Professional Documents
Culture Documents
Q1.
CA AB4 40D 2C 96A A9C C87 7873 316 62B 797 775C C39 9DD DCA AB4 40D 2C
9 8 2 7 7
N.B.:
B 0D 2C 6 9 87 7 16 B 97 5 3 D D C B 0D 2C 96
Units
Week
B4 40D 2C 96A A9C C87 873 316 2B7 797 75C C39 9DD CA AB4 40D 2C 96A A9C
2 9 8 2 7 D 2 9
Activity
40 0D2 C96 6A9 9C8 8787 731 162B B79 9775 5C3 39D DC CAB B40 0D2 C96 6A9 9C8 8787
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
below:
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
6A 9C 878 73 162 B7 977 5C 39 D CA B4 0D C9 6A 9C 878 73 162 B7
as follows:
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
1
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C
100
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
compulsory.
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
Preceding Activity
Requirements:
Duration (in hours)
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39 DD CA B4
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
80
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D DC AB 40 D2 C9 6A
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC AB 40 D2 C9 6A9 9C8
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC AB 40 D2 C96 6A9 C8 787
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
2
A
6A 9C 878 73 162 B7 977 5C 39 D CA B4 0D C9 6A 9C 878 73 162 B7
3
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
110
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C
-
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
1
C
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
1
4
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
115
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D DC AB 40 D2 C9 6A
4
A
D
MMS - IV
Time :3 Hours
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC AB 40 D2 C96 6A9 C8 787
8
E
5
University Examination
105
Q1 of section – I is compulsory, and it carries 9 marks.
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 5
F
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
Pertech Computers Limited Pune
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
7873162B79775C39DDCAB40D2C96A9C8
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
3
C
G
6
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
110
9th week. The initial forecast for 1st week was 15 units and α= 0.2.
Section – II is having 30 MCQs for one mark each is compulsory.
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
1
D
H
time (EFT), Latest start time (EST) and Latest finishing time (LFT).
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC AB 40 D2 C96 6A9 C8 787
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
I
7
5
125
E, G
F
Attempt any three questions out of four questions, and each one carries 7 marks.
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C
8
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39
120
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
3
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
K
(9 marks)
Max Marks:60
Pertech computers limited is having a small assembly plant in Pune where they assemble
Question paper is having two sections carries 30 marks each and both the sections are
personal computers through nine interlinked activities. The time duration for which is given
Q2. The weekly demand for units manufactured by the Acme water Purifier Company has been
c. Calculate and tabulate for each activity: Earliest start time (EST), Earliest finishing
SET – 2
(3 marks)
(1 mark)
(1 mark)
(7 marks)
e. Find total float, free float, independent float, interfering float for each activity. (2 marks)
(2 marks)
Use the exponential smoothing method to forecast the number of units from 2nd week to
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D
H, I, J
SV
CV
SPI
CPI
ETC
40 0D2 C96 6A9 9C8 8787 731 162B B79 9775 5C3 39D DC CAB B40 0D2 C96 6A9 9C8 8787
TCPI
A (in ₹)
B (in ₹)
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
Projects
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
6A 9C 878 73 162 B7 977 5C 39 D CA B4 0D C9 6A 9C 878 73 162 B7
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C
Critical Ratio
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39 DD CA B4
1
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
b. Project Crashing
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
1,50,000
1,00,000
a. Project Life Cycle
Discount Factor
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D DC AB 40 D2 C9 6A
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC AB 40 D2 C9 6A 9C8
Particulars
6A 9C 878 73 162 B7 977 5C 39 D CA B4 0D C9 6A 9C 878 73 162 B7
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C
2
above information find the following
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
150,000
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
2,00,000
c. Work Breakdown Structure (WBS)
2
Q4. Write short note on any two of the following:
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D DC AB 40 D2 C9 6A
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC AB 40 D2 C9 6A 9C8
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC AB 40 D2 C96 6A9 9C8 787
3
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
Years
5
A
6A 9C 878 73 162 B7 977 5C 39 D CA B4 0D C9 6A 9C 878 73 162 B7
2,00,000
2,00,000
10%
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
25,000/-
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C
6,00,000/-
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
7873162B79775C39DDCAB40D2C96A9C8
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39 DD CA B4
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
Project
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
4
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D DC AB 40 D2 C9 6A
1,50,000
1,00,000
5
B
5
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C
1,00,000
1,50,000
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
(3 ½ marks)
(3 ½ marks)
(3 ½ marks)
Q5. Compare project A and B using the given data. Calculate NPV and PI for both the project
(1 mark)
(1 mark)
this project is budgeted at ₹9,37,500/- per month. Six months into the project you find that
Q3. You have planned for a project to write a software application to take one year. The cost on
(1 mark)
(7 marks)
(1 mark)
(1 mark)
(1 mark)
(1 mark)
(7 Marks)
the software application is 50% completed and you have spent ₹52,50,000/-. Based on
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D D
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC
D2 C9 A C 78 31 62 7 77 C 9D D A
C9 6A 9C 878 73 62 B7 977 5C 39D D CA
6A 9C 878 73 162 B7 977 5C 39 D CA B
9C 87 73 162 B7 97 5C 39 DD CA B4
87 873 16 B7 97 75C 39 DD CA B4 0
87 16 2B 97 75 3 DD C B 0D
31 2 79 7 C3 9D C AB 40
D C
97 775C C39 9DD DCA AB4 40D 2C 96A A9C C87
77 75C 39D DDC CA B40 0D2 2C9 96A 9C8 878 8731
5 39 D A B D C 6 9C 7 7 6
5C C39 DD CA B4 40D 2C9 96A A9C 878 873 3162 2B7
D 2
C3 39D DC CAB B40 0D2 C96 6A9 9C8 8787 731 162B B79 9775
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3
9D DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C3 9D
6 9 7 B 5
DD DCA AB 40D D2C C96 A9 C87 787 316 62B 797 775 C39 9DD DCA
4 9 A C 8 3 2 7 7 C
DC CAB B40 0D2 2C9 6A 9C8 878 731 162 B79 977 5C 39D DDC CAB B40
D C 6 9 7 B 5 3 D
CA AB4 40D 2C 96A A9C C87 7873 316 62B 797 775C C39 9DD DCA AB4 40D 2C
9 8 2 7 7 D
B 0D 2C 6 9 87 7 16 B 97 5 3 D C B 0D 2C 96
B4 40D 2C 96A A9C C87 873 316 2B7 797 75C C39 9DD CA AB4 40D 2C 96A A9C
2 9 8 2 7 D 2 9
D) 5
12%
10%
40 0D2 C96 6A9 9C8 8787 731 162B B79 9775 5C3 39D DC CAB B40 0D2 C96 6A9 9C8 8787
A) 3/8
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
B) 20/6
C) 11/6
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
PV factor @
C) Crash cost
B) Crash time
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
D) Crash Slope
A) Normal cost
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39 DD CA B4
1
D) Sub-contracting
A) Reducing quality
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
B) Working overtime
0.892
0.909
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
C) Optimality is reached
D) Project is justifiable
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D DC AB 40 D2 C9 6A
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC AB 40 D2 C9 6A 9C8
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC AB 40 D2 C96 6A9 9C8 787
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
0.797
0.826
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
3
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D DC AB 40 D2 C9 6A
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC AB 40 D2 C9 6A 9C8
Section – II
7873162B79775C39DDCAB40D2C96A9C8
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39 DD CA B4
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
4
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
Q.1.Profitability index (PI) decision rule states that if PI < 1, then -------------
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
6A 9C 878 73 162 B7 977 5C 39 D CA B4 0D C9 6A 9C 878 73 162 B7
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
Q.5.For an activity in a project, optimistic time is 2 days; most likely time is 3 days and
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75
5
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C
0.567
0.621
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C
Q.2.Which of the following activities would NOT be an appropriate way of crashing a project?
C) Negative
A) Tax Effect
A) Free Float
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
D) Total Float
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
B) Independent
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39 DD CA B4
B) Interfering Float
Net Present Value will be
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
C) Independent Float
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D DC AB 40 D2 C9 6A
B) Time Value of Money
4
Q.10.Which activity is to be selected for crashing
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D DC AB 40 D2 C9 6A
7873162B79775C39DDCAB40D2C96A9C8
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
Q.7. Which of the following is not incorporated in capital budgeting?
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39 DD CA B4
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D DC AB 40 D2 C9 6A
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC AB 40 D2 C9 6A 9C8
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC AB 40 D2 C96 6A9 9C8 787
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
6A 9C 878 73 162 B7 977 5C 39 D CA B4 0D C9 6A 9C 878 73 162 B7
C) The activity with the lowest cost irrespective of it being on Critical path or no
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
D) The activity with the highest cost irrespective of it being on Critical path or no
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
Q.6. A project whose cash flows are more than the capital invested for Rate of Return then the
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D D
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC
D2 C9 A C 78 31 62 7 77 C 9D D A
C9 6A 9C 878 73 62 B7 977 5C 39D D CA
6A 9C 878 73 162 B7 977 5C 39 D CA B
9C 87 73 162 B7 97 5C 39 DD CA B4
87 873 16 B7 97 75C 39 DD CA B4 0
87 16 2B 97 75 3 DD C B 0D
31 2 79 7 C3 9D C AB 40
D C
97 775C C39 9DD DCA AB4 40D 2C 96A A9C C87
77 75C 39D DDC CA B40 0D2 2C9 96A 9C8 878 8731
5 39 D A B D C 6 9C 7 7 6
5C C39 DD CA B4 40D 2C9 96A A9C 878 873 3162 2B7
D 2
C3 39D DC CAB B40 0D2 C96 6A9 9C8 8787 731 162B B79 9775
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3
9D DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C3 9D
6 9 7 B 5
DD DCA AB 40D D2C C96 A9 C87 787 316 62B 797 775 C39 9DD DCA
4 9 A C 8 3 2 7 7 C
DC CAB B40 0D2 2C9 6A 9C8 878 731 162 B79 977 5C 39D DDC CAB B40
D C 6 9 7 B 5 3 D
CA AB4 40D 2C 96A A9C C87 7873 316 62B 797 775C C39 9DD DCA AB4 40D 2C
9 8 2 7 7 D
B 0D 2C 6 9 87 7 16 B 97 5 3 D C B 0D 2C 96
B4 40D 2C 96A A9C C87 873 316 2B7 797 75C C39 9DD CA AB4 40D 2C 96A A9C
2 9 8 2 7 D 2 9
40 0D2 C96 6A9 9C8 8787 731 162B B79 9775 5C3 39D DC CAB B40 0D2 C96 6A9 9C8 8787
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
D) Third
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
B) Lowest
A) Highest
6A 9C 878 73 162 B7 977 5C 39 D CA B4 0D C9 6A 9C 878 73 162 B7
D) A and B
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
on an on-going basis
______ level of the WBS
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D DC AB 40 D2 C9 6A
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC AB 40 D2 C9 6A 9C8
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC AB 40 D2 C96 6A9 9C8 787
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
A) Earliest Start Time - Duration
5
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC AB 40 D2 C96 6A9 9C8 787
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
6A 9C 878 73 162 B7 977 5C 39 D CA B4 0D C9 6A 9C 878 73 162 B7
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
uncertainties, and inflation that could occur during the project
7873162B79775C39DDCAB40D2C96A9C8
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39 DD CA B4
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
Q.14.Determining budget can be best described by which of the following?
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
Q.13.To assist in budget control, it is suggested that an estimate be created at the _____ ____
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D D
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC
D2 C9 A C 78 31 62 7 77 C 9D D A
C9 6A 9C 878 73 62 B7 977 5C 39D D CA
6A 9C 878 73 162 B7 977 5C 39 D CA B
9C 87 73 162 B7 97 5C 39 DD CA B4
87 873 16 B7 97 75C 39 DD CA B4 0
87 16 2B 97 75 3 DD C B 0D
31 2 79 7 C3 9D C AB 40
D C
97 775C C39 9DD DCA AB4 40D 2C 96A A9C C87
77 75C 39D DDC CA B40 0D2 2C9 96A 9C8 878 8731
5 39 D A B D C 6 9C 7 7 6
5C C39 DD CA B4 40D 2C9 96A A9C 878 873 3162 2B7
D 2
C3 39D DC CAB B40 0D2 C96 6A9 9C8 8787 731 162B B79 9775
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3
9D DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C3 9D
6 9 7 B 5
DD DCA AB 40D D2C C96 A9 C87 787 316 62B 797 775 C39 9DD DCA
4 9 A C 8 3 2 7 7 C
DC CAB B40 0D2 2C9 6A 9C8 878 731 162 B79 977 5C 39D DDC CAB B40
D C 6 9 7 B 5 3 D
CA AB4 40D 2C 96A A9C C87 7873 316 62B 797 775C C39 9DD DCA AB4 40D 2C
9 8 2 7 7 D
B 0D 2C 6 9 87 7 16 B 97 5 3 D C B 0D 2C 96
B)
A)
D)
C)
B4 40D 2C 96A A9C C87 873 316 2B7 797 75C C39 9DD CA AB4 40D 2C 96A A9C
2 9 8 2 7 D 2 9
variance?
40 0D2 C96 6A9 9C8 8787 731 162B B79 9775 5C3 39D DC CAB B40 0D2 C96 6A9 9C8 8787
B) -75
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
D) -50
A) 350
C) 400
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
6A 9C 878 73 162 B7 977 5C 39 D CA B4 0D C9 6A 9C 878 73 162 B7
c-a-b-d
a-b-c-d
a-c-b-d
b-c-a-d
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
d) Control Costs
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
B) Cost of Quality
c) Estimate Costs
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
C) Expert Judgment
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39 DD CA B4
A) Cost Aggregation
a) Determine Budget
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
B) Succeeding activities
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D DC AB 40 D2 C9 6A
b) Plan Cost Management
D) Historical Relationships
What is the correct sequence?
6
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
7873162B79775C39DDCAB40D2C96A9C8
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39 DD CA B4
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D DC AB 40 D2 C9 6A
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC AB 40 D2 C9 6A 9C8
Q.16.The Project Cost Management Process comprises the following activities:
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC AB 40 D2 C96 6A9 9C8 787
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
6A 9C 878 73 162 B7 977 5C 39 D CA B4 0D C9 6A 9C 878 73 162 B7
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97
Q.17.The tools and techniques used in the process of Determine Budget includes all but
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
Q.19. If earned value (EV) =350, actual cost (AC) =400, planned value (PV) =325, what is cost
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D D
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC
D2 C9 A C 78 31 62 7 77 C 9D D A
C9 6A 9C 878 73 62 B7 977 5C 39D D CA
6A 9C 878 73 162 B7 977 5C 39 D CA B
9C 87 73 162 B7 97 5C 39 DD CA B4
87 873 16 B7 97 75C 39 DD CA B4 0
87 16 2B 97 75 3 DD C B 0D
31 2 79 7 C3 9D C AB 40
D C
97 775C C39 9DD DCA AB4 40D 2C 96A A9C C87
77 75C 39D DDC CA B40 0D2 2C9 96A 9C8 878 8731
5 39 D A B D C 6 9C 7 7 6
5C C39 DD CA B4 40D 2C9 96A A9C 878 873 3162 2B7
D 2
C3 39D DC CAB B40 0D2 C96 6A9 9C8 8787 731 162B B79 9775
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3
9D DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C3 9D
6 9 7 B 5
DD DCA AB 40D D2C C96 A9 C87 787 316 62B 797 775 C39 9DD DCA
4 9 A C 8 3 2 7 7 C
DC CAB B40 0D2 2C9 6A 9C8 878 731 162 B79 977 5C 39D DDC CAB B40
D C 6 9 7 B 5 3 D
CA AB4 40D 2C 96A A9C C87 7873 316 62B 797 775C C39 9DD DCA AB4 40D 2C
9 8 2 7 7 D
B 0D 2C 6 9 87 7 16 B 97 5 3 D C B 0D 2C 96
B4 40D 2C 96A A9C C87 873 316 2B7 797 75C C39 9DD CA AB4 40D 2C 96A A9C
2 9 8 2 7 D 2 9
C) zero
40 0D2 C96 6A9 9C8 8787 731 162B B79 9775 5C3 39D DC CAB B40 0D2 C96 6A9 9C8 8787
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
D) infinite
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
A) Minimum
6A 9C 878 73 162 B7 977 5C 39 D CA B4 0D C9 6A 9C 878 73 162 B7
B) maximum
B) free float
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
A) Total float
A) Crash time
A) Crash time
B) normal time
B) normal time
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
D) standard time
C) optimistic time
C) optimistic time
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
C) interfering float
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39 DD CA B4
D) independent float
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
7
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
7873162B79775C39DDCAB40D2C96A9C8
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39 DD CA B4
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D DC AB 40 D2 C9 6A
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC AB 40 D2 C9 6A 9C8
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC AB 40 D2 C96 6A9 9C8 787
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
6A 9C 878 73 162 B7 977 5C 39 D CA B4 0D C9 6A 9C 878 73 162 B7
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C
Q.22.The time with which direct cost does not reduce with the increase in time is known as
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
Q.21.The time by which a particular activity can be delayed without affecting the preceding and
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D D
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC
D2 C9 A C 78 31 62 7 77 C 9D D A
C9 6A 9C 878 73 62 B7 977 5C 39D D CA
6A 9C 878 73 162 B7 977 5C 39 D CA B
9C 87 73 162 B7 97 5C 39 DD CA B4
87 873 16 B7 97 75C 39 DD CA B4 0
87 16 2B 97 75 3 DD C B 0D
31 2 79 7 C3 9D C AB 40
D C
97 775C C39 9DD DCA AB4 40D 2C 96A A9C C87
77 75C 39D DDC CA B40 0D2 2C9 96A 9C8 878 8731
5 39 D A B D C 6 9C 7 7 6
5C C39 DD CA B4 40D 2C9 96A A9C 878 873 3162 2B7
D 2
C3 39D DC CAB B40 0D2 C96 6A9 9C8 8787 731 162B B79 9775
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3
9D DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C3 9D
6 9 7 B 5
DD DCA AB 40D D2C C96 A9 C87 787 316 62B 797 775 C39 9DD DCA
4 9 A C 8 3 2 7 7 C
DC CAB B40 0D2 2C9 6A 9C8 878 731 162 B79 977 5C 39D DDC CAB B40
D C 6 9 7 B 5 3 D
CA AB4 40D 2C 96A A9C C87 7873 316 62B 797 775C C39 9DD DCA AB4 40D 2C
9 8 2 7 7 D
B 0D 2C 6 9 87 7 16 B 97 5 3 D C B 0D 2C 96
B4 40D 2C 96A A9C C87 873 316 2B7 797 75C C39 9DD CA AB4 40D 2C 96A A9C
2 9 8 2 7 D 2 9
40 0D2 C96 6A9 9C8 8787 731 162B B79 9775 5C3 39D DC CAB B40 0D2 C96 6A9 9C8 8787
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
B) an event
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39 DD CA B4 Q.29.Interfering float is the difference between
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
8
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
6A 9C 878 73 162 B7 977 5C 39 D CA B4 0D C9 6A 9C 878 73 162 B7
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
7873162B79775C39DDCAB40D2C96A9C8
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C 9D DC
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C 39 D A
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39 DD CA B4
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3 DD C B 0D
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D C AB 40 2
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D DC AB 40 D2 C9
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D DC AB 40 D2 C9 6A
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC AB 40 D2 C9 6A 9C8
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC AB 40 D2 C96 6A9 9C8 787
D2 C9 A C 78 31 62 7 77 C 9D D A 40 D2 C9 A C 78 31
C9 6A 9C 878 73 62 B7 977 5C 39D D CA B4 D2 C9 6A 9C 878 73 62
6A 9C 878 73 162 B7 977 5C 39 D CA B4 0D C9 6A 9C 878 73 162 B7
9C 87 73 162 B7 97 5C 39 DD CA B4 0D 2C 6A 9C 87 73 162 B7 97
87 873 16 B7 97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97
87 16 2B 97 75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75
31 2B 79 75 C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75
62 7 77 C 9D DC A 40 D2 C9 A C 78 31 62 7 77 C
B7 97 5C 39 D A B4 D C 6A 9C 87 73 62 B7 97 5C
97 75C 39 DD CA B4 0D 2C 96A 9C 87 873 16 B7 97 75C 39
75 3 DD C B 0D 2C 96 9 87 87 16 2B 97 75 3
C) crash durations for all the activities along the critical path obtained by taking into account
D) crash durations for all the activities along the critical path obtained by taking into account
C3 9D C AB 40 2 96 A9 C8 87 31 2B 79 75 C3 9D
9D DC AB 40 D2 C9 A C8 78 31 62 79 77 C3 9D
DC AB 40 D2 C9 6A 9C8 78 731 62 B79 77 5C 9D D
AB 40 D2 C9 6A 9C8 78 731 62B B79 77 5C3 39D DC
40 D2 C96 6A9 9C8 787 731 62B 79 775 5C3 9D DC
D2 C9 A C 78 31 62 7 77 C 9D D A
C9 6A 9C 878 73 62 B7 977 5C 39D D CA
6A 9C 878 73 162 B7 977 5C 39 D CA B
9C 87 73 162 B7 97 5C 39 DD CA B4
87 873 16 B7 97 75C 39 DD CA B4 0
87 16 2B 97 75 3 DD C B 0D
31 2 79 7 C3 9D C AB 40