NH13- SOLAPUR-BIJAPUR PROJECT

CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
1 NH13-SOLAPUR-BIJAPUR - WORK PROGRAM 901 days May 3, 2018 October 19, 2020

2 Events 901 days May 3, 2018 October 19, 2020

3 LOI issued 0 days May 3, 2018 May 3, 2018 5/3

4 Work order and appointed date 0 days August 1, 2018 August 1, 2018 3FS+91 days 8/1

5 Milestone-I (165 days) 0 days January 13, 2019 January 13, 2019 4FS+165 days 1/13

6 Milestone-II (360 days) 0 days July 27, 2019 July 27, 2019 4FS+360 days 7/27

7 Milestone-III (585 days) 0 days March 8, 2020 March 8, 2020 4FS+585 days 3/8

8 Milestone-IV (810 days) scheduled completion date 0 days October 19, 2020 October 19, 2020 4FS+810 days 10/19

9 Permission of Trees removal from concrened authority 0 days July 31, 2018 July 31, 2018 3FS+90 days 7/31

10 Permission of Trees tranplantation and WO. 0 days July 1, 2018 July 1, 2018 3FS+60 days 7/1

11 Land clearence and encroachment removal permission from Concerned 0 days July 31, 2018 July 31, 2018 3FS+90 days 7/31
authority

12 Permission for Electrical poles shifting from Entity owning authority 0 days July 31, 2018 July 31, 2018 3FS+90 days 7/31

13 Permission for water line shifting from Entity owning authority 0 days August 30, 2018 August 30, 2018 3FS+120 days 8/30

14 Activities 805 days May 18, 2018 July 30, 2020

15 Pre Construction Activities 570 days May 18, 2018 December 8, 2019

16 Camp and Office 75 days May 18, 2018 July 31, 2018 3FS+15 days 5/18 7/31

17 Site Laboratory 75 days May 18, 2018 July 31, 2018 3FS+15 days 5/18 7/31

18 RMC-30 CUM- 1 75 days May 24, 2018 August 6, 2018 3FS+21 days 5/24 8/6

19 RMC-30 CUM-2 60 days August 22, 2018 October 20, 2018 18FS+15 days 8/22 10/20

20 WMM Plant -200 TPH 30 days August 17, 2018 September 15, 2018 4FS+15 days 8/17 9/15

21 HOT MIX PLANT-124 TPH 60 days August 17, 2018 October 15, 2018 4FS+15 days 8/17 10/15

22 Crusher installaton 90 days June 2, 2018 August 30, 2018 3FS+30 days 6/2 8/30

23 Joint survey and detailing 30 days May 18, 2018 June 16, 2018 3FS+15 days 5/18 6/16

24 ROW Fixing 75 days May 18, 2018 July 31, 2018 3FS+15 days 5/18 7/31

25 Trees tranplantation below 1.2 m girth size 60 days July 9, 2018 September 6, 2018 10FS+7 days,23 7/9 9/6

26 Trees felling above 1.2 m girth size 30 days August 8, 2018 September 6, 2018 9FS+7 days,23 8/8 9/6

27 Electrical poles shiftng by Enitnty owning 30 days August 8, 2018 September 6, 2018 12FS+7 days,23 8/8 9/6

28 Water line shifting by entity owning authority 30 days September 15, 2018 October 14, 2018 13FS+15 days,23 9/15 10/14

29 Encroachment Removal 15 days August 16, 2018 August 30, 2018 11FS+15 days 8/16 8/30

30 others and land clearneces 30 days August 16, 2018 September 14, 2018 11FS+15 days 8/16 9/14

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 1
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
31 Plan & Profile 1 day August 17, 2018 August 17, 2018

32 Issue of working Drawings- from km 69.00 to 89.00 1 day August 17, 2018 August 17, 2018 4FS+15 days 8/17 8/17

33 Cross section 1 day August 19, 2018 August 19, 2018

34 Issue of working Drawings- from km 69.00 to 89.00 1 day August 19, 2018 August 19, 2018 32SS+2 days 8/19 8/19

35 Drainage plan 1 day August 19, 2018 August 19, 2018

36 Issue of working Drawings- from km 69.00 to 89.00 1 day August 19, 2018 August 19, 2018 32SS+2 days 8/19 8/19

37 Issue of Working Drawing for HPC 153 days August 17, 2018 January 16, 2019

38 @75.660 -HPC 1 day August 25, 2018 August 25, 2018 32FS+7 days 8/25 8/25

39 @70.323-HPC 1 day August 27, 2018 August 27, 2018 38FS+1 day 8/27 8/27

40 @ 70.664-HPC 1 day August 29, 2018 August 29, 2018 39FS+1 day 8/29 8/29

41 @ 70.807-HPC 1 day August 31, 2018 August 31, 2018 40FS+1 day 8/31 8/31

42 @71.087-HPC 1 day September 2, 2018 September 2, 2018 41FS+1 day 9/2 9/2

43 @ 71.125-HPC 1 day September 4, 2018 September 4, 2018 42FS+1 day 9/4 9/4

44 @71.402-HPC 1 day September 6, 2018 September 6, 2018 43FS+1 day 9/6 9/6

45 @ 74.708-HPC 1 day September 8, 2018 September 8, 2018 44FS+1 day 9/8 9/8

46 @69.807 -HPC 1 day September 10, 2018 September 10, 2018 45FS+1 day 9/10 9/10

47 @77.025-HPC 1 day September 12, 2018 September 12, 2018 46FS+1 day 9/12 9/12

48 @78.33-HPC 1 day September 14, 2018 September 14, 2018 47FS+1 day 9/14 9/14

49 @78.774-HPC 1 day September 16, 2018 September 16, 2018 48FS+1 day 9/16 9/16

50 @78.99 - HPC 1 day September 18, 2018 September 18, 2018 49FS+1 day 9/18 9/18

51 @80.287-HPC 1 day September 20, 2018 September 20, 2018 50FS+1 day 9/20 9/20

52 @ 80.665-HPC 1 day September 22, 2018 September 22, 2018 51FS+1 day 9/22 9/22

53 @ 83.185-HPC 1 day September 24, 2018 September 24, 2018 52FS+1 day 9/24 9/24

54 @ 83.42-HPC 1 day September 26, 2018 September 26, 2018 53FS+1 day 9/26 9/26

55 @ 83.57-HPC 1 day September 28, 2018 September 28, 2018 54FS+1 day 9/28 9/28

56 @ 83.800- HPC 1 day September 30, 2018 September 30, 2018 55FS+1 day 9/30 9/30

57 @ 83.845-HPC 1 day September 30, 2018 September 30, 2018 55FS+1 day 9/30 9/30

58 @ 84.75-HPC 1 day October 2, 2018 October 2, 2018 56FS+1 day 10/2 10/2

59 @84.989-HPC 1 day October 2, 2018 October 2, 2018 57FS+1 day 10/2 10/2

60 @87.926-HPC 1 day October 4, 2018 October 4, 2018 58FS+1 day 10/4 10/4

61 Issue of Working Drawing for BOX Culvert 17 days September 2, 2018 September 18, 2018

62 @74.375- Box culvert 1 day September 2, 2018 September 2, 2018 32FS+15 days 9/2 9/2

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 2
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
63 @79.842- Box culvert 1 day September 18, 2018 September 18, 2018 62FS+15 days 9/18 9/18

64 PUP and slip road/service road 47 days September 17, 2018 November 2, 2018

65 Issue of working Drawings (GAD/RCC/Plan and 47 days September 17, 2018 November 2, 2018
profile/cross section)

66 Issue of @ 84.975- PUP Structure RCC/GAD Drawing 1 day September 17, 2018 September 17, 2018 32FS+30 days 9/17 9/17

67 Preperation and Submission RE Wall design 30 days September 19, 2018 October 18, 2018 66FS+1 day 9/19 10/18

68 Approval of RE Wall Design 15 days October 19, 2018 November 2, 2018 67 10/19 11/2

69 Issue of @ 87.530- PUP Structure RCC/GAD Drawing 1 day September 17, 2018 September 17, 2018 32FS+30 days 9/17 9/17

70 Preperation and Submission RE Wall design 30 days September 19, 2018 October 18, 2018 69FS+1 day 9/19 10/18

71 Approval of RE Wall Design 15 days October 19, 2018 November 2, 2018 70 10/19 11/2

72 VOP- Horti village 1 day September 17, 2018 September 17, 2018

73 Issue of working Drawings (GAD/RCC/Plan and 1 day September 17, 2018 September 17, 2018
profile/cross section)

74 @ 72.995 -VOP strucutres/RCC wall/ Draiange plan 1 day September 17, 2018 September 17, 2018 32FS+30 days 9/17 9/17

75 Service road- plan and profile/cross section from 72.660 to 1 day September 17, 2018 September 17, 2018 74SS 9/17 9/17
73.380

76 MAJOR BRIDGES 31 days September 17, 2018 October 17, 2018

77 Issue of working Drawings (GAD/RCC/Plan and 1 day October 17, 2018 October 17, 2018
profile/cross section)

78 @ 87.105 -GAD/RCC drawings 1 day September 17, 2018 September 17, 2018 32FS+30 days 9/17 9/17

79 MINOR BRIDGES 153 days August 17, 2018 January 16, 2019

80 Issue of working Drawings (GAD/RCC/Plan and 76 days September 2, 2018 November 16, 2018
profile/cross section)

81 @ 68.984- ( RHS and LHS) 1 day September 2, 2018 September 2, 2018 32FS+15 days 9/2 9/2

82 @ 72.680 -( RHS,LHS, Service road RHS, Service road 1 day September 25, 2018 September 25, 2018 75FS+7 days 9/25 9/25
LHS)

83 @73.380 -( RHS,LHS, Service road RHS, Service road 1 day September 25, 2018 September 25, 2018 75FS+7 days 9/25 9/25
LHS)

84 @ 74.985- ( RHS and LHS) 1 day September 2, 2018 September 2, 2018 32FS+15 days 9/2 9/2

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 3
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
85 @ 78.060- ( RHS and LHS) 1 day September 17, 2018 September 17, 2018 32FS+30 days 9/17 9/17

86 @ 80.155- ( RHS and LHS) 1 day October 2, 2018 October 2, 2018 32FS+45 days 10/2 10/2

87 @ 81.045- ( RHS and LHS) 1 day October 17, 2018 October 17, 2018 32FS+60 days 10/17 10/17

88 @ 84.295- ( RHS and LHS) 1 day November 1, 2018 November 1, 2018 32FS+75 days 11/1 11/1

89 @86.836 -( RHS,LHS, Service road RHS, Service road 1 day November 16, 2018 November 16, 2018 32FS+90 days 11/16 11/16
LHS)

90 Junctions drawing and details 1 day November 17, 2018 November 17, 2018

91 Issue of working Drawings 1 day November 17, 2018 November 17, 2018 89 11/17 11/17

92 Bus-bay/truck lay bye darwing and details 1 day November 17, 2018 November 17, 2018

93 Issue of working Drawings 1 day November 17, 2018 November 17, 2018 89 11/17 11/17

94 DRAINAGE, PROTECTION WORK & RCC WALL 1 day September 24, 2018 September 24, 2018

95 Issue of working Drawings 1 day September 24, 2018 September 24, 2018 75SS+7 days 9/24 9/24

96 Footpath Drain RCC drawing 1 day September 24, 2018 September 24, 2018

97 Issue of working Drawings 1 day September 24, 2018 September 24, 2018 75SS+7 days 9/24 9/24

98 Pavement design 1 day August 17, 2018 August 17, 2018

99 Issue of working Drawings 1 day August 17, 2018 August 17, 2018 4FS+15 days 8/17 8/17

100 Miscellenious 153 days August 17, 2018 January 16, 2019

101 Toll Plaza ( Plan/profile/crosssection) 1 day August 17, 2018 August 17, 2018

102 Issue of working Drawings 1 day August 17, 2018 August 17, 2018 4FS+15 days 8/17 8/17

103 Administrative building 1 day September 2, 2018 September 2, 2018

104 Issue of working Drawings 1 day September 2, 2018 September 2, 2018 102FS+15 days 9/2 9/2

105 ROAD furniture and safety devices 1 day January 16, 2019 January 16, 2019

106 Issue of working Drawings 1 day January 16, 2019 January 16, 2019 89FS+60 days 1/16 1/16

107 Miscellenious and Crash barrier 1 day January 16, 2019 January 16, 2019

108 Issue of working Drawings 1 day January 16, 2019 January 16, 2019 89FS+60 days 1/16 1/16

109 Quality control Documentation 60 days June 2, 2018 July 31, 2018

110 QAP Approval 60 days June 2, 2018 July 31, 2018 3FS+30 days 6/2 7/31

111 Project safety plan 60 days June 2, 2018 July 31, 2018 110SS 6/2 7/31

112 Traffic Management Plan 60 days June 2, 2018 July 31, 2018 111SS 6/2 7/31

113 Aggregate Production 510 days July 17, 2018 December 8, 2019

114 Outsourced for M-15/M-20 concrete for Initial work 60 days July 17, 2018 September 14, 2018 3FS+75 days 7/17 9/14

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 4
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
115 Aggregate Production from Crusher 450 days September 15, 2018 December 8, 2019 22FS+15 days 9/15 12/8

116 Source Approval 300 days May 18, 2018 March 13, 2019

117 Stone quarry 90 days May 18, 2018 August 15, 2018 3FS+15 days 5/18 8/15

118 Murum quarry 300 days May 18, 2018 March 13, 2019 3FS+15 days 5/18 3/13

119 Cement 45 days July 2, 2018 August 15, 2018 3FS+60 days 7/2 8/15

120 steel - 45 days July 2, 2018 August 15, 2018 3FS+60 days 7/2 8/15

121 Water 45 days July 2, 2018 August 15, 2018 3FS+60 days 7/2 8/15

122 Sand 45 days July 17, 2018 August 30, 2018 3FS+75 days 7/17 8/30

123 Coarse Aggregate 60 days July 18, 2018 September 15, 2018 114SS+1 day 7/18 9/15

124 Fine Aggregate 60 days July 18, 2018 September 15, 2018 114SS+1 day 7/18 9/15

125 Admitxture 45 days July 19, 2018 September 1, 2018 114SS+2 days 7/19 9/1

126 RCC Pipes 45 days July 2, 2018 August 15, 2018 3FS+60 days 7/2 8/15

127 Bitumen 45 days August 11, 2018 September 24, 2018 3FS+100 days 8/11 9/24

128 Mix Design 83 days July 19, 2018 October 9, 2018

129 M-15 30 days July 19, 2018 August 17, 2018 119SS,121SS,122SS,123SS,124SS,125SS
7/19 8/17

130 M-20 30 days July 19, 2018 August 17, 2018 129SS 7/19 8/17

131 M-25 45 days July 20, 2018 September 2, 2018 130SS+1 day 7/20 9/2

132 M-30 45 days July 21, 2018 September 3, 2018 131SS+1 day 7/21 9/3

133 M-40 and 45 45 days July 22, 2018 September 4, 2018 132SS+1 day 7/22 9/4

134 DLC-M 10 45 days August 6, 2018 September 19, 2018 133SS+15 days 8/6 9/19

135 PQC-M-40 45 days August 6, 2018 September 19, 2018 133SS+15 days 8/6 9/19

136 GSB 7 days September 16, 2018 September 22, 2018 115SS+1 day 9/16 9/22

137 WMM 7 days September 16, 2018 September 22, 2018 115SS+1 day 9/16 9/22

138 DBM 7 days September 26, 2018 October 2, 2018 127FS+1 day 9/26 10/2

139 BC 7 days October 3, 2018 October 9, 2018 138 10/3 10/9

140 Field trail 3 days October 16, 2018 October 18, 2018

141 DBM 2 days October 16, 2018 October 17, 2018 21,138 10/16 10/17

142 BC 1 day October 18, 2018 October 18, 2018 139,141 10/18 10/18

143 Post Construction Activities 90 days April 17, 2020 July 30, 2020

144 Miscellaneous Works (Road Marking, Plantation, Amenities, etc.) 60 days May 20, 2020 July 28, 2020 148FF+3 days 5/20 7/28

145 Quality Testing of Highway 45 days April 17, 2020 June 8, 2020 148FS-85 days 4/17 6/8

146 Testing of Toll Plaza working 15 days June 5, 2020 June 22, 2020 597FS-14 days 6/5 6/22

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 5
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
147 Safety Audit & Compliance 90 days April 17, 2020 July 30, 2020 148FS-85 days 4/17 7/30

148 Construction Activities 664 days May 3, 2018 July 24, 2020

149 Section-4 (69 Km to 89 Km) 579 days August 15, 2018 July 24, 2020

150 Road Works 579 days August 15, 2018 July 24, 2020

151 C&G & BC Excavation Works (BHS) 250 days August 15, 2018 June 17, 2019 4FS+7 days 8/15 6/17

152 Embankment (Cut / Fill) 528 days August 24, 2018 June 1, 2020

153 Embankment (NCW) 182 days August 24, 2018 April 4, 2019

154 69+000 to 70+000 LHS 20 days November 5, 2018 November 27, 2018 166 11/5 11/27

155 70+000 to 70+500 RHS 9 days November 28, 2018 December 7, 2018 154 11/28 12/7

156 70+500 to 71+000 LHS 8 days December 8, 2018 December 17, 2018 155 12/8 12/17

157 71+000 to 71+800 LHS 11 days December 18, 2018 December 29, 2018 156 12/18 12/29

158 71+800 to 72+600 LHS 19 days December 31, 2018 January 21, 2019 157 12/31 1/21

159 72+600 to 73+500 LHS 40 days October 22, 2018 December 6, 2018 164,74,29 10/22 12/6

160 73+500 to 73+900 LHS 2 days December 7, 2018 December 8, 2018 159 12/7 12/8

161 73+900 to 74+420 LHS 7 days December 10, 2018 December 17, 2018 160 12/10 12/17

162 74+610 to 75+300 LHS 13 days December 18, 2018 January 1, 2019 161 12/18 1/1

163 75+300 to 76+000 LHS 10 days August 24, 2018 September 8, 2018 32FS+3 days 8/24 9/8

164 76+000 to 77+000 LHS 40 days August 24, 2018 October 20, 2018 32FS+3 days 8/24 10/20

165 77+000 to 77+600 LHS 26 days September 10, 2018 October 16, 2018 163 9/10 10/16

166 77+600 to 78+700 LHS 40 days September 14, 2018 November 3, 2018 32FS+15 days 9/14 11/3

167 78+700 to 79+500 LHS 27 days November 22, 2018 December 22, 2018 211 11/22 12/22

168 79+500 to 80+300 LHS 21 days December 24, 2018 January 16, 2019 167 12/24 1/16

169 80+300 to 81+300 LHS 17 days January 17, 2019 February 5, 2019 168 1/17 2/5

170 81+300 to 82+200 LHS 10 days January 22, 2019 February 1, 2019 158 1/22 2/1

171 82+200 to 83+100 LHS 12 days February 2, 2019 February 15, 2019 170 2/2 2/15

172 83+100 to 83+600 LHS 5 days February 16, 2019 February 21, 2019 171 2/16 2/21

173 83+600 to 84+800 RHS 25 days February 22, 2019 March 22, 2019 172 2/22 3/22

174 84+800 to 85+500 RHS 25 days March 7, 2019 April 4, 2019 178 3/7 4/4

175 85+500 to 86+200 RHS-Toll plaza 8 days January 2, 2019 January 10, 2019 162 1/2 1/10

176 86+200 to 86+600 RHS 6 days January 11, 2019 January 17, 2019 175 1/11 1/17

177 86+600 to 87+300 RHS 29 days January 18, 2019 February 20, 2019 176 1/18 2/20

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 6
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
178 87+300 to 88+100 LHS 25 days February 6, 2019 March 6, 2019 169 2/6 3/6

179 88+100 to 89+000 LHS 10 days March 7, 2019 March 18, 2019 178 3/7 3/18

180 Embankment (ECW) 412 days January 18, 2019 June 1, 2020

181 69+000 to 70+000 LHS 20 days May 27, 2019 June 18, 2019 394,257 5/27 6/18

182 70+000 to 70+500 RHS 9 days July 16, 2019 July 25, 2019 395,186 7/16 7/25

183 70+500 to 71+000 LHS 8 days December 18, 2019 December 26, 2019 396,218 12/18 12/26

184 71+000 to 71+800 LHS 11 days July 30, 2019 August 16, 2019 397,256 7/30 8/16

185 71+800 to 72+600 LHS 19 days January 1, 2020 January 22, 2020 398,243 1/1 1/22

186 72+600 to 73+500 LHS 40 days May 6, 2019 June 20, 2019 159,508 5/6 6/20

187 73+500 to 73+900 LHS 2 days January 24, 2019 January 25, 2019 400,208 1/24 1/25

188 73+900 to 74+420 LHS 7 days February 11, 2019 February 18, 2019 401,247 2/11 2/18

189 74+610 to 75+300 LHS 13 days August 10, 2019 August 31, 2019 402,258 8/10 8/31

190 75+300 to 76+000 LHS 10 days January 18, 2019 January 29, 2019 403,269 1/18 1/29

191 76+000 to 77+000 LHS 40 days February 21, 2019 April 8, 2019 404,268 2/21 4/8

192 77+000 to 77+600 LHS 26 days March 7, 2019 April 5, 2019 405,263 3/7 4/5

193 77+600 to 78+700 LHS 40 days May 17, 2019 July 2, 2019 406,266 5/17 7/2

194 78+700 to 79+500 LHS 27 days February 17, 2020 March 18, 2020 407,262 2/17 3/18

195 79+500 to 80+300 LHS 21 days March 27, 2020 April 20, 2020 408,254 3/27 4/20

196 80+300 to 81+300 LHS 17 days June 29, 2019 July 18, 2019 409,241 6/29 7/18

197 81+300 to 82+200 LHS 10 days April 16, 2019 April 26, 2019 410,252 4/16 4/26

198 82+200 to 83+100 LHS 12 days July 15, 2019 July 27, 2019 411,253 7/15 7/27

199 83+100 to 83+600 LHS 5 days January 15, 2020 January 20, 2020 412,265 1/15 1/20

200 83+600 to 84+800 RHS 25 days December 9, 2019 January 6, 2020 413,246 12/9 1/6

201 84+800 to 85+500 RHS 25 days March 8, 2019 April 5, 2019 174SS+1 day 3/8 4/5

202 85+500 to 86+200 RHS-Toll plaza 8 days January 31, 2020 February 8, 2020 415FS+21 days,245 1/31 2/8

203 86+200 to 86+600 RHS 6 days February 25, 2019 March 2, 2019 416,248 2/25 3/2

204 86+600 to 87+300 RHS 29 days April 29, 2020 June 1, 2020 417,255 4/29 6/1

205 87+300 to 88+100 LHS 25 days February 8, 2019 March 8, 2019 178SS+2 days 2/8 3/8

206 88+100 to 89+000 LHS 10 days April 19, 2019 April 30, 2019 419,251 4/19 4/30

207 Embankment (SR / SLR) 51 days September 21, 2018 November 21, 2018

208 72+660 to 73+380 BHS 15 days September 21, 2018 October 10, 2018 151SS+21 days,29 9/21 10/10

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 7
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
209 84+800 to 85+750 BHS 10 days October 17, 2018 October 27, 2018 66,165 10/17 10/27

210 86+150 to 87+000 BHS 14 days October 11, 2018 October 26, 2018 208 10/11 10/26

211 87+200 to 88+030 BHS 16 days November 3, 2018 November 21, 2018 209,68 11/3 11/21

212 Sub Grade 525 days September 8, 2018 June 8, 2020

213 Sub Grade (NCW) 179 days September 8, 2018 April 11, 2019

214 69+000 to 70+000 LHS 10 days November 27, 2018 December 7, 2018 154FS-1 day 11/27 12/7

215 70+000 to 70+500 RHS 5 days December 7, 2018 December 12, 2018 155FS-1 day 12/7 12/12

216 70+500 to 71+000 LHS 5 days December 17, 2018 December 21, 2018 156FS-1 day 12/17 12/21

217 71+000 to 71+800 LHS 8 days December 29, 2018 January 7, 2019 157FS-1 day 12/29 1/7

218 71+800 to 72+600 LHS 8 days January 21, 2019 January 29, 2019 158FS-1 day 1/21 1/29

219 72+600 to 73+500 LHS 11 days December 6, 2018 December 18, 2018 159FS-1 day 12/6 12/18

220 73+500 to 73+900 LHS 4 days December 8, 2018 December 12, 2018 160FS-1 day 12/8 12/12

221 73+900 to 74+420 LHS 6 days December 17, 2018 December 22, 2018 161FS-1 day 12/17 12/22

222 74+610 to 75+300 LHS 7 days January 1, 2019 January 8, 2019 162FS-1 day 1/1 1/8

223 75+300 to 76+000 LHS 7 days September 8, 2018 September 19, 2018 163FS-1 day 9/8 9/19

224 76+000 to 77+000 LHS 10 days October 20, 2018 October 31, 2018 164FS-1 day 10/20 10/31

225 77+000 to 77+600 LHS 6 days October 16, 2018 October 22, 2018 165FS-1 day 10/16 10/22

226 77+600 to 78+700 LHS 11 days November 3, 2018 November 15, 2018 166FS-1 day 11/3 11/15

227 78+700 to 79+500 LHS 8 days December 22, 2018 December 31, 2018 167FS-1 day 12/22 12/31

228 79+500 to 80+300 LHS 8 days January 16, 2019 January 24, 2019 168FS-1 day 1/16 1/24

229 80+300 to 81+300 LHS 10 days February 5, 2019 February 15, 2019 169FS-1 day 2/5 2/15

230 81+300 to 82+200 LHS 9 days February 1, 2019 February 11, 2019 170FS-1 day 2/1 2/11

231 82+200 to 83+100 LHS 9 days February 15, 2019 February 25, 2019 171FS-1 day 2/15 2/25

232 83+100 to 83+600 LHS 5 days February 21, 2019 February 26, 2019 172FS-1 day 2/21 2/26

233 83+600 to 84+800 RHS 12 days March 22, 2019 April 4, 2019 173FS-1 day 3/22 4/4

234 84+800 to 85+500 RHS 7 days April 4, 2019 April 11, 2019 174FS-1 day 4/4 4/11

235 85+500 to 86+200 RHS-Toll plaza 7 days January 10, 2019 January 17, 2019 175FS-1 day 1/10 1/17

236 86+200 to 86+600 RHS 4 days January 17, 2019 January 21, 2019 176FS-1 day 1/17 1/21

237 86+600 to 87+300 RHS 7 days February 20, 2019 February 27, 2019 177FS-1 day 2/20 2/27

238 87+300 to 88+100 LHS 8 days March 6, 2019 March 14, 2019 178FS-1 day 3/6 3/14

239 88+100 to 89+000 LHS 9 days March 18, 2019 March 27, 2019 179FS-1 day 3/18 3/27

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 8
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
240 Sub Grade (ECW) 409 days January 29, 2019 June 8, 2020

241 69+000 to 70+000 LHS 10 days June 18, 2019 June 28, 2019 181FS-1 day 6/18 6/28

242 70+000 to 70+500 RHS 5 days July 25, 2019 July 30, 2019 182FS-1 day 7/25 7/30

243 70+500 to 71+000 LHS 5 days December 26, 2019 December 31, 2019 183FS-1 day 12/26 12/31

244 71+000 to 71+800 LHS 8 days August 16, 2019 August 28, 2019 184FS-1 day 8/16 8/28

245 71+800 to 72+600 LHS 8 days January 22, 2020 January 30, 2020 185FS-1 day 1/22 1/30

246 72+600 to 73+500 LHS 11 days June 20, 2019 July 2, 2019 186FS-1 day,219 6/20 7/2

247 73+500 to 73+900 LHS 4 days February 6, 2019 February 9, 2019 187FS-1 day,250 2/6 2/9

248 73+900 to 74+420 LHS 6 days February 18, 2019 February 23, 2019 188FS-1 day 2/18 2/23

249 74+610 to 75+300 LHS 7 days August 31, 2019 September 11, 2019 189FS-1 day 8/31 9/11

250 75+300 to 76+000 LHS 7 days January 29, 2019 February 5, 2019 190FS-1 day 1/29 2/5

251 76+000 to 77+000 LHS 10 days April 8, 2019 April 18, 2019 191FS-1 day 4/8 4/18

252 77+000 to 77+600 LHS 6 days April 5, 2019 April 11, 2019 192FS-1 day 4/5 4/11

253 77+600 to 78+700 LHS 11 days July 2, 2019 July 13, 2019 193FS-1 day 7/2 7/13

254 78+700 to 79+500 LHS 8 days March 18, 2020 March 26, 2020 194FS-1 day 3/18 3/26

255 79+500 to 80+300 LHS 8 days April 20, 2020 April 28, 2020 195FS-1 day 4/20 4/28

256 80+300 to 81+300 LHS 10 days July 18, 2019 July 29, 2019 196FS-1 day 7/18 7/29

257 81+300 to 82+200 LHS 9 days April 26, 2019 May 6, 2019 197FS-1 day 4/26 5/6

258 82+200 to 83+100 LHS 9 days July 27, 2019 August 9, 2019 198FS-1 day 7/27 8/9

259 83+100 to 83+600 LHS 5 days January 20, 2020 January 24, 2020 199FS-1 day 1/20 1/24

260 83+600 to 84+800 RHS 12 days January 6, 2020 January 18, 2020 200FS-1 day 1/6 1/18

261 84+800 to 85+500 RHS 7 days April 5, 2019 April 12, 2019 201FS-1 day 4/5 4/12

262 85+500 to 86+200 RHS -Toll Plaza 7 days February 8, 2020 February 15, 2020 202FS-1 day 2/8 2/15

263 86+200 to 86+600 RHS 4 days March 2, 2019 March 6, 2019 203FS-1 day 3/2 3/6

264 86+600 to 87+300 RHS 7 days June 1, 2020 June 8, 2020 204FS-1 day 6/1 6/8

265 87+300 to 88+100 LHS 8 days March 8, 2019 March 16, 2019 205FS-1 day 3/8 3/16

266 88+100 to 89+000 LHS 9 days April 30, 2019 May 9, 2019 206FS-1 day 4/30 5/9

267 Sub Grade (SR / SLR) 118 days October 26, 2018 February 20, 2019

268 72+660 to 73+380 BHS 8 days February 12, 2019 February 20, 2019 208FS-1 day,230 2/12 2/20

269 84+800 to 85+750 BHS 22 days October 27, 2018 November 21, 2018 209FS-1 day 10/27 11/21

270 86+150 to 87+000 BHS 20 days October 26, 2018 November 17, 2018 210FS-1 day 10/26 11/17

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 9
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
271 87+200 to 88+030 BHS 19 days November 21, 2018 December 12, 2018 211FS-1 day 11/21 12/12

272 GSB 467 days December 6, 2018 June 22, 2020

273 GSB (NCW) 453 days December 18, 2018 June 17, 2020

274 69+000 to 70+000 LHS 5 days May 10, 2019 May 15, 2019 214,323 5/10 5/15

275 70+000 to 70+500 RHS 3 days June 22, 2019 June 25, 2019 215,277 6/22 6/25

276 70+500 to 71+000 LHS 3 days October 18, 2019 October 21, 2019 216,279 10/18 10/21

277 71+000 to 71+800 LHS 4 days June 18, 2019 June 21, 2019 217,317 6/18 6/21

278 71+800 to 72+600 LHS 4 days October 28, 2019 October 31, 2019 218,306 10/28 10/31

279 72+600 to 73+500 LHS 5 days October 12, 2019 October 17, 2019 219,302 10/12 10/17

280 73+500 to 73+900 LHS 2 days December 27, 2018 December 28, 2018 220,281 12/27 12/28

281 73+900 to 74+420 LHS 3 days December 24, 2018 December 26, 2018 221,283 12/24 12/26

282 74+610 to 75+300 LHS 4 days January 9, 2019 January 12, 2019 222,281 1/9 1/12

283 75+300 to 76+000 LHS 4 days December 18, 2018 December 21, 2018 223FS+30 days,330 12/18 12/21

284 76+000 to 77+000 LHS 5 days January 28, 2019 February 1, 2019 224,285 1/28 2/1

285 77+000 to 77+600 LHS 3 days January 24, 2019 January 26, 2019 225,296 1/24 1/26

286 77+600 to 78+700 LHS 6 days April 27, 2019 May 3, 2019 226,307 4/27 5/3

287 78+700 to 79+500 LHS 4 days November 1, 2019 November 5, 2019 227,278 11/1 11/5

288 79+500 to 80+300 LHS 4 days February 5, 2020 February 8, 2020 228,305 2/5 2/8

289 80+300 to 81+300 LHS 5 days May 25, 2019 May 30, 2019 229,312 5/25 5/30

290 81+300 to 82+200 LHS 5 days April 3, 2019 April 8, 2019 230,299 4/3 4/8

291 82+200 to 83+100 LHS 5 days May 31, 2019 June 5, 2019 231,289 5/31 6/5

292 83+100 to 83+600 LHS 3 days January 4, 2020 January 7, 2020 232,303 1/4 1/7

293 83+600 to 84+800 RHS 6 days September 27, 2019 October 3, 2019 233,304 9/27 10/3

294 84+800 to 85+500 RHS 4 days June 13, 2020 June 17, 2020 234,324 6/13 6/17

295 85+500 to 86+200 RHS -Toll Plaza 4 days October 4, 2019 October 8, 2019 235,293 10/4 10/8

296 86+200 to 86+600 RHS 2 days January 22, 2019 January 23, 2019 236,331 1/22 1/23

297 86+600 to 87+300 RHS 4 days April 1, 2020 April 4, 2020 237,314 4/1 4/4

298 87+300 to 88+100 LHS 4 days February 10, 2020 February 13, 2020 238,288 2/10 2/13

299 88+100 to 89+000 LHS 5 days March 28, 2019 April 2, 2019 239,329 3/28 4/2

300 GSB (ECW) 351 days April 20, 2019 June 22, 2020

301 69+000 to 70+000 RHS 5 days June 29, 2019 July 4, 2019 241,275 6/29 7/4

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 10
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
302 70+000 to 70+500 LHS 3 days October 9, 2019 October 11, 2019 242,295 10/9 10/11

303 70+500 to 71+000 RHS 3 days January 1, 2020 January 3, 2020 243,287 1/1 1/3

304 71+000 to 71+800 RHS 4 days September 20, 2019 September 25, 2019 244,309 9/20 9/25

305 71+800 to 72+600 RHS 4 days January 31, 2020 February 4, 2020 245,292 1/31 2/4

306 72+600 to 73+500 RHS 5 days October 22, 2019 October 26, 2019 246,276 10/22 10/26

307 73+500 to 73+900 RHS 2 days April 25, 2019 April 26, 2019 247,310 4/25 4/26

308 73+900 to 74+420 RHS 3 days May 4, 2019 May 7, 2019 248,286 5/4 5/7

309 74+610 to 75+300 RHS 4 days September 13, 2019 September 18, 2019 249,318 9/13 9/18

310 75+300 to 76+000 RHS 4 days April 20, 2019 April 24, 2019 250,328 4/20 4/24

311 76+000 to 77+000 RHS 5 days May 16, 2019 May 21, 2019 251,274 5/16 5/21

312 77+000 to 77+600 RHS 3 days May 22, 2019 May 24, 2019 252,311 5/22 5/24

313 77+600 to 78+700 RHS 6 days July 15, 2019 July 20, 2019 253,282 7/15 7/20

314 78+700 to 79+500 RHS 4 days March 27, 2020 March 31, 2020 254,319 3/27 3/31

315 79+500 to 80+300 RHS 4 days April 29, 2020 May 2, 2020 255,297 4/29 5/2

316 80+300 to 81+300 RHS 5 days July 30, 2019 August 5, 2019 256,313 7/30 8/5

317 81+300 to 82+200 RHS 5 days June 12, 2019 June 17, 2019 257,326 6/12 6/17

318 82+200 to 83+100 RHS 5 days August 10, 2019 August 17, 2019 258,316 8/10 8/17

319 83+100 to 83+600 RHS 3 days March 2, 2020 March 4, 2020 259,320 3/2 3/4

320 83+600 to 84+800 LHS 6 days February 24, 2020 February 29, 2020 260,322 2/24 2/29

321 84+800 to 85+500 LHS 4 days June 18, 2020 June 22, 2020 261,294 6/18 6/22

322 85+500 to 86+200 LHS Tollplaza 4 days February 19, 2020 February 22, 2020 262,325 2/19 2/22

323 86+200 to 86+600 LHS 2 days May 8, 2019 May 9, 2019 263,308 5/8 5/9

324 86+600 to 87+300 LHS 4 days June 9, 2020 June 12, 2020 264,315 6/9 6/12

325 87+300 to 88+100 RHS 4 days February 14, 2020 February 18, 2020 265,298 2/14 2/18

326 88+100 to 89+000 RHS 5 days June 6, 2019 June 11, 2019 266,291 6/6 6/11

327 GSB (SR / SLR) 135 days December 6, 2018 April 19, 2019

328 72+660 to 73+380 BHS 10 days April 9, 2019 April 19, 2019 268,290 4/9 4/19

329 84+800 to 85+750 BHS 10 days February 2, 2019 February 13, 2019 269,284 2/2 2/13

330 86+150 to 87+000 BHS 10 days December 6, 2018 December 17, 2018 270FS+15 days 12/6 12/17

331 87+200 to 88+030 BHS 10 days December 29, 2018 January 9, 2019 271,280 12/29 1/9

332 WMM TOP Layer 444 days January 4, 2019 June 24, 2020

333 WMM -Top layer (NCW) 437 days January 8, 2019 June 19, 2020

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 11
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
334 69+000 to 70+000 LHS 3 days May 16, 2019 May 18, 2019 274,383 5/16 5/18

335 70+000 to 70+500 RHS 2 days June 26, 2019 June 27, 2019 275,337 6/26 6/27

336 70+500 to 71+000 LHS 2 days October 22, 2019 October 23, 2019 276,339 10/22 10/23

337 71+000 to 71+800 LHS 3 days June 22, 2019 June 25, 2019 277,377 6/22 6/25

338 71+800 to 72+600 LHS 3 days November 1, 2019 November 4, 2019 278,366 11/1 11/4

339 72+600 to 73+500 LHS 3 days October 18, 2019 October 21, 2019 279,362 10/18 10/21

340 73+500 to 73+900 LHS 2 days January 12, 2019 January 14, 2019 280,341 1/12 1/14

341 73+900 to 74+420 LHS 2 days January 10, 2019 January 11, 2019 281,343 1/10 1/11

342 74+610 to 75+300 LHS 2 days July 8, 2019 July 9, 2019 282,361 7/8 7/9

343 75+300 to 76+000 LHS 2 days January 8, 2019 January 9, 2019 283,390 1/8 1/9

344 76+000 to 77+000 LHS 3 days February 2, 2019 February 5, 2019 284,345 2/2 2/5

345 77+000 to 77+600 LHS 2 days January 28, 2019 January 29, 2019 285,356 1/28 1/29

346 77+600 to 78+700 LHS 4 days May 4, 2019 May 8, 2019 286,367 5/4 5/8

347 78+700 to 79+500 LHS 3 days November 6, 2019 November 8, 2019 287,338 11/6 11/8

348 79+500 to 80+300 LHS 3 days February 10, 2020 February 12, 2020 288,365 2/10 2/12

349 80+300 to 81+300 LHS 3 days May 31, 2019 June 3, 2019 289,372 5/31 6/3

350 81+300 to 82+200 LHS 3 days April 9, 2019 April 11, 2019 290,359 4/9 4/11

351 82+200 to 83+100 LHS 3 days June 6, 2019 June 8, 2019 291,349 6/6 6/8

352 83+100 to 83+600 LHS 2 days January 8, 2020 January 9, 2020 292,363 1/8 1/9

353 83+600 to 84+800 RHS 4 days October 4, 2019 October 8, 2019 293,364 10/4 10/8

354 84+800 to 85+500 RHS 2 days June 18, 2020 June 19, 2020 294,384 6/18 6/19

355 85+500 to 86+200 RHS 0 days October 8, 2019 October 8, 2019 295,353 10/8

356 86+200 to 86+600 RHS 2 days January 24, 2019 January 25, 2019 296,391 1/24 1/25

357 86+600 to 87+300 RHS 2 days April 6, 2020 April 7, 2020 297,374 4/6 4/7

358 87+300 to 88+100 LHS 3 days February 14, 2020 February 17, 2020 298,348 2/14 2/17

359 88+100 to 89+000 LHS 3 days April 3, 2019 April 5, 2019 299,389 4/3 4/5

360 WMM- Top Layer (ECW) 349 days April 25, 2019 June 24, 2020

361 69+000 to 70+000 RHS 2 days July 5, 2019 July 6, 2019 301,335 7/5 7/6

362 70+000 to 70+500 LHS 2 days October 12, 2019 October 14, 2019 302,355 10/12 10/14

363 70+500 to 71+000 RHS 2 days January 4, 2020 January 6, 2020 303,347 1/4 1/6

364 71+000 to 71+800 RHS 2 days September 27, 2019 September 28, 2019 304,369 9/27 9/28

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 12
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
365 71+800 to 72+600 RHS 2 days February 5, 2020 February 6, 2020 305,352 2/5 2/6

366 72+600 to 73+500 RHS 2 days October 28, 2019 October 29, 2019 306,336 10/28 10/29

367 73+500 to 73+900 RHS 1 day April 27, 2019 April 27, 2019 307,370 4/27 4/27

368 73+900 to 74+420 RHS 2 days May 9, 2019 May 10, 2019 308,346 5/9 5/10

369 74+610 to 75+300 RHS 2 days September 20, 2019 September 21, 2019 309,378 9/20 9/21

370 75+300 to 76+000 RHS 2 days April 25, 2019 April 26, 2019 310,388 4/25 4/26

371 76+000 to 77+000 RHS 2 days May 22, 2019 May 23, 2019 311,334 5/22 5/23

372 77+000 to 77+600 RHS 2 days May 25, 2019 May 27, 2019 312,371 5/25 5/27

373 77+600 to 78+700 RHS 2 days July 22, 2019 July 23, 2019 313,342 7/22 7/23

374 78+700 to 79+500 RHS 2 days April 1, 2020 April 2, 2020 314,379 4/1 4/2

375 79+500 to 80+300 RHS 2 days May 4, 2020 May 5, 2020 315,357 5/4 5/5

376 80+300 to 81+300 RHS 3 days August 7, 2019 August 10, 2019 316,373 8/7 8/10

377 81+300 to 82+200 RHS 2 days June 18, 2019 June 19, 2019 317,386 6/18 6/19

378 82+200 to 83+100 RHS 2 days August 19, 2019 August 21, 2019 318,376 8/19 8/21

379 83+100 to 83+600 RHS 2 days March 5, 2020 March 6, 2020 319,380 3/5 3/6

380 83+600 to 84+800 LHS 3 days March 2, 2020 March 4, 2020 320,382 3/2 3/4

381 84+800 to 85+500 LHS 2 days June 23, 2020 June 24, 2020 321,354 6/23 6/24

382 85+500 to 86+200 LHS 0 days February 22, 2020 February 22, 2020 322,385 2/22

383 86+200 to 86+600 LHS 1 day May 11, 2019 May 11, 2019 323,368 5/11 5/11

384 86+600 to 87+300 LHS 2 days June 13, 2020 June 15, 2020 324,375 6/13 6/15

385 87+300 to 88+100 RHS 2 days February 19, 2020 February 20, 2020 325,358 2/19 2/20

386 88+100 to 89+000 RHS 2 days June 12, 2019 June 13, 2019 326,351 6/12 6/13

387 WMM-I (SR / SLR) 110 days January 4, 2019 April 23, 2019

388 72+660 to 73+380 BHS 3 days April 20, 2019 April 23, 2019 328,350 4/20 4/23

389 84+800 to 85+750 BHS 3 days February 14, 2019 February 16, 2019 329,344 2/14 2/16

390 86+150 to 87+000 BHS 3 days January 4, 2019 January 7, 2019 330FS+15 days 1/4 1/7

391 87+200 to 88+030 BHS 3 days January 15, 2019 January 17, 2019 331,340 1/15 1/17

392 DBM 455 days January 9, 2019 July 11, 2020

393 DBM (NCW) 446 days January 16, 2019 July 8, 2020

394 69+000 to 70+000 LHS 2 days May 24, 2019 May 25, 2019 334FS+1 day,443 5/24 5/25

395 70+000 to 70+500 RHS 3 days July 12, 2019 July 15, 2019 335FS+1 day,397 7/12 7/15

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 13
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
396 70+500 to 71+000 LHS 3 days December 14, 2019 December 17, 2019 336FS+1 day,399 12/14 12/17

397 71+000 to 71+800 LHS 3 days July 9, 2019 July 11, 2019 337FS+1 day,437 7/9 7/11

398 71+800 to 72+600 LHS 2 days December 23, 2019 December 24, 2019 338FS+1 day,426 12/23 12/24

399 72+600 to 73+500 LHS 2 days December 12, 2019 December 13, 2019 339FS+1 day,415 12/12 12/13

400 73+500 to 73+900 LHS 3 days January 21, 2019 January 23, 2019 340FS+1 day,401 1/21 1/23

401 73+900 to 74+420 LHS 2 days January 18, 2019 January 19, 2019 341FS+1 day,403 1/18 1/19

402 74+610 to 75+300 LHS 4 days July 23, 2019 July 26, 2019 342FS+1 day,421 7/23 7/26

403 75+300 to 76+000 LHS 2 days January 16, 2019 January 17, 2019 343FS+1 day,450 1/16 1/17

404 76+000 to 77+000 LHS 4 days February 7, 2019 February 11, 2019 344FS+1 day,405 2/7 2/11

405 77+000 to 77+600 LHS 3 days February 4, 2019 February 6, 2019 345FS+1 day,416 2/4 2/6

406 77+600 to 78+700 LHS 3 days May 14, 2019 May 16, 2019 346FS+1 day,427 5/14 5/16

407 78+700 to 79+500 LHS 4 days December 25, 2019 December 28, 2019 347FS+1 day,398 12/25 12/28

408 79+500 to 80+300 LHS 3 days February 25, 2020 February 27, 2020 348FS+1 day,458 2/25 2/27

409 80+300 to 81+300 LHS 3 days June 7, 2019 June 10, 2019 349FS+1 day,432 6/7 6/10

410 81+300 to 82+200 LHS 2 days April 13, 2019 April 15, 2019 350FS+1 day,419 4/13 4/15

411 82+200 to 83+100 LHS 4 days June 22, 2019 June 26, 2019 351FS+1 day,465 6/22 6/26

412 83+100 to 83+600 LHS 3 days January 11, 2020 January 14, 2020 352FS+1 day,423 1/11 1/14

413 83+600 to 84+800 RHS 3 days December 5, 2019 December 7, 2019 353FS+1 day,462 12/5 12/7

414 84+800 to 85+500 RHS 1 day July 8, 2020 July 8, 2020 354FS+1 day,475 7/8 7/8

415 85+500 to 86+200 RHS 0 days December 11, 2019 December 11, 2019 355FS+7 days,422 12/11

416 86+200 to 86+600 RHS 3 days January 31, 2019 February 2, 2019 356FS+1 day,451 1/31 2/2

417 86+600 to 87+300 RHS 3 days April 10, 2020 April 13, 2020 357FS+1 day,434 4/10 4/13

418 87+300 to 88+100 LHS 3 days February 28, 2020 March 2, 2020 358FS+1 day,408 2/28 3/2

419 88+100 to 89+000 LHS 4 days April 8, 2019 April 11, 2019 359FS+1 day,509 4/8 4/11

420 DBM (ECW) 355 days May 6, 2019 July 11, 2020

421 69+000 to 70+000 RHS 6 days July 16, 2019 July 22, 2019 361FS+1 day,395 7/16 7/22

422 70+000 to 70+500 LHS 3 days December 9, 2019 December 11, 2019 362FS+1 day,413 12/9 12/11

423 70+500 to 71+000 RHS 3 days January 8, 2020 January 10, 2020 363FS+1 day,407 1/8 1/10

424 71+000 to 71+800 RHS 5 days November 20, 2019 November 25, 2019 364FS+1 day,429 11/20 11/25

425 71+800 to 72+600 RHS 5 days February 8, 2020 February 13, 2020 365FS+1 day,457 2/8 2/13

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 14
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
426 72+600 to 73+500 RHS 4 days December 18, 2019 December 21, 2019 366FS+1 day,396 12/18 12/21

427 73+500 to 73+900 RHS 3 days May 10, 2019 May 13, 2019 367FS+1 day,430 5/10 5/13

428 73+900 to 74+420 RHS 3 days May 17, 2019 May 20, 2019 368FS+1 day,406 5/17 5/20

429 74+610 to 75+300 RHS 4 days November 15, 2019 November 19, 2019 369FS+1 day,471 11/15 11/19

430 75+300 to 76+000 RHS 4 days May 6, 2019 May 9, 2019 370FS+1 day,508 5/6 5/9

431 76+000 to 77+000 RHS 6 days May 27, 2019 June 1, 2019 371FS+1 day,394 5/27 6/1

432 77+000 to 77+600 RHS 4 days June 3, 2019 June 6, 2019 372FS+1 day,431 6/3 6/6

433 77+600 to 78+700 RHS 6 days July 27, 2019 August 3, 2019 373FS+1 day,402 7/27 8/3

434 78+700 to 79+500 RHS 5 days April 4, 2020 April 9, 2020 374FS+1 day,439 4/4 4/9

435 79+500 to 80+300 RHS 5 days May 7, 2020 May 12, 2020 375FS+1 day,417 5/7 5/12

436 80+300 to 81+300 RHS 6 days August 14, 2019 August 23, 2019 376FS+1 day,433 8/14 8/23

437 81+300 to 82+200 RHS 5 days July 3, 2019 July 8, 2019 377FS+1 day,446 7/3 7/8

438 82+200 to 83+100 RHS 5 days August 24, 2019 August 31, 2019 378FS+1 day,436 8/24 8/31

439 83+100 to 83+600 RHS 3 days March 14, 2020 March 17, 2020 379FS+1 day,442 3/14 3/17

440 83+600 to 84+800 LHS 7 days March 6, 2020 March 13, 2020 380FS+1 day,445 3/6 3/13

441 84+800 to 85+500 LHS 3 days July 9, 2020 July 11, 2020 381FS+1 day,414 7/9 7/11

442 85+500 to 86+200 LHS 0 days March 13, 2020 March 13, 2020 382FS+7 days,440 3/13

443 86+200 to 86+600 LHS 3 days May 21, 2019 May 23, 2019 383FS+1 day,428 5/21 5/23

444 86+600 to 87+300 LHS 4 days June 17, 2020 June 20, 2020 384FS+1 day,468 6/17 6/20

445 87+300 to 88+100 RHS 3 days March 3, 2020 March 5, 2020 385FS+1 day,418 3/3 3/5

446 88+100 to 89+000 RHS 5 days June 27, 2019 July 2, 2019 386FS+1 day,411 6/27 7/2

447 DBM (SR / SLR) 112 days January 9, 2019 April 30, 2019

448 72+660 to 73+380 BHS 5 days April 25, 2019 April 30, 2019 388FS+1 day,410 4/25 4/30

449 84+800 to 85+750 BHS 7 days February 19, 2019 February 26, 2019 389FS+1 day,510 2/19 2/26

450 86+150 to 87+000 BHS 6 days January 9, 2019 January 15, 2019 390FS+1 day 1/9 1/15

451 87+200 to 88+030 BHS 6 days January 24, 2019 January 30, 2019 391FS+1 day,400 1/24 1/30

452 BC 437 days February 12, 2019 July 24, 2020

453 BC (NCW) 330 days June 17, 2019 July 24, 2020

454 69+000 to 70+000 LHS 2 days January 22, 2020 January 23, 2020 394FS+1 day,481 1/22 1/23

455 70+000 to 70+500 RHS 1 day January 24, 2020 January 24, 2020 395FS+1 day,482,454 1/24 1/24

456 70+500 to 71+000 LHS 1 day January 25, 2020 January 25, 2020 396FS+1 day,483,455 1/25 1/25

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 15
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
457 71+000 to 71+800 LHS 2 days January 27, 2020 January 28, 2020 397FS+1 day,484,456 1/27 1/28

458 71+800 to 72+600 LHS 2 days February 22, 2020 February 24, 2020 398FS+1 day,485,459 2/22 2/24

459 72+600 to 73+500 LHS 2 days February 20, 2020 February 21, 2020 399FS+1 day,486 2/20 2/21

460 73+500 to 73+900 LHS 1 day November 30, 2019 November 30, 2019 400FS+1 day,487 11/30 11/30

461 73+900 to 74+420 LHS 1 day December 2, 2019 December 2, 2019 401FS+1 day,488,460 12/2 12/2

462 74+610 to 75+300 LHS 2 days December 3, 2019 December 4, 2019 402FS+1 day,489,461 12/3 12/4

463 75+300 to 76+000 LHS 2 days June 17, 2019 June 18, 2019 403FS+1 day,490 6/17 6/18

464 76+000 to 77+000 LHS 2 days June 19, 2019 June 20, 2019 404FS+1 day,491,463 6/19 6/20

465 77+000 to 77+600 LHS 1 day June 21, 2019 June 21, 2019 405FS+1 day,492,464 6/21 6/21

466 77+600 to 78+700 LHS 2 days May 21, 2020 May 22, 2020 406FS+1 day,493 5/21 5/22

467 78+700 to 79+500 LHS 2 days May 23, 2020 May 25, 2020 407FS+1 day,494,466 5/23 5/25

468 79+500 to 80+300 LHS 2 days May 26, 2020 May 27, 2020 408FS+1 day,495,467 5/26 5/27

469 80+300 to 81+300 LHS 2 days November 8, 2019 November 9, 2019 409FS+1 day,496 11/8 11/9

470 81+300 to 82+200 LHS 2 days November 11, 2019 November 12, 2019 410FS+1 day,497,469 11/11 11/12

471 82+200 to 83+100 LHS 2 days November 13, 2019 November 14, 2019 411FS+1 day,498,470 11/13 11/14

472 83+100 to 83+600 LHS 1 day July 20, 2020 July 20, 2020 412FS+1 day,499 7/20 7/20

473 83+600 to 84+800 RHS 2 days July 21, 2020 July 22, 2020 413FS+1 day,500,472 7/21 7/22

474 84+800 to 85+500 RHS 2 days July 23, 2020 July 24, 2020 414FS+1 day,473 7/23 7/24

475 85+500 to 86+200 RHS-toll plaza 0 days July 7, 2020 July 7, 2020 415FS+21 days,502,476 7/7

476 86+200 to 86+600 RHS 1 day July 7, 2020 July 7, 2020 416FS+1 day,503,477 7/7 7/7

477 86+600 to 87+300 RHS 2 days July 4, 2020 July 6, 2020 417FS+1 day,504,478,589 7/4 7/6

478 87+300 to 88+100 LHS 2 days July 2, 2020 July 3, 2020 418FS+1 day,479 7/2 7/3

479 88+100 to 89+000 LHS 2 days June 30, 2020 July 1, 2020 419FS+1 day,506 6/30 7/1

480 BC (ECW) 330 days June 11, 2019 July 18, 2020

507 BC (SR / SLR) 82 days February 12, 2019 May 4, 2019

512 Structure Works 641 days May 3, 2018 June 27, 2020

513 Minor Bridge @ Ch: 72+680 (Length: 27 Mtr) 108 days April 3, 2019 August 9, 2019 520

514 Foundation 45 days April 3, 2019 May 24, 2019 515SF+26 days 4/3 5/24

515 Sub Structure 60 days April 3, 2019 June 11, 2019 219FF-60 days 4/3 6/11

516 Super Structure 75 days May 11, 2019 August 9, 2019 515SS+33 days 5/11 8/9

517 Minor Bridge(SR) @ Ch: 72+680 (Length: 27 Mtr) 125 days November 8, 2018 April 2, 2019

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 16
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
518 Foundation 45 days December 10, 2018 January 30, 2019 519SF+72 days 12/10 1/30

519 Sub Structure 90 days November 8, 2018 February 20, 2019 268FF 11/8 2/20

520 Super Structure 90 days December 19, 2018 April 2, 2019 519SS+35 days 12/19 4/2

521 Minor Bridge(Recon) @ Ch: 72+680 (Length: 27 Mtr) 127 days July 9, 2019 December 23, 2019 508

522 Foundation 45 days July 9, 2019 September 13, 2019 516FS-25 days 7/9 9/13

523 Sub Structure 60 days July 31, 2019 October 28, 2019 522FS-26 days 7/31 10/28

524 Super Structure 75 days September 27, 2019 December 23, 2019 523SS+33 days 9/27 12/23

525 VOP @ Ch: 72+995 (Length: 30 Mtr) 90 days May 13, 2019 September 6, 2019 508,560

526 Foundation 90 days May 13, 2019 September 6, 2019 527SF+45 days 5/13 9/6

527 Sub Structure 90 days May 13, 2019 September 6, 2019 219FF-11 days 5/13 9/6

528 Super Structure 60 days May 14, 2019 July 22, 2019 527SS+1 day 5/14 7/22

529 Minor Bridge @ Ch: 73+360 (Length: 36 Mtr) 163 days April 5, 2019 October 31, 2019 536

530 Foundation 60 days April 5, 2019 June 13, 2019 536 4/5 6/13

531 Sub Structure 90 days April 29, 2019 August 16, 2019 530SS+20 days 4/29 8/16

532 Super Structure 90 days June 29, 2019 October 31, 2019 531SS+53 days 6/29 10/31

533 Minor Bridge(SR) @ Ch: 73+360 (Length: 36 Mtr) 162 days September 28, 2018 April 4, 2019

534 Foundation 60 days September 28, 2018 December 6, 2018 535SF+40 days 9/28 12/6

535 Sub Structure 90 days October 22, 2018 February 2, 2019 268FF-15 days 10/22 2/2

536 Super Structure 90 days December 21, 2018 April 4, 2019 535SS+52 days 12/21 4/4

537 Minor Bridge(Recon) @ Ch: 73+360 (Length: 36 Mtr) 161 days November 1, 2019 May 6, 2020 508

538 Foundation 60 days November 1, 2019 January 9, 2020 532 11/1 1/9

539 Sub Structure 90 days November 25, 2019 March 7, 2020 538SS+20 days 11/25 3/7

540 Super Structure 90 days January 23, 2020 May 6, 2020 539SS+51 days 1/23 5/6

541 Minor Bridge @ Ch: 74+985 (Length: 17.40 Mtr) 75 days April 5, 2019 July 1, 2019 536

542 Foundation 45 days April 5, 2019 May 27, 2019 543SF 4/5 5/27

543 Sub Structure 30 days April 5, 2019 May 9, 2019 162FF-53 days 4/5 5/9

544 Super Structure 45 days May 10, 2019 July 1, 2019 543 5/10 7/1

545 Minor Bridge(Recon) @ Ch: 74+985 (Length: 17.40 Mtr) 120 days October 7, 2019 February 22, 2020 402

546 Foundation 45 days October 7, 2019 November 27, 2019 556 10/7 11/27

547 Sub Structure 30 days November 28, 2019 January 1, 2020 546 11/28 1/1

548 Super Structure 45 days January 2, 2020 February 22, 2020 547 1/2 2/22

549 Minor Bridge @ Ch: 78+060 (Length: 8.10 Mtr) 105 days August 10, 2018 December 26, 2018

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 17
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
550 Foundation 25 days August 10, 2018 September 22, 2018 551SF 8/10 9/22

551 Sub Structure 35 days September 22, 2018 November 3, 2018 166FF 9/22 11/3

552 Super Structure 45 days November 5, 2018 December 26, 2018 551 11/5 12/26

553 Minor Bridge(Recon) @ Ch: 78+060 (Length: 8.10 Mtr) 105 days May 17, 2019 October 5, 2019 406

554 Foundation 25 days May 17, 2019 June 14, 2019 552 5/17 6/14

555 Sub Structure 35 days June 15, 2019 July 25, 2019 554 6/15 7/25

556 Super Structure 45 days July 26, 2019 October 5, 2019 555 7/26 10/5

557 Minor Bridge @ Ch: 80+155 (Length: 8.10 Mtr) 80 days February 8, 2019 May 11, 2019 585

558 Foundation 25 days February 8, 2019 March 8, 2019 559SF 2/8 3/8

559 Sub Structure 35 days February 8, 2019 March 20, 2019 168FF-280 days 2/8 3/20

560 Super Structure 45 days March 21, 2019 May 11, 2019 559 3/21 5/11

561 Minor Bridge(Recon) @ Ch: 80+155 (Length: 8.10 Mtr) 45 days May 7, 2020 June 27, 2020 408

562 Foundation 15 days May 7, 2020 May 23, 2020 540 5/7 5/23

563 Sub Structure 15 days May 25, 2020 June 10, 2020 562 5/25 6/10

564 Super Structure 15 days June 11, 2020 June 27, 2020 563 6/11 6/27

565 Minor Bridge(Recon) @ Ch: 81+042 (Length: 21 Mtr) 108 days June 11, 2019 November 2, 2019 409,593

566 Foundation 45 days June 11, 2019 August 2, 2019 6/11 8/2

567 Sub Structure 35 days July 16, 2019 September 6, 2019 566SS+30 days 7/16 9/6

568 Super Structure 45 days September 4, 2019 November 2, 2019 567FS-2 days 9/4 11/2

569 Minor Bridge @ Ch: 84+295 (Length: 35.20 Mtr) 140 days February 8, 2019 July 20, 2019 585

570 Foundation 60 days February 8, 2019 April 18, 2019 571SF+40 days 2/8 4/18

571 Sub Structure 105 days February 8, 2019 June 10, 2019 173FF-117 days 2/8 6/10

572 Super Structure 90 days April 8, 2019 July 20, 2019 571SS+50 days 4/8 7/20

573 PUP @ Ch: 84+975 (Length: 7 Mtr) 269 days July 22, 2019 June 18, 2020 509,572

574 Foundation 30 days July 22, 2019 September 6, 2019 572 7/22 9/6

575 Sub Structure 30 days September 7, 2019 October 18, 2019 574 9/7 10/18

576 Super Structure 45 days October 19, 2019 December 10, 2019 575 10/19 12/10

577 Approaches (RE Wall Erection) 134 days January 15, 2020 June 18, 2020 174SS-15 days,321FF-3 days 1/15 6/18

578 Minor Bridge @ Ch: 86+836 (Length: 17.40 Mtr) 120 days November 4, 2019 March 21, 2020 568

579 Foundation 45 days November 4, 2019 December 25, 2019 568 11/4 12/25

580 Sub Structure 30 days December 26, 2019 January 29, 2020 579 12/26 1/29

581 Super Structure 45 days January 30, 2020 March 21, 2020 580 1/30 3/21

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone

Page 18
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME

ID Task Name Duration Start Finish Predecessors 2018 2019 2020


Mar Apr MayJun Jul AugSep Oct NovDec JanFebMar Apr MayJun Jul AugSep Oct NovDec Jan FebMar Apr MayJun Jul AugSep Oct NovDec Jan
582 Minor Bridge(SR) @ Ch: 86+836 (Length: 17.40 Mtr) 120 days September 17, 2018 February 7, 2019

583 Foundation 45 days September 17, 2018 November 13, 2018 584SF 9/17 11/13

584 Sub Structure 30 days November 13, 2018 December 17, 2018 330FF 11/13 12/17

585 Super Structure 45 days December 18, 2018 February 7, 2019 584 12/18 2/7

586 Major Bridge @ Ch: 87+105 (Length: 61.80 Mtr) 230 days June 14, 2019 March 27, 2020 544FS-15 days

587 Foundation 100 days June 14, 2019 October 28, 2019 544FS-15 days 6/14 10/28

588 Sub Structure 140 days July 13, 2019 January 11, 2020 587SS+25 days 7/13 1/11

589 Super Structure 170 days September 4, 2019 March 27, 2020 588SS+35 days 9/4 3/27

590 PUP @ Ch: 87+530 (Length: 7 Mtr) 296 days February 15, 2019 February 14, 2020 511

591 Foundation 30 days February 15, 2019 March 21, 2019 592SF 2/15 3/21

592 Sub Structure 30 days February 15, 2019 March 21, 2019 178FF-246 days 2/15 3/21

593 Super Structure 45 days March 22, 2019 May 13, 2019 592 3/22 5/13

594 Approaches (RE Wall Erection) 138 days August 28, 2019 February 14, 2020 325FF-3 days,178SS-15 days 8/28 2/14

595 Culverts & Misc. Works 500 days May 3, 2018 January 15, 2020 151FF+15 days 5/3 1/15

596 RE Wall Casting 365 days May 3, 2018 July 22, 2019 5/3 7/22

597 Toll Plaza Construction 270 days July 23, 2019 June 20, 2020

598 PQC / DLC 120 days February 3, 2020 June 20, 2020 355SS,502FF 2/3 6/20

599 Tunnel Construction 180 days July 23, 2019 March 7, 2020 598SS-150 days 7/23 3/7

600 Toll Booth Construction 150 days September 9, 2019 March 7, 2020 599SS+30 days 9/9 3/7

601 Toll Plaza Building Construction 220 days July 23, 2019 April 23, 2020 599SS 7/23 4/23

602 Canopy Erection & Fixing 30 days March 9, 2020 April 11, 2020 600 3/9 4/11

603 HTMS and All Ancillary Works 30 days February 14, 2020 March 19, 2020 600FS-20 days 2/14 3/19

Task Rolled Up Progress Inactive Milestone Manual Summary Progress


Milestone Split Inactive Summary Start-only Deadline
Project: RIDPL Draft WP-IJM Summary External Tasks Manual Task Finish-only
Rolled Up Task Project Summary Duration-only External Tasks
Rolled Up Milestone Group By Summary Manual Summary Rollup External Milestone