Professional Documents
Culture Documents
1 4
To identify the key constraints and establish their magnitude of effect
to on-site construction productivity in the construction industry of
Uganda.
Main
objective
Research
Objectives Specific
objectives
1 5
JUSTIFICATION OF THE STUDY
➢A global review by International Labour Organization(2013) finds that increases in on-site
productivity within economic sectors are the main driver of economic growth. In particular,
growth in industry and services plays an important role in aggregate economic growth.
➢According to Mahamid et al. (2013), on-site construction productivity plays a key role in
determining the success of a project. However, it might be affected by many unexpected
variables. These variables may include factors related to labour, materials, tools and
equipment, construction methods, politics, financing, and environment (Alinaitwe et al
2007).
➢On account of the labor-intensive nature of construction operations, identifying and
addressing labour productivity limiting factors is a fundamental approach to enhancing the
productivity performance of the construction industry (Durdyev & Mbachu 2011).
1 6
SCOPE OF THE STUDY
➢Geographical Scope
The research was conducted within Rubaga division in Kampala district.
➢Content Scope and Limitations of the Study
The study is limited in terms of covering all aspects of construction productivity that
ought to have been taken into consideration in order to identify overall constraints to
construction productivity and improvement techniques.
➢Time scope
This Research was conducted between the month of April 2022 and September 2022,
which approximately was five months.
➢
1 7
METHODOLOGY
1 8
KEY
KEY COLLABORATIONS & PARTNERSHIPS
METHODOLOGYPARTNERSHIPS
1 9
SPECIFIC OBJECTIVE ONE
1 12
Demographic data
Respondents in percentages
Foreman,
19%
Site
engineer, 1-3 4-6 Above 6 Below 1 year
Safety
engineer, 39%
5%
9%
22%
Project 32%
manager,
19%
Quantity
Surveyor,
15%
Site engineer Quantity Surveyor
Project manager Safety engineer
41%
1 12
SPECIFIC OBJECTIVE TWO
Model Equation
𝑌 = 𝑀𝑋 + 𝐶(Where Y is the schedule, X are predictor
variables and M and C are constants).
Schedule(time)=0.814D+0.02C+0.015di+0.265Q-
1 0.126M-1.005 13
Satisfaction of work done(quality) vs material-related constraint
factors
Hypothesis.
Ho-Material-related constraints do not have a
significant effect on satisfaction of work done.
1 14
SPECIFIC OBJECTIVE THREE
1 15
CONCLUSION
➢Productivity is in essence the backbone that makes or breaks a company in the
construction industry, as it is the key-determining factor in performance and
success.
➢The main objectives of this study have been to identify the key constraints to on-
site productivity and to establish their effect on on-site productivity, based on
views of contractors, consultants and subcontractors
➢In total 26 constraint factors were identified in five broad categories of project
finance, Workforce, building process, materials and unforeseen events.
➢Reworks, late payments, material shortage at site, delay in delivery of materials,
failure to adopt new technologies were the most contributors to the biggest
percentage of on-site construction problems.
➢Generally material related constraints dominated the priority factors and had a
significant effect on on-site construction1 productivity. 16
RECOMENDATIONS
➢construction projects are unique worldwide, so construction companies should focus on
sourcing the most modern suitable methods of executing construction projects to
improve their productivity on site.
➢This study mostly focused on constraints to on-site productivity during the construction
phase; however, there are several aspects to construction productivity.
➢Future studies should explore other influencing factors affecting construction
productivity at all stages of the procurement process and pre construction phase.
➢Also further studies should include opinions more from clients ,designers and suppliers
1 17