Professional Documents
Culture Documents
Sanitary and
Waste
Services for
Buildings
Fifth Edition
U T T E R W O R T H
E I N E M A N N
First published by The Mitchell Publishing Company Ltcl. ii subsidiary of B.T. Batsford 1079
Second edition I98 I
Third crlition 1986
Fourth edition published by Longinan Scientific and Technical 1'99s
Fifth edition publishcd by Butterworth-Heinemann 2002
Copyright 2002, A.F.E. Wise and J.A. Swaffield. All rights reserved
The right of A.F.E. Wise and J.A. Swaffield to be identilied as the authors of this work
has been asserted in accordance with the Copyright, Designs and
Patents Act 1988
B
Washing 4@50 Urinal (stall, 3 or 6) 65
machine
Kitchen waste 40 Waste disposal unit 50
Bottle trap with removoble disposal unit (commercial)
lower section; the latter
may be of glass, e.g. Note: Where there are more than six urinal stalls in
Econa one range, more than one outlet should be provided
(iii) WCs
Traditionally the W C branch was required to
be not less in diameter than the outgo from the
pan. This was to ensure that a stoppage
occurred in the pan rather than in the pipe-
Length between trap weir and vent, Llm)
work and could, therefore, be more readily
cleared. Washdown pans thus, commonly,
Figure 5.3 Waste pipes from washbasins - max- have an outgo of somewhat less than 100mm
imum slope for various lengths of 32 m m pipe and discharge into 100mm branches. Siphonic
Design of soil and waste pipe installations 69
pans with outgoes perhaps as small as the object of reducing the risk of cross-flow
5 5 4 0 mm may discharge into 75 mm branches. from one branch into another.
In these circumstances, moreover, there is no
danger of full-bore flow in the branch and
hence of self-siphonage with the WC in any Design of combined branches
normal position in relation to the soil stack.
(i) Bath and basin wastes combined
Thus with P-trap WCs, there should be no
need to limit the length of branch; a practical From a siphonage standpoint some arrange-
limit of 6 m is suggested in Approved Docu- ments of combined bath and basin wastes
ment H, Building Regulations 1991. Branches perform satisfactorily unvented, but general
from S-trap WCs contained within the floor design recommendations are not readily
are normally quite short, the pan being sited formulated. Tests are needed to check the
close to the stack so that the branch at the performance of particular installations.
normal angle does not appear in the room Installing a vent as shown, for example, in
below. Self-siphonage does not normally occur figure 5.6 avoids the need for testing. Care is
under these conditions, nor with much longer also necessary to avoid water from the basin
branches. Experience has not shown any flowing into the bath, as can occur unless
special precautions to be necessary in this precautions are taken. From this standpoint,
respect with siphonic pans. the bath and basin wastes should join at an
angle of 45" on plan and the length of the
waste between the bath trap and tee should
Application of information
be sloping, preferably using a bath trap with
on individual branches
9 per cent rake of outlet. The waste between
Figure 5.4 shows a few examples of compact the tee and the stack should, if possible, be
sanitary layouts against which the data on straight. If a horizontal bend is necessary
branches may be considered. The appliances into the stack it should be of large radius.
are so positioned in relation to the service shaft The whole length of waste from basin to
that each branch to the stack is normally well stack should have a continuous fall, 4 per
within the limits for P-traps given in the cent being reasonable.
previous section. Pipe connections of the type
shown in figure 5.4 may, therefore, be used.
(ii) Bath wastes combined
With figure 5.5, the basin or sink is some way
from the main stack and would, therefore, With the arrangement in figure 5.7 water from
probably require a separate stack or venting - one bath may flow into the other unless
the arrangement shown in figure 5.6. precautions are taken. The waste pipes should,
As regards the tolerance in fixing the basin therefore, join as far from the traps as possible
branch (for which the slope of pipe is an and have a good fall. It is often convenient to
important factor, figure 5.3), the plans in figure use a Y-junction connecting directly into a
5.4 may be grouped as follows. 50mm boss in the stack wall with the angle of
Plans 1-4: the basin waste typically would be the Y nominally 60 '.
some 600 mm long and the slope would not be
critical. Plans 5-7: the basin waste typically
(iii) Combined soil and waste branches
would be about 1OOOmm long. The slope is
important; a working rule is to ensure that the Bathrooms in which the WC is 2 or 3 m from
difference in level between the trap outlet and the stack may be conveniently arranged with
stack connection does not exceed 50 mm. the WC branch, 100 mm diameter, containing
An alternative with some constructions and connections for the basin and bath or shower.
layouts may be to connect waste appliances A typical arrangement is with an S-trap WC,
into a larger 'horizontal' branch at or below with the WC branch beneath the floor, if
floor level - see next section. construction permits, where the waste connec-
Figure 5.9 gives recommendations, elabor- tions may readily be made in the upper half of
ated later, regarding the relative positions of the WC branch. The connections should be
WC and bath connections to the stack, with selected to ensure that the waste flows are
70 Water, Sanitary and Waste Services for Buildings
0
0
I\
h
--- I
Sink Basin
__J
Bath
A- 3
3200
Service shaft
4
Pipe connections to
I
the stack
U
1600
1700 800 5
T S e r v i c e shaft
6 Stock 2
1 I
1600
1700 7 3
2500
Sink or
basin
Note: Approximate dimensions of accommodation
are given (mm). See also figure 7.4
Figure 5.6 Bath and basin waste pipes combined (v) Ranges of WCs
Ranges of WCs are common in public and
(iv) Ranges of washbasins
commercial buildings. Branch pipes serving
Ranges of basins are common in public and such ranges normally are 100 mm diameter and
commercial buildings. Design recommen- do not run full, whatever the slope. There is,
dations (figure 5.8) have been formulated therefore, usually no need for branch venting,
with the aim of limiting siphonage in the although, as a precaution, it is recommended
event of full-bore flow anywhere in the branch. for more than eight WCs. Where there are
Full-bore flow depends upon such factors as bends in the pipe it may be necessary to fit
discharge rate, pipe size, the length and slope a vent pipe to the appliance furthest from the
of the branch and the shape of tee connections. stack. Hydraulic considerations indicate that
It is unlikely if washing is done under a W C connections to the common branch should
running tap and, as the latter is common, this be swept in the direction of flow.
Bath Bath
40 m m
wc
50 m m boss
Service Stock
shaft Stock
branch
Stack
Basin
connection in shaded
Curved t part (180° on plan)
or 135' h t a B + - ? --
angle
J Drain
Minimum (0)Bungalow
Stack dia. distance
Stack (mm) Nmml
75 90
Waste 90 100
branch 100 110
125 210
- 150 250 Basin
Table 5.2 Stack sizes and vents for various domestic loadings
Nofes: Each appliance group includes WC, bath and/or shower, basin and sink, and may include a washing
machine. WC branches should have entries swept or at an angle of 135" into the stack. Bend at base of stack
should be large radius. There should be no offsets in the 'wet' part of the stack. One connection of vent stack
to discharge stack in each storey should suffce
Norex 0 means no vent stack needed; /////// means overloaded on ‘one-quarter-full’ basis. WC branches should
have entries swept or at an angle of 135” into the stack. Bend at base of stack should be large radius. There
should be no offsets in the ‘wet’ part of the stack
Design of soil and waste pipe installations 77
because the substantial suctions due to wind in Table 5.4 Conversions to be used in conjunction
these areas may cause considerable loss of seal. with table 5.3
Application of the recommendations will ~
commonly involve the use of table 5.3 with WC Urinal Basin WC Basin
figure 5.8. Suppose, for example, that in a
‘commercial’ building there are four floors
2 +I +2 equivalent to 2 +2
2 + 2 + 3 3 + 3
with four WCs on each. The individual ranges 3 + 3 + 4 4 + 4
may be served by 100mm straight branches 4 + 4 + 5 5 +5
without venting; from table 5.3, the four
branches may discharge into a l00mm dis-
charge stack without the addition of a vent stack cross-section to be occupied by water
stack. Suppose that four washbasins on each under idealized conditions of annular flow.
floor are also connected to the discharge The ‘one-quarter-full’ criterion has been
stack. With the arrangement shown in figure assumed in most UK procedures (BS 5572),
5.8(a) the individual branches d o not need including the data in tables 5.2 and 5.3, along
venting and table 5.3 shows that the addition with swept W C entries. Proposals in CEN
of these basins does not necessitate a vent (De Cuyper 1993) took a greater safety margin
stack. With the basins fitted with S-traps and assumed around ‘one-sixth full’, along
according to figure 5.8(c), however, the indi- with ‘normal’ WC entries, which gives smaller
vidual ranges require venting as shown and a capacities. Figure 5.12 gives the calculated
vent stack would be required to link this vent information from the equations in chapter 8.
piping together and with the outside air. The T h e capacities that appear in the C E N
information available suggests that a vent standard are rounded to satisfy the wide
stack of 30mm diameter should be sufficient. range of views in different countries. An
A vent stack remains unnecessary as far as attempt to allow for the greater capacity
table 5.3 is concerned; limitation of induced permissible with swept WC branch entries
siphonage and back pressure associated with can be made through the recommendation of
flow in the discharge stack itself is virtually an arbitrary increase on the ‘one-sixth-full’
independent of the way in which the basins are values.
installed. In a sizing exercise the diameter of the
As a further example, consider 12 ‘commercial’ discharge stack should be determined from
floors with four WCs and four basins on each, figure 5.12 after establishing the likely flow
all discharging into the same stack. The using one of the discharge unit procedures of
individual W C ranges d o not need venting, chapter I . The diameter of vent stack required,
nor d o the basins if served by P-traps as shown if any, is then determined from table 5.5 (as in
in figure 5.8(a). The installation does, however, BS 5572) or other rule.
require a 40mm vent stack according to table
5.3, and this should be cross-connected to the
Design of ‘horizontal’ installations
discharge stack at each floor and near its base.
If the basins were to be fitted with S-traps, In this section we consider ‘horizontal’ instal-
venting would be required as in figure 5.8(c) lations of the kind illustrated in chapter 4, with
and this could be linked by the 40mm vent long drain lines or branches taking a consider-
stack derived from table 5.3. able number of inflows (figure 5.13). Where
applicable the information given in the fore-
going sections may be used. The following
(iv) General sizing method
notes supplement this from the experience
The basis is set out under the section on water available.
flow capacity in chapter 8. Based on equation Estimation of the peak flow load in the main
(8.1 l), which is not dependent in any way on drain may be done on the basis of the methods
shape of water entry to the stack, two relation- set out in chapter 1. As indicated, information
ships yield tables of capacity against cast iron on the frequency of use of appliances in
stack diameter. The values depend upon the hospitals is scanty and the best course is
assumption made about the proportion of the probably to assume that the frequency of use
78 Water, Sanitary a n d Waste Services for Buildings
Table 5.5 Diameters of ventilating stacks corresponds to not less than that assumed for
peak hours in public buildings.
Diameter of Diameter of The capacity of the drain to carry the peak
discharge stack, D ventilating stack load has to be considered. For underground
-
drains the assumption is often made that pipes
Less than 75 mm Two-thirds D
75 mm and over Half D should be designed for flow three-quarters full,
thus providing some spare capacity. Some
Design of soil and waste pipe installations 79
Figure 5.13 Example of 'horizontal' drainage installation in a hospital (Nottingham Teaching Hospital;
courtesy of Schott UK Ltd)
assumption of this kind must be made for 120 or 135 fittings. They should have access
O O
'horizontal' systems inside buildings. It might doors fitted to the side opposite the branch
reasonably be assumed that the 'horizontal' drain. Double-branch junctions on plan should
drains in the building should not flow more not be used. Access door openings should be
than half full, thus providing a greater safety rectangular in shape, large enough for cleaning
margin against surcharge in the branches equipment to be easily inserted into the pipe,
from the appliances, and permitting ready and should be positioned where the removal of
circulation of air. Such considerations apply the door and the insertion of the equipment
particularly to the main drains such as that can be easily carried out. They should not be
illustrated in figure 4.17. As to gradients of obstructed, for example, by other pipes. Access
pipes, limited experience with main drains laid points should be provided at each end of every
at 1 in 80 (1.25 per cent) has been successful main horizontal drain, at the top end possibly
and it is suggested that 1 in 80 should be by a screwed cap and socket ferrule and at the
regarded as a reasonable practical minimum lower end by a rectangular door on the crown
for pipes of 100 and 150mm diameters within of the pipe.
buildings. At this gradient these two pipe sizes Waste pipes should as far as possible run in
will take around 5 l/s and 13 I/s flowing half full straight lines at even gradients of not less than
(compare figure 12.4). The equivalent dis- about 2 per cent, and with any bends of not less
charge units may be obtained from chapter 1. than 75 mm radius on plan. Such piping should
Figure 1.7, for instance, gives around 300 and be well provided with cleaning eyes and with
2300 units respectively with mixed appliances, as means for readily dismantling sections for the
in BS 5572 (1994). clearing of stoppages. Wastes should enter the
For the reasons given in chapter 4, blockages main drain in the direction of flow using 120
are particularly likely to occur in this type of or 135" unequal branch junctions. Where a
installation, and the design and construction boss is used it should not discharge vertically
should take account of this point. Offsets and downwards into a horizontal drain.
short-radius bends should be avoided as far as It is usual in such installations to fit S-traps
possible as present evidence suggests they are a to waste appliances. Following the principles
main source of blockage. When a change of set out earlier, the trap either should be vented
direction is necessary it should be made by to prevent self-siphonage or should be of a
using either a large-radius bend or by combin- special resealing type. As a guide, the length of
ing two 135" bends. All such bends should be unvented waste pipe in the latter case should be
fitted with access doors. Junctions should be limited to 6 m in order to limit noise. In general
made obliquely in the direction of flow using the guidance given earlier for limiting self- and
80 Water, Sanitary and Waste Services for Buildings
This new edition of this classic text draws together material from
a variety of sources to provide the comprehensive coverage not
available elsewhere. It is a resource for the sound design,
operation and maintenance of these services and should be on
the bookshelf of every building services engineer and architect.
UTTERWORTH
E I N E M A N N
An imprint of Elsevier Science
www.bh.com