) could pose a dan-
lower in an unlined steel pipe, as this has been shown ger to workers in the area. The use of gate valves rather
to give an optimal balance between tonnage throughput than ball or butterfly valves should be considered, as
and pipe wear. At velocities greater than 2 m/s it is rec- they are more effective in controlling pressure in the line.
ommended that a rubber-lined pipe should be used (con- Depending on the alkalinity and scaling potential of
crete lining has been used at Ergo but is not the monitor water, it may prove necessary to add anti-
recommended for long life operations due to erosion scalent into the monitor water system. This is stage in-
A. Muir et al. / Minerals Engineering 18 (2005) 811–824 819

jected into the water pipeline with a total addition of 5. Sand reclamation and milling
about 4 ppm usually proving sufficient.
Both the main slurry and monitor water pipelines 5.1. Hydraulic reclamation
should, in any event, incorporate a facility to allow pig-
ging on a regular basis to remove scale build up and re- Hydraulic re-mining of sand can be done and is prac-
tain capacity without major impact on production. ticed at a number of operations. It is not however the fa-
voured option for sand due to the fact that the coarse
4.5. Water balance nature of the material requires steep launder slopes in
the order of one in fifty to ensure adequate slurry veloc-
The water balance on a slimes reclamation circuit ity to prevent the particles from settling out and choking
employing hydraulic re-mining needs constant aware- the launders. This results in extremely deep launders
ness, monitoring and control. Consistent water inputs being required over the length of the deposit and since
in terms of quantity and quality are required for the this is not really practical, mobile satellite pumpstations
monitoring feed system to ensure steady pressures are are required to follow the moving face and maintain an
maintained at the face. acceptable launder depth or pump the slurry directly to
Since the water volumes involved are large on a high the transfer pumpstation.
tonnage operation it is essential to re-use water in order The guns also need to be close to the face being re-
to reduce the consumption of expensive potable water claimed. This can all be done but it results in a cumber-
and of course to avoid process water accumulation some, mechanically complex and labour intensive
build-up which can lead to environmental problems. operation. The preferred route of sand reclamation is
Re-circulated water originates from the plant thickener therefore by mechanical means.
overflow and from the return water system at the final
deposition site. Rainwater falling on reclamation sites 5.2. Mechanical reclamation of sand
and tailings dam basins is also captured and added to
the process water system. It is therefore necessary to Bulldozers and front-end loaders remove the sand
monitor and control external water addition into the cir- from the dump and load it on to a system of conveyor
cuit to avoid build-up of the total water inventory. The belts and transfer chutes. These deliver the dry sand to
major water loss mechanism is the water retention a screening and slurrying section, which is where the
within the settled bed in the final tailings dam. coarse oversize and grit is removed in a multi-stage
Some of the process water could contain minor resid- screening process (normally wet screening for the finer
ual levels of cyanide, which could depress flotation re- screen sizes).
sponse, and this must be allowed for during the This slurried sand is then pumped to the milling
flowsheet design. plant. The slurry would be pumped in rubber lined steel
As previously noted, due to the minor amounts of pipes at a density of 1.45–1.55 and a velocity of 2.1–
cyanide in the process water and the precipitated nature 2.4 m/s. The slurry can be pumped for considerable dis-
of some of the gold in the resource, reclaimed slime will tance if required.
contain appreciable levels (up to 20%) of dissolved gold
before it even reaches the processing facility. This needs 5.3. Milling of sand
to be measured and reflected in the gold accounting sys-
tem with care taken that recirculating soluble gold is not Location of the milling plant will be project specific
double accounted. and is dependent on the geographic layout of the project
It has been demonstrated that leaching continues resources in relation to available milling infrastructure
(at low levels) on the residues during pumping to and utilities. The milling section could be located at
the dam and on the beach. On a large operation it the main processing facility or at a remote location
may be justified to install separate carbon columns depending on the most convenient and cost effective
on the tailings dam return water system to recover arrangement. The milling circuit would typically employ
any residual dissolved gold present. The carbon from overflow ball mills operating at about 70% of critical
these columns simply becomes part of the overall speed with a grinding media of 50 mm balls. Once the
CIL carbon circuit. sand has been milled it becomes slime and can be mixed
It should be noted that it is not possible to use a car- with other slime for processing.
bon column system on the thickener overflow if unstable The slurried sand is pumped from a stock tank into
calcium sulphate salts are present as these scale up the the milling circuit primary sump from where it is
column and carbon in just a few hours. This does not pumped to the primary cyclone classification circuit.
happen on the tailings dam return as the calcium sul- The underflow gravitates to the mill and the overflow
phate has stabilised due to retention time on the dam reports to the secondary cyclone. Underflow from the
and does not precipitate out. secondary cyclone reports back to the primary sump
820 A. Muir et al. / Minerals Engineering 18 (2005) 811–824

for re-circulation together with the mill discharge and the incoming water or thickener overflow directly to
new feed, while the overflow discharges into the second- the tailings dam for storage until the reclamation site
ary sump. has recovered and this facility should be incorporated
From the secondary sump, the slurry is pumped to a into the flowsheet design in areas where high rainfall
de-watering cyclone cluster which is designed to dis- events can be anticipated.
charge a consistent underflow product at a RD 1.40 The preferred route for the slime treatment is typi-
which is then pumped to the processing plant. De-water- cally a ‘‘Carbon in Leach’’ (CIL) circuit. This is a result
ing cyclone overflow reports back to the primary sump of the high volume treatment not being really suited to a
to supplement the dilution water added at this point. pump cell type of operation and the low grade probably
The use of de-watering cyclones provides an underflow not justifying the increased capital cost of a separate
density suitable for downstream treatment processes leach and absorption section. Also the low solution gold
and enables return of water via the overflow back into tenor and the possibility of preg robbing by carbon spe-
the milling circuit. cies in the slime or other material absorbents is such that
presentation to active carbon as soon as possible is likely
to be advantageous.
6. Metallurgical treatment As the slime has been previously processed, gold
recovery is lower than with newly mined ore and is liable
6.1. Slime treatment with no pyrite recovery to be in the range of 50–80% dissolution and adsorption
of about 95%. Much of the gold recovery is essentially
The low grade of the incoming slime will necessitate a from the original soluble loss (from old filter plant oper-
high volume throughput to provide economy of scale ations), which will have precipitated as a gold cyanide
and enhance profitability. A relatively short leach resi- species on the material surface and is now re-dissolved,
dence time in the order of 8 h will probably provide an leachable gold left in residue due to historical processing
optimum return on the project. inefficiencies and a release of previously occluded gold
The reclaimed slime would normally be received at due to weathering and ageing of the material. This
the treatment facility at a relative density (RD) of recovery figure will be determined during the testwork
1.40–1.50. However reclamation methods, stop/start phase.
periods, flushing of lines for maintenance, ‘‘wetness’’ Although ‘‘preg robbing’’ is evaluated during the test-
of in situ slime, low monitor water pressure, flaring of work phase, it should be appreciated that carbonaceous
the water jets due to nozzle wear, surface clean-up oper- species present, such as old boiler ash, are not liable to
ations, and in particular heavy rainfall, can all result in a be very active, may well be already loaded to their full
much lower incoming density to be achieved (especially capability with gold and will in all probability not be
on a short term basis where large fluctuations in the able to compete with the active carbon. A leach response
incoming density can arise). similar to the laboratory testwork is liable to be
In the event of heavy rainfall the reclamation site may achieved in practice unless fine carbon has been gener-
be flooded and, as a result only water or very dilute ated during milling for example.
slime would be pumped to the plant while recovering Reagent consumption will have been derived during
the reclamation site. It should be remembered that rain- testwork. Experience indicates that a cyanide tenor of
water falling on to an uncleaned reclamation site is con- about 60 ppm should be maintained throughout to en-
sidered to be contaminated and must be incorporated sure optimum leach efficiency although different ores
into the process water system of the operation. may require more cyanide to drive the leach kinetics if
Due to this variability in incoming density and ton- residence time is particularly short. Oxygen addition to
nage fluctuation for other reasons, it is strongly recom- every tank or alternate tanks is considered essential
mended that conventional thickeners (not high rate) be and should preferably maintain dissolved oxygen levels
installed to provide a degree of surge and storage flexi- of 15–20 ppm and not less than 8 ppm. Oxygen levels
bility between the reclamation operations and the pro- higher than 20 ppm are not recommended as this may
cessing plant. Starting and stopping of the reclamation result in increased cyanide consumption. As a low leach
system is a long and complex procedure with some de- time is the likely scenario, every effort should be made to
gree of risk (most pump/pipeline failures occur at start raise the oxygen to an acceptable level at the start of
up) and it is inappropriate to design the system in such leaching and this may involve injection of oxygen prior
a way that every downstream problem interrupts the to cyanide addition. The use of oxygen to consume
reclamation process. The thickeners also ensure a con- cyanicides should also be explored as a method of reduc-
sistent feed stream in terms of volume and density to ing reagent costs.
the treatment plant, which enables better process control For example, the conversion of ferrous species to fer-
and usually facilitates efficiency optimisation. During ric (from a cyanide consumer to a non-consumer) has
extreme rainfall/flooding it may be necessary to pump proved successful although this is very pH dependent
A. Muir et al. / Minerals Engineering 18 (2005) 811–824 821

(best pH around 5–6) and is influenced by oxygen solu- The leached slurry passes over linear screens to scav-
bility and ferrous solubility. enge any coarse carbon escaping from the circuit and the
Oxygen injection direct into the overland transfer screen undersize is pumped to the tailings disposal site.
pipelines can be employed to counteract cyanicides Water is re-cycled from the tailings storage facility water
and enable the CIL leach to attain the desired oxygen dams to the reclamation sites for use as monitor water.
in solution as quickly as possible. Care however must The loaded carbon is pumped to washing screens,
be exercised to ensure that the oxygen concentration at acid washed to remove calcium carbonate, eluted and
the injection point and in the pipeline does not go too regenerated before being returned to the adsorption cir-
high and cause accelerated corrosion when mild steel cuit. Due to the potential for organic fouling of the car-
pipelines are being used. bon, due to rotting vegetation, historical dumping of
Leach residence time of about 7–8 h with oxygen organic waste on the site currently being reclaimed, die-
addition is normally sufficient since the available gold sel spillage from machinery on the sites, the presence of
is normally in a form, which dissolves easily. The incre- flotation reagents and so on, it is strongly recommended
mental dissolution achieved after this time is liable to be that regeneration capacity employs rotary kilns correctly
inadequate to support the capital for the equipment in- sized to ensure regeneration of all eluted carbon (i.e. no
volved and the solution gold tenor will be so low that it bypassing), is used for thermal regeneration.
will no longer provide a strong driving force to the Organic species in the slime will be adsorbed on the
adsorption kinetics. carbon and organic loading on carbon can exceed 6%.
A typical CIL slime circuit will comprise de-gritting Whilst this does not appear to impair the gold loading
via linear screens, with the de-gritted slurry being capacity of carbon dramatically (due to the large pore
pumped to the CIL tanks. The first of the tanks could area) it does make it essential to thermally regenerate
incorporate a desanding facility to prevent near size grit the carbon with every elution cycle. If this is not done,
build up in the system with the recirculation of this back organic build up and carbon surface coating will eventu-
to the linear screens. ally decrease adsorption efficiency. Where flotation re-
The linear screen oversize is re-pulped and pumped to agents are present they will be loaded onto the carbon
join the CIL tailings prior to disposal to the tailings stor- and experience has shown that the resultant gases re-
age facility. The CIL tanks will be mechanically agi- leased during thermal activation can leach nickel from
tated, incorporate an oxygen addition system and be the kiln steel and cause premature shell failure. Rotary
equipped with mechanically swept screens for carbon kilns are therefore better suited to this application as
retention. This plant section should include a slurry they offer rapid exhaust of internal gases.
mass flow calibration facility with this being essential The carbon loading is liable to be much lower than
in a slimes circuit due to the inherent difficulty in ton- achieved in high-grade ore circuits and could be as low
nage accounting on a reclamation operation. as 200 g/t. As a result, the eluate grade will also be

TYPICAL RECLAMATION FLOW-SHEET

SLIMES
DAM
MONITOR
GUN
Slurry

IN-LAUNDER
FINGER SCREENS
± 100 mm

BOOSTER
PUMPS TRASH
SCREENS Oversize
DUMP

Undersize

PUMPS

MONITOR WATER FROM


PROCESS PLANT RECIRCULATION PROCESS PLANT
OR OTHER SOURCES

C o m p il e d By : S G l en s o r

Fig. 2. Simplified flowsheet for slimes reclamation.


822 A. Muir et al. / Minerals Engineering 18 (2005) 811–824

BASIC FLOW-SHEET OF RESIDUE TREATMENT

RECLAMATION RECLAMATION
OF & MILLING OF
SLIMES DAMS SAND DUMPS

FLOTATION Pyrite ACID


Possible
PLANT PLANT

Tails
Monitor Water O/F
THICKENERS
Calcine SULPHURIC
U/F ACID AND OLEUM
Calcine Residue

CARBON CARBON
Eluate GOLD
RETURNED TO IN LEACH
PLANT
CIL PLANT PLANT
Residue

CARBON Water TAILINGS


COLUMN DAM

WATER RETURNED GOLD


TO RECLAMATION BULLION
AND PROCESS
PLANT

Co mpiled By: S G len sor

Fig. 3. Simplified flowsheet for sand reclamation and milling.

SIMPLIFIED FLOW-SHEET OF SANDS MILLING


SANDS RECLAMATION SAND MILLING CIRCUIT
DUMP
ROCK O/F
STOCKPILE Oversize
100mm STATIC Secondar y
GRIZZLEY Cyclone O/F
Undersize
MAKE-UP Primary
Cyclone
WATER ROCK U/F
Oversize SCREEN
Undersize

PROCESS SURGE
WATER TANK BIN STOCK U/F
MILL
TANK
LIME
Dilution
STORAGE TANK Water

TRASH Oversize PRIMARY SECONDARY


TRASH SCREEN
STOCKPILE SUMP SUMP
Undersize O/F
Oversize
Oversize LINEAR
DE-WATERING De-watering
SCREEN SCREEN Cyclone
Undersize

WATER RETURNED PUMPED TO PROCESS PL ANT


U/F
TO CIRCUIT

Compiled By: S G lensor

Fig. 4. Simplified flowsheet for residue retreatment.


A. Muir et al. / Minerals Engineering 18 (2005) 811–824 823

low and electrowinning from the eluate may be imprac- In the flotation circuit, incoming slurry should pass
tical due to competition from other metallic species. In through storage tanks to enable surge capacity,
this event, standard zinc precipitation will be the pre- density adjustment, pH and reagent conditioning as
ferred final gold recovery route. well as to ensure a constant volume of slime is
pumped to the flotation cells to facilitate flotation
6.2. Slime treatment with pyrite recovery optimisation. The system should also incorporate a
mass flow calibration system. In the event of very
If the resource material contains significant pyrite low incoming density, or low sulphur levels, a facility
(around 0.8–1% sulphide sulphur) some of the gold is to bypass the feed to the CIL feed thickeners should
liable to be associated with the pyrite. If this pyritic gold exist.
is simply allowed to follow a slime processing circuit as The flotation tails would report to the CIL feed thick-
described above it will report directly to the CIL plant eners with the underflow being directed to the CIL plant
where two undesirable impacts will arise. and the overflow water being re-cycled to the reclama-
Firstly, pyrite has a high cyanide demand and will in- tion system.
crease the overall cyanide consumption of the circuit.
Secondly, gold in pyrite tends to be slow leaching and, 6.3. Sand treatment
due to the short residence time available, the recovery
of the pyritic gold component will be lower than that Obviously the major difference between sand and
achieved for the remainder of the material (often in slime is the coarser particle size of sand. As previously
the range 30–35%). noted up to about 10% sand can be ‘‘carried’’ by slime
Consideration must therefore be given to introducing and tolerated in the circuit. Sand percentages above
a flotation process to remove the pyrite for separate this will cause accelerated erosion of mild steel pipes/
treatment and this option should be evaluated during valves and the grit which will settle out of suspension
the metallurgical testwork programme. Flotation of in the CIL tanks will result in reduced residence time
material of less than 0.8% sulphide sulphur is not gener- due to volume loss (grit build up) in the CIL tanks
ally viable. as well as the necessity to take tanks out of circuit
The pyrite concentrate grade, which can be achieved for de-gritting.
during flotation, may dictate the subsequent pyrite pro- It follows therefore that the sand must be milled to
cessing step. If the pyrite concentrate sulphur grade is enable subsequent processing. Milling to about 45–
less than 25% the pyrite will simply be cyanide leached, 55% passing 74 lm is usually adequate to overcome
followed by solid/liquid separation, solution clarifica- the erosion and settling problems. The extent of milling
tion and recovery of gold from solution. Leach resi- to be used (i.e. to what degree of fineness) will be dic-
dence time of at least 18 h will be required and tated by mill throughput rates for the various degrees
cyanide consumption may be as high as 7.0 kg/t. Gold of fineness and the incremental change in recovery that
recovery from this processing option will be about 60– can be achieved at these different grind levels. Consider-
70%. ing the relatively low headgrade of most sand deposits
If the concentrate sulphur grade is at least 30% sul- and the fact that milling is a costly process, testwork
phur (or can be upgraded to this level) the potential of must establish at which point finer grinding does not
installing a pyrite burning sulphuric acid plant to roast produce any additional economic benefit. Obviously
the pyrite and generate revenue from the acid should recovery will improve with finer grind, but the reduction
be evaluated. The calcine (roasted pyrite) would then in throughput or increase in cost required to achieve this
undergo cyanide leaching, solid/liquid separation, solu- may not be justified by the small incremental gold recov-
tion clarification and recovery of gold from solution. ery benefit.
A leach residence time of about 18 h will be required Following size reduction, the processing of the sand
and cyanide consumption will be lower at about 1.5– will be the same as outlined for slime and the same con-
2.0 kg/t. Gold recovery from this circuit will be in the re- siderations related to flotation should be applied to sul-
gion of 90%. These options must be evaluated during the phur bearing sand.
pre-feasibility study during which an evaluation of all
factors, including the sulphuric acid market, will illus-
trate any benefit from this circuit. 7. Environmental rehabilitation
In both the pyrite and calcine processing circuits a
carbon circuit incorporating pump cells could replace It is beyond the scope of this paper to detail all of the
the solid/liquid separation recovery method. Ultra environmental rehabilitation aspects required for even-
fine milling can also be considered for pyrite grades tual mine closure, however the cost, complexity and im-
below 25% but this will depend on the fineness of pact on production of final clean-up of remnant material
the gold. on sites should not be underestimated.
824 A. Muir et al. / Minerals Engineering 18 (2005) 811–824

8. Conclusion ‘‘environmentally unfriendly’’ dumps (and their associ-


ated long-term liability) to a more modern facility.
Key practical aspects to consider when evaluating the
treatment of a gold residue deposit have been presented.
Whilst a deliberate attempt has been made to keep the Appendix A. Process flowsheets
methodologies as generic as possible, it should be noted
that often a residue deposit or even a portion of a depos- Simplified flowsheets for slimes reclamation (Fig. 2),
it displays unique characteristics necessitating unique sand reclamation and milling (Fig. 3) and residue treat-
solutions. Cognisance of this need to be taken by build- ment (Fig. 4) are presented.
ing flexibility into the reclamation and processing stages
where possible.
Accepting the potential risk since the cost of mining
and size reduction (partial in the case of sand) has al- Further readings
ready been incurred these residue materials normally
represent a ‘‘cheap’’ source of gold especially when re- Stanley, G.G., 1987. The Extractive Metallurgy of Gold in South
Africa. South African Institute of Mining and Metallurgy Publi-
claimed as a tonnage makeup to fill up excess treatment
cations, Johannesburg, Chapter 12.
capacity within an existing processing facility. Van Huyssteen, J., 2004. The unique challenges associated with the
In addition other benefits may accrue such as the re- closure of a surface operation. Mine Metallurgical ManagerÕs
lease of land for urban development or relocation of Association of South Africa.

You might also like