Professional Documents
Culture Documents
Environmental Plan
Page 1 of 36
Health, Safety and
Environmental Plan
This Version
Authored by:
Name: Faraz
Role: HSE Engineer
Signed:
Date:
Reviewed by:
Name: Ali Hyder Shah
Role: Site Manager
Signed:
Date:
Page 2 of 36
Health, Safety and
Environmental Plan
Contents
Page 3 of 36
Health, Safety and
Environmental Plan
Page 4 of 36
Health, Safety and
Environmental Plan
11 Emergency Procedures 28
11.1 Definitions and abbreviations 28
11.2 Emergency response plan 29
11.2.1 Equipment’s 30
11.2.2 Local emergency response centre 30
11.3 Implementation of emergency plan 30
11.3.1 Training 30
11.3.2 What every Employ need to Know 31
11.3.3 Inspection by competent person 31
11.3.4 Training and monitoring 31
11.4 Fire or Explosion Procedure 31
11.4.1 Notification and warning of a Fire and fire wardens 31
11.4.2 Emergency coordinator checklist 32
11.5 Hazardous material incident procedure 32
11.5.1 Notification and warning 33
11.5.2 Emergency coordinator 33
11.6 Utility outage Emergency procedure 33
11.6.1 Notification and warning 33
11.6.2 Temporary electrical power failure 33
11.7 Callout Protocol 34
Page 5 of 36
Health, Safety and
Environmental Plan
1. INTODUCTION
Oil & Gas Company limited owns and operates the KUNAR re-construction crude storage Tank
Project in the Sindh near Hyderabad of Pakistan. The project covers Dismantling of old Tank ,
repair/reconstruction of civil foundations and construction, testing, installation, commissioning and
calibration of new crude Oil storage tank. .
The objective of this PLAN is to define the Health, Safety and Environment (HSE) obligations
associated the current operation at the KUNAR re-construction crude storage Tank Project and to
implement these HSE obligations by the HESPAK during the compression project. HESPAK obligation
is to ensure that APPLICABLE LAWS relating to HSE are respected, complied with and monitored
during the entire performance. HSE criteria describe the basic requirements to ensure an inherently
safe design of the plant and related facilities. HSE criteria include facilities design, equipment design
and equipment selection in order to:
This Plan will be used as a safe instruction to guide the operation and the construction for KUNAR
reconstruction crude storage Tank project. It also sets out measures, based on the HSE management
procedures of HESPAK and local laws regarding HSE as well as owner’s safety regulations, to ensure
through the whole course of contract period protection for personal, safe working condition and
prevent or minimize the losses due to unsafe actions or factors and negligence of activities.
Page 6 of 36
Health, Safety and
Environmental Plan
Promises
All activities shall be carried out in compliance with local laws regarding HSE and OWNER’S safety
regulations which set out in document and HESPAK promises
To run effective operation of HSE management system throughout Kunar re-construction crude
storage tank project.
Design carefully and carry out construction strictly to protect personnel’s health and safety and
natural environment.
Protect social and public interests, establish excellent enterprise culture and make efforts to improve
the HSE performance level of the company.
Objectives
The top objectives for HESPAK HSE management is to seek no accident , pollution, damages and try
to prove ourselves as the first class international company by the satisfactory of our client.
SUB CONTRACORS with all APPLICABLE LAWS relating to HSE and HSE standards mentioned
throughout the performance of Kunar re-construction of crude storage tank project. Industry
standards shall be also respected and in compliance with. HESPAK shall comply and ensure
compliance by any of its.
Page 7 of 36
Health, Safety and
Environmental Plan
Personnel on Site:
Access of personnel to the work sites is controlled to ensure that no personnel commence work on
the site without being registered in the muster list, wearing the proper personal protective
equipment, and receiving a suitable HSE induction safety course.
Page 8 of 36
Health, Safety and
Environmental Plan
Site Manager
This Health, Safety and Environmental (HSE) Plan sets out the manner in which Hespak intends to deliver the
commitments set out in the Company Health, Safety and Environmental policy statements, the requirements
of accepted industry codes of practice and the requirements of the client and Consultant on the project.
The principles of control for the safe execution of the contract as outlined in this project HSE plan. Further
detail as to how the Hespak will control safe execution on the project can be found in the HSE work
procedures and standards. UK Health and Safety Regulations, whilst not law are adopted as good practice but
the plan is based on the following principal legislation (this is not exhaustive):
Zero Fatalities
Page 9 of 36
Health, Safety and
Environmental Plan
An Accident Frequency Rate reportable below 0.01 :- whilst working towards AFR target Zero
ZERO HARM focuses on continually improving the management of health, safety and welfare and
environmental issues within the organisation.
3.1 Purpose
This plan is to define the general guidelines established by Hespak, to provide all personnel with safe operating
practices and awareness for the work they perform in the course of their duties during the project.
To explain the rules set by statutory authorities, Client and Hespak to monitor and improve the
performance regarding health and safety of employees at work and environmental protection.
To ensure the legal and other requirement.
3.2 Scope
This plan applies to “detached retail Units Hespak” site and office.
This HSE Plan shall be distributed to Project Management for approval. Once approved it will be distributed to
key personnel on the project site. Hard copies will be issued to subcontractors.
The Project and Safety Leads shall ensure that the plan is reviewed to ensure:
The objectives and requirements of the plan are still valid, and are being met.
forthcoming activities are reviewed and any necessary amendments to the plan are put in place
before the relevant work begins
HSE processes shall be reviewed to ensure continuing suitability and effectiveness.
Page 10 of 36
Health, Safety and
Environmental Plan
INTERNAL
Site Manager
The Site Manager is responsible for the overall HSE management of the contracts undertaken by him. He is
responsible for:
Ensuring knowledge of and compliance with company policies, procedures, Hespak Health and
Safety standards and site safety rules.
Being visible in the Health and Safety process, constantly monitoring the project environment
and performance.
Provide the force and resources necessary for project compliance with agreed safety procedures
and standards.
Taking action to correct discrepancies reported as a result of surveys or inspections.
Ensuring that all employees (including sub-contractors) are competent to perform their work
tasks.
Providing safe plant, equipment and working conditions for all employees.
Appointment of key personnel
Ensuring that resources allotted for HSE activities are being properly utilised.
Highlighting safety priorities.
Monitoring compliance with agreed safety procedures and standards.
Page 11 of 36
Health, Safety and
Environmental Plan
The Project HSE Engineer report to the Site Manager. He is responsible for:
Page 12 of 36
Health, Safety and
Environmental Plan
Page 13 of 36
Health, Safety and
Environmental Plan
Monthly review - Observations from the - Site Manager Monthly meeting to discuss the
Leadership Tour - Senior Engineers monthly performance on the
- Previous minutes - Supervisors project and will be held once in
- Risk elimination - Project HSE lead receipt of the project. The meeting
- Inspection/Trend - Subcontractor will be coordinated by the HSE
analysis Management Engineer and will be chaired by the
- Outstanding actions Project Director.
- Safety focus for the
month
- Safety resource
requirements
- AOB
Page 14 of 36
Health, Safety and
Environmental Plan
Page 15 of 36
Health, Safety and
Environmental Plan
Prior to setting any employee to work the Project Management and Supervisory teams should satisfy
themselves where possible, that all persons are physically, medically, and emotionally fit for performing the
duties to which they are assigned. Consideration should also be given to the employee’s strength, endurance,
agility, and coordination, visual and hearing acuity.
Page 16 of 36
Health, Safety and
Environmental Plan
Adequate sanitation facilities, sanitary sewage and water source shall be provided in the workplace in
accordance with the Dubai Municipality Code of construction safety practices.
Page 17 of 36
Health, Safety and
Environmental Plan
8.14 Ladders/Stepladders
Ladders and Stepladders may only be used once proven that it is not reasonably practicable for any other form
of access to be used. They may be used for work of a short duration (minutes) and only when in receipt of a
permit issued by the project safety team. Stepladders (under permit) will be footed by a second operative if
working above 2m.
Page 18 of 36
Health, Safety and
Environmental Plan
8.15 Scaffolds
Scaffolds and mobile towers can only be used when an in date and signed scafftag is in place which indicates
the scaffold is fit for purpose. Scaffolds must only be used once erected and inspected by a competent person.
Alterations to scaffolds of any type are prohibited unless undertaken by a competent person. A documented
inspection must then be undertaken prior to use.
8.16 MEWPs
Only trained and competent persons will be permitted to use a Mobile Elevated Work Platform. All occupants
of the MEWP will be required to wear a fall restraint lanyard. Where space restrictions allow all stationary
MEWPS will have a barricaded exclusion zone at the front and rear to prevent accidental contact with
pedestrians.
8.17 Excavations
Hespak will never work in or around unsupported ground of any depth where there is a risk of injury from
ground movement or in any situation 1.2m or more below the ground surface unless ground support measures
are in place.
Hespak will ensure suitable barriers will remain in place around the excavation at all times along with
adequate warning signage. Hespak recognises that barriers act as edge protection and an exclusion zone and
will therefore ensure barriers are at least 1 meter back from the excavation edge.
8.18 Confined Space
All work requiring entry into confined spaces will only be undertaken by trained and competent persons.
Access to confined spaces can only be gained once in receipt of a permit issued by an authorised person once
the following requirements have been met:
Permit is communicated to all affected personnel and posted, as required.
All people involved are competent to do the work and must be trained first.
All people involved are equipped with the appropriate PPE and safety equipment.
Testing of atmosphere is conducted, verified and repeated as often as defined by the
risk assessment.
Stand-by person is stationed.
A rescue plan is in place.
Page 19 of 36
Health, Safety and
Environmental Plan
Page 20 of 36
Health, Safety and
Environmental Plan
8.23 Noise
Where possible, noise levels will be kept to a minimum at all times. Hearing protection will be provided to all
operatives if requested and be mandated for all tasks where risk assessments identify that noise levels may
reach in excess of 85dBA. Periodic noise assessments will be carried out by the project safety team and if
necessary noise exclusion zones will be implemented.
8.25 Electricity
Hespak will never work on a live system unless the energy source has been isolated and verified through
testing.
Plant/switch rooms, transformer banks and high voltage equipment shall be protected from unauthorized
access. Entrances not under constant observation shall be kept locked. Gates or doors to enclosures for
electrical equipment shall swing outward or provide clearance from installed equipment.
All power tools and electrically operated plant will be double insulated. Transformer banks or high voltage
equipment shall be protected from unauthorized access. Entrances not under constant observation shall be
kept locked.
Page 21 of 36
Health, Safety and
Environmental Plan
Page 22 of 36
Health, Safety and
Environmental Plan
Page 23 of 36
Health, Safety and
Environmental Plan
Page 24 of 36
Health, Safety and
Environmental Plan
Page 25 of 36
Health, Safety and
Environmental Plan
a) General
When controls required either fail or are inadequate to prevent harmful exposure to employees, appropriate
respiratory protective devices shall be provided by the employer / contractor and shall be used.
Respiratory protective devices shall be of the type and standard for the contaminant to which the employee is
exposed.
c) Respirator Selection
The chemical and physical properties of the contaminant as well as the toxicity and concentration of the
hazardous material shall be considered in selecting the proper respirators.
The nature and extent of the hazard, work requirements, and conditions as well as the limitations and
characteristics of the available respirators, shall also be factors considered in making the proper selection.
9.0 Environmental
The Site Manager will appoint designated store personnel to ensure the following rules apply to materials
stored on site:
Materials and consumables will be protected from the elements and stored on pallets and covered.
Items will be stacked safely and secured.
Flammable substances will only be ordered in small containers and will be stored in shaded location out
of direct sunlight.
No fuel will be stored in the Hespak stores.
Heavy items of equipment will not be stacked or stored at high level and will be stored so that easy
access is available for the forklift.
Hespak stores compound will be maintained in a clean and tidy manner. Records of stores issues will be
maintained.
All Materials located on site will be stacked in lay down agreed areas.
Storage of combustible materials will be carried out in accordance with the Manufacturer instructions.
Packaging materials will be removed from site at the earliest opportunity in order to reduce the fire load.
Page 26 of 36
Health, Safety and
Environmental Plan
Page 27 of 36
Health, Safety and
Environmental Plan
Breaking of bricks
Volatile chemicals released or opened to the atmosphere.
Working in an enclosed room / area
Uncovered smelling waste materials
Saw dust
Fumes produced from welding activity
To all this, we are tend to put in place some dynamic measure to alleviate any hazards i.e. air quality.
Anywhere, dust / particles are flowing at an above than normal rate. The area will be wet with water
effectively. This will reduce the particles and make the air in the area absorbable. Discretionally, this action
normally will be taken by the workers in that area with the approval of the present supervisor. The reason for
this approval is to make sure water is not applied to some area where it need not to, and again for proper
instruction on the capacity of water to use, because if the water is too much, the area become marshy or
slippery, and any of the two will have consequences.
Covered waste bins will be provided so as to prevent any foul odor that comes out of it. Normally, not all
wastes are smelly waste product, but for example, the remains of foods, chemicals buckets, etc. could have an
impact on the air quality so it’s best not to be opened.
Working in an enclosed area really needs more attention and care, because the IAQ in the area will really
determine the air intake of the workers present.
In an enclosed area, the air instead of circulating, rotate thereby not going thru to bring in fresh air exchange.
However, any enclosed area will be provided with an exhaust fan which will make for the lack of air circulation.
The exhaust fan will however not be facing the person’s working and prevent any particle inhaling.
Where possible fuels will not be stored on project sites. Where storage of fuels is necessary storage tanks will
be sealed to prevent unauthorized use. Required fuels, oils and petroleum based lubricants will only be stored
in minor quantities to reduce fire risk. Containers in excess of 1 gallon will not be stored outside of a shaded,
bounded fuel store. Fuel and oil spills will be contained and cleaned immediately. Contaminated soil / sand
will be bagged and removed from site for appropriate disposal. The fuel store will be restricted to authorized
personnel only and storage will be locked. Smoking in the fuel areas is not permitted. Signage will be clearly
displayed. Appropriate number of fire extinguishers / fire protection will be placed around the fuel storage
area and signage displayed
Page 28 of 36
Health, Safety and
Environmental Plan
The following fire fighting facilities shall be made available at site & offices
Fire points comprising CO2 fire extinguishers each in locations 15 M apart in the offices and the site
fire extinguishers shall be provided in addition to the above near to all generators & flammable liquid
storage area
Fire & emergency assembly points shall be made available, emergency contact numbers shall be posted in
conspicuous places.
Page 29 of 36
Health, Safety and
Environmental Plan
a. Fire or Explosion
b. Hazardous Material / Chemical Leakage.
c. Heavy Machinery and Equipment Failure Or Collapse
d. Accident/ Incident
e. Personnel injury;
f. Extreme Weather Conditions
g. Facility Blackout.
h. Confined space
i. Electric Shock
This plan describes general issues for emergency preparedness, post emergency, evacuation drills and
emergency prevention.
Access Control Point - A staffed or barricaded point established to prohibit access to a hazardous or
potentially hazardous area
Assembly Area - A designated area, located away from the emergency scene, where persons gather
during an emergency evacuation for the purpose of receiving emergency briefings and instructions,
and to be accounted for. An assembly area may or may not be offsite; the location generally depends
upon the size and type of project Manager involved and the type of surrounding land uses at each
project.
Disaster - An occurrence or imminent threat of widespread or severe damage, injury, or loss of life or
property resulting from a natural or man-made cause, including but not limited to fire, flood, snow,
ice, tornado, windstorm, wave action, oil spill, water contamination, utility failure, hazardous
peacetime radiological incident, major transportation accident, hazardous material incident, epidemic,
air contamination, blight, drought, infestation, explosion, or hostile military action, or paramilitary
action, or similar effects resulting from terrorist activities, riots or civil disorders.
Emergency Plan - The plan developed and maintained for the purpose of organizing and coordinating
its emergency response activities and operations. The plan is consistent with the Emergency
Operations Plan.
Page 30 of 36
Health, Safety and
Environmental Plan
Evacuation - A protective action strategy that provides for the orderly movement of people away from
an actual or potential hazard.
Protective Actions - Those emergency measures taken to protect people from the effects of a hazard.
These may include evacuation and in-place sheltering.
State of Disaster - A declaration by executive order or proclamation by the Government activates the
disaster response and recovery aspects of state and local emergency plans and authorizes deployment
and use of any forces to which the plan or plans apply.
Unit Emergency Coordinator - The person designated from each unit to carry out protective measures
(evacuation or protective shelter) at the project.
Team members will be involved in both planning and response activities. Teamwork insures all necessary issues
and increases staff awareness of the plan and combines different tasks incorporated in team positions.
Emergency response team for initial response will manage emergency situation and team members will be
equipped with the skill to fulfil their roles. The team will comprise of:
Emergency coordinator
First aider
Site Manager and safety personnel
Specialist operators
11.2.1 Equipment’s
Survey the project for equipment resources that may be needed to respond to the hazards identified in hazard
analysis. For example, if the project lacks an alarm system or public warning system, what can be done to warn
employees during any emergency? The following safety items shall be provided in sufficient quantities and
maintained properly to ensure working condition when in demand:
Fire Extinguishers
First aid apparatus
Public warning system (Alarm, Bell, Horn, Flashing Lights)
Mobile Phone or other communication system
Flashlights spare batteries
Spill control facilities
Emergency light and power facilities
Personnel protection equipment such as safety harness, life jacket, if applicable
Page 31 of 36
Health, Safety and
Environmental Plan
The Project emergency team will identify what resources local response agencies have and how those agencies
plan to respond to an incident at the Project. In order to respond effectively, the team will work with the local
emergency management coordinator, fire, police, and emergency medical services.
To implement the plan, make the plan known, employees must be trained and the plan must be exercised.
Exercising and testing the Project emergency plan also allows the project emergency team to determine, first
hand, whether the plan will actually work. If certain procedures do not work, then the plan will be revised.
11.3.1 Training
There are certain pieces of information that every employee needs to know in advance of an emergency.
Page 32 of 36
Health, Safety and
Environmental Plan
Fire Marshals/HSE Leads / Project emergency coordinator will inspect for all support works and maintain
record of inspections.
Training for emergency response will be provided to all during safety induction. As a special training, an
evacuation drill should be effectively utilized. Continuous monitoring will be performed through evacuation
drills and implementing Emergency Plan. A meeting shall be initiated by the project senior management and
reviewed the emergency drill findings and any areas for improvement. Drill assessment and follow-up actions
to be documented and distributed to responsible persons.
Notification of a fire or explosion in the project will be made by fire alarm/Air horn.
If alarm is not available in the vicinity he should shout Fire... Fire … Fire to inform all people. The
warning signal consists of ringing bell.
The first person spotting a fire should activate the alarm system/Air Horn
Telephone call will be made to project HSE/project manager/ emergency services.
Disconnects electrical power source from any live equipment.
Guide and support employees/subcontract/occupants/visitors to the nearest exit routes/assembly
points.
At each assembly point takes head count and report to emergency coordinator.
Notify fire department and determine the extent of the fire or explosion.
Determine what staff and personnel should do during interim period.
Authorize the use of organization resources by Project Emergency Team.
Ensure that the fire alarm system has been activated.
Activate the Project Emergency Plan.
Coordinate with maintenance personnel, utility companies, and the fire department in shutting down
utility lines or systems that might present an additional hazard (i.e., Electric, gas main).
Police 100
Fire Department 101
Ambulance 102,108
Page 33 of 36
Health, Safety and
Environmental Plan
Work areas using, storing, transporting, or producing hazardous materials may have certain requirements to
follow during a release or spill. These project Managers may choose to add those specific procedures for
project hazardous material incident to this plan.
Page 34 of 36
Health, Safety and
Environmental Plan
The Emergency Coordinator will determine the extent of the utility emergency and contact the
appropriate repair and emergency response personnel.
Situations of an isolated nature (i.e., power outage or water main break affecting one building or unit)
that can be resolved quickly and safely may only require a partial evacuation or temporary shutdown
of operations.
Telephone Managery
Page 35 of 36
Health, Safety and
Environmental Plan
Ambulance 102
The HSE Award Certificate will be endorsed by the Project Manager and, HSE Engineer, documented and
distributed to responsible persons.
Page 36 of 36