CONSTRUCTION PROGRAMME
4 Work order and appointed date 0 days August 1, 2018 August 1, 2018 3FS+91 days 8/1
5 Milestone-I (165 days) 0 days January 13, 2019 January 13, 2019 4FS+165 days 1/13
6 Milestone-II (360 days) 0 days July 27, 2019 July 27, 2019 4FS+360 days 7/27
7 Milestone-III (585 days) 0 days March 8, 2020 March 8, 2020 4FS+585 days 3/8
8 Milestone-IV (810 days) scheduled completion date 0 days October 19, 2020 October 19, 2020 4FS+810 days 10/19
9 Permission of Trees removal from concrened authority 0 days July 31, 2018 July 31, 2018 3FS+90 days 7/31
10 Permission of Trees tranplantation and WO. 0 days July 1, 2018 July 1, 2018 3FS+60 days 7/1
11 Land clearence and encroachment removal permission from Concerned 0 days July 31, 2018 July 31, 2018 3FS+90 days 7/31
authority
12 Permission for Electrical poles shifting from Entity owning authority 0 days July 31, 2018 July 31, 2018 3FS+90 days 7/31
13 Permission for water line shifting from Entity owning authority 0 days August 30, 2018 August 30, 2018 3FS+120 days 8/30
15 Pre Construction Activities 570 days May 18, 2018 December 8, 2019
16 Camp and Office 75 days May 18, 2018 July 31, 2018 3FS+15 days 5/18 7/31
17 Site Laboratory 75 days May 18, 2018 July 31, 2018 3FS+15 days 5/18 7/31
18 RMC-30 CUM- 1 75 days May 24, 2018 August 6, 2018 3FS+21 days 5/24 8/6
19 RMC-30 CUM-2 60 days August 22, 2018 October 20, 2018 18FS+15 days 8/22 10/20
20 WMM Plant -200 TPH 30 days August 17, 2018 September 15, 2018 4FS+15 days 8/17 9/15
21 HOT MIX PLANT-124 TPH 60 days August 17, 2018 October 15, 2018 4FS+15 days 8/17 10/15
22 Crusher installaton 90 days June 2, 2018 August 30, 2018 3FS+30 days 6/2 8/30
23 Joint survey and detailing 30 days May 18, 2018 June 16, 2018 3FS+15 days 5/18 6/16
24 ROW Fixing 75 days May 18, 2018 July 31, 2018 3FS+15 days 5/18 7/31
25 Trees tranplantation below 1.2 m girth size 60 days July 9, 2018 September 6, 2018 10FS+7 days,23 7/9 9/6
26 Trees felling above 1.2 m girth size 30 days August 8, 2018 September 6, 2018 9FS+7 days,23 8/8 9/6
27 Electrical poles shiftng by Enitnty owning 30 days August 8, 2018 September 6, 2018 12FS+7 days,23 8/8 9/6
28 Water line shifting by entity owning authority 30 days September 15, 2018 October 14, 2018 13FS+15 days,23 9/15 10/14
29 Encroachment Removal 15 days August 16, 2018 August 30, 2018 11FS+15 days 8/16 8/30
30 others and land clearneces 30 days August 16, 2018 September 14, 2018 11FS+15 days 8/16 9/14
Page 1
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
32 Issue of working Drawings- from km 69.00 to 89.00 1 day August 17, 2018 August 17, 2018 4FS+15 days 8/17 8/17
34 Issue of working Drawings- from km 69.00 to 89.00 1 day August 19, 2018 August 19, 2018 32SS+2 days 8/19 8/19
36 Issue of working Drawings- from km 69.00 to 89.00 1 day August 19, 2018 August 19, 2018 32SS+2 days 8/19 8/19
37 Issue of Working Drawing for HPC 153 days August 17, 2018 January 16, 2019
38 @75.660 -HPC 1 day August 25, 2018 August 25, 2018 32FS+7 days 8/25 8/25
39 @70.323-HPC 1 day August 27, 2018 August 27, 2018 38FS+1 day 8/27 8/27
40 @ 70.664-HPC 1 day August 29, 2018 August 29, 2018 39FS+1 day 8/29 8/29
41 @ 70.807-HPC 1 day August 31, 2018 August 31, 2018 40FS+1 day 8/31 8/31
42 @71.087-HPC 1 day September 2, 2018 September 2, 2018 41FS+1 day 9/2 9/2
43 @ 71.125-HPC 1 day September 4, 2018 September 4, 2018 42FS+1 day 9/4 9/4
44 @71.402-HPC 1 day September 6, 2018 September 6, 2018 43FS+1 day 9/6 9/6
45 @ 74.708-HPC 1 day September 8, 2018 September 8, 2018 44FS+1 day 9/8 9/8
46 @69.807 -HPC 1 day September 10, 2018 September 10, 2018 45FS+1 day 9/10 9/10
47 @77.025-HPC 1 day September 12, 2018 September 12, 2018 46FS+1 day 9/12 9/12
48 @78.33-HPC 1 day September 14, 2018 September 14, 2018 47FS+1 day 9/14 9/14
49 @78.774-HPC 1 day September 16, 2018 September 16, 2018 48FS+1 day 9/16 9/16
50 @78.99 - HPC 1 day September 18, 2018 September 18, 2018 49FS+1 day 9/18 9/18
51 @80.287-HPC 1 day September 20, 2018 September 20, 2018 50FS+1 day 9/20 9/20
52 @ 80.665-HPC 1 day September 22, 2018 September 22, 2018 51FS+1 day 9/22 9/22
53 @ 83.185-HPC 1 day September 24, 2018 September 24, 2018 52FS+1 day 9/24 9/24
54 @ 83.42-HPC 1 day September 26, 2018 September 26, 2018 53FS+1 day 9/26 9/26
55 @ 83.57-HPC 1 day September 28, 2018 September 28, 2018 54FS+1 day 9/28 9/28
56 @ 83.800- HPC 1 day September 30, 2018 September 30, 2018 55FS+1 day 9/30 9/30
57 @ 83.845-HPC 1 day September 30, 2018 September 30, 2018 55FS+1 day 9/30 9/30
58 @ 84.75-HPC 1 day October 2, 2018 October 2, 2018 56FS+1 day 10/2 10/2
59 @84.989-HPC 1 day October 2, 2018 October 2, 2018 57FS+1 day 10/2 10/2
60 @87.926-HPC 1 day October 4, 2018 October 4, 2018 58FS+1 day 10/4 10/4
61 Issue of Working Drawing for BOX Culvert 17 days September 2, 2018 September 18, 2018
62 @74.375- Box culvert 1 day September 2, 2018 September 2, 2018 32FS+15 days 9/2 9/2
Page 2
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
64 PUP and slip road/service road 47 days September 17, 2018 November 2, 2018
65 Issue of working Drawings (GAD/RCC/Plan and 47 days September 17, 2018 November 2, 2018
profile/cross section)
66 Issue of @ 84.975- PUP Structure RCC/GAD Drawing 1 day September 17, 2018 September 17, 2018 32FS+30 days 9/17 9/17
67 Preperation and Submission RE Wall design 30 days September 19, 2018 October 18, 2018 66FS+1 day 9/19 10/18
68 Approval of RE Wall Design 15 days October 19, 2018 November 2, 2018 67 10/19 11/2
69 Issue of @ 87.530- PUP Structure RCC/GAD Drawing 1 day September 17, 2018 September 17, 2018 32FS+30 days 9/17 9/17
70 Preperation and Submission RE Wall design 30 days September 19, 2018 October 18, 2018 69FS+1 day 9/19 10/18
71 Approval of RE Wall Design 15 days October 19, 2018 November 2, 2018 70 10/19 11/2
72 VOP- Horti village 1 day September 17, 2018 September 17, 2018
73 Issue of working Drawings (GAD/RCC/Plan and 1 day September 17, 2018 September 17, 2018
profile/cross section)
74 @ 72.995 -VOP strucutres/RCC wall/ Draiange plan 1 day September 17, 2018 September 17, 2018 32FS+30 days 9/17 9/17
75 Service road- plan and profile/cross section from 72.660 to 1 day September 17, 2018 September 17, 2018 74SS 9/17 9/17
73.380
77 Issue of working Drawings (GAD/RCC/Plan and 1 day October 17, 2018 October 17, 2018
profile/cross section)
78 @ 87.105 -GAD/RCC drawings 1 day September 17, 2018 September 17, 2018 32FS+30 days 9/17 9/17
79 MINOR BRIDGES 153 days August 17, 2018 January 16, 2019
80 Issue of working Drawings (GAD/RCC/Plan and 76 days September 2, 2018 November 16, 2018
profile/cross section)
81 @ 68.984- ( RHS and LHS) 1 day September 2, 2018 September 2, 2018 32FS+15 days 9/2 9/2
82 @ 72.680 -( RHS,LHS, Service road RHS, Service road 1 day September 25, 2018 September 25, 2018 75FS+7 days 9/25 9/25
LHS)
83 @73.380 -( RHS,LHS, Service road RHS, Service road 1 day September 25, 2018 September 25, 2018 75FS+7 days 9/25 9/25
LHS)
84 @ 74.985- ( RHS and LHS) 1 day September 2, 2018 September 2, 2018 32FS+15 days 9/2 9/2
Page 3
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
86 @ 80.155- ( RHS and LHS) 1 day October 2, 2018 October 2, 2018 32FS+45 days 10/2 10/2
87 @ 81.045- ( RHS and LHS) 1 day October 17, 2018 October 17, 2018 32FS+60 days 10/17 10/17
88 @ 84.295- ( RHS and LHS) 1 day November 1, 2018 November 1, 2018 32FS+75 days 11/1 11/1
89 @86.836 -( RHS,LHS, Service road RHS, Service road 1 day November 16, 2018 November 16, 2018 32FS+90 days 11/16 11/16
LHS)
90 Junctions drawing and details 1 day November 17, 2018 November 17, 2018
91 Issue of working Drawings 1 day November 17, 2018 November 17, 2018 89 11/17 11/17
92 Bus-bay/truck lay bye darwing and details 1 day November 17, 2018 November 17, 2018
93 Issue of working Drawings 1 day November 17, 2018 November 17, 2018 89 11/17 11/17
94 DRAINAGE, PROTECTION WORK & RCC WALL 1 day September 24, 2018 September 24, 2018
95 Issue of working Drawings 1 day September 24, 2018 September 24, 2018 75SS+7 days 9/24 9/24
96 Footpath Drain RCC drawing 1 day September 24, 2018 September 24, 2018
97 Issue of working Drawings 1 day September 24, 2018 September 24, 2018 75SS+7 days 9/24 9/24
99 Issue of working Drawings 1 day August 17, 2018 August 17, 2018 4FS+15 days 8/17 8/17
100 Miscellenious 153 days August 17, 2018 January 16, 2019
101 Toll Plaza ( Plan/profile/crosssection) 1 day August 17, 2018 August 17, 2018
102 Issue of working Drawings 1 day August 17, 2018 August 17, 2018 4FS+15 days 8/17 8/17
104 Issue of working Drawings 1 day September 2, 2018 September 2, 2018 102FS+15 days 9/2 9/2
105 ROAD furniture and safety devices 1 day January 16, 2019 January 16, 2019
106 Issue of working Drawings 1 day January 16, 2019 January 16, 2019 89FS+60 days 1/16 1/16
107 Miscellenious and Crash barrier 1 day January 16, 2019 January 16, 2019
108 Issue of working Drawings 1 day January 16, 2019 January 16, 2019 89FS+60 days 1/16 1/16
109 Quality control Documentation 60 days June 2, 2018 July 31, 2018
110 QAP Approval 60 days June 2, 2018 July 31, 2018 3FS+30 days 6/2 7/31
111 Project safety plan 60 days June 2, 2018 July 31, 2018 110SS 6/2 7/31
112 Traffic Management Plan 60 days June 2, 2018 July 31, 2018 111SS 6/2 7/31
113 Aggregate Production 510 days July 17, 2018 December 8, 2019
114 Outsourced for M-15/M-20 concrete for Initial work 60 days July 17, 2018 September 14, 2018 3FS+75 days 7/17 9/14
Page 4
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
116 Source Approval 300 days May 18, 2018 March 13, 2019
117 Stone quarry 90 days May 18, 2018 August 15, 2018 3FS+15 days 5/18 8/15
118 Murum quarry 300 days May 18, 2018 March 13, 2019 3FS+15 days 5/18 3/13
119 Cement 45 days July 2, 2018 August 15, 2018 3FS+60 days 7/2 8/15
120 steel - 45 days July 2, 2018 August 15, 2018 3FS+60 days 7/2 8/15
121 Water 45 days July 2, 2018 August 15, 2018 3FS+60 days 7/2 8/15
122 Sand 45 days July 17, 2018 August 30, 2018 3FS+75 days 7/17 8/30
123 Coarse Aggregate 60 days July 18, 2018 September 15, 2018 114SS+1 day 7/18 9/15
124 Fine Aggregate 60 days July 18, 2018 September 15, 2018 114SS+1 day 7/18 9/15
125 Admitxture 45 days July 19, 2018 September 1, 2018 114SS+2 days 7/19 9/1
126 RCC Pipes 45 days July 2, 2018 August 15, 2018 3FS+60 days 7/2 8/15
127 Bitumen 45 days August 11, 2018 September 24, 2018 3FS+100 days 8/11 9/24
129 M-15 30 days July 19, 2018 August 17, 2018 119SS,121SS,122SS,123SS,124SS,125SS
7/19 8/17
130 M-20 30 days July 19, 2018 August 17, 2018 129SS 7/19 8/17
131 M-25 45 days July 20, 2018 September 2, 2018 130SS+1 day 7/20 9/2
132 M-30 45 days July 21, 2018 September 3, 2018 131SS+1 day 7/21 9/3
133 M-40 and 45 45 days July 22, 2018 September 4, 2018 132SS+1 day 7/22 9/4
134 DLC-M 10 45 days August 6, 2018 September 19, 2018 133SS+15 days 8/6 9/19
135 PQC-M-40 45 days August 6, 2018 September 19, 2018 133SS+15 days 8/6 9/19
136 GSB 7 days September 16, 2018 September 22, 2018 115SS+1 day 9/16 9/22
137 WMM 7 days September 16, 2018 September 22, 2018 115SS+1 day 9/16 9/22
138 DBM 7 days September 26, 2018 October 2, 2018 127FS+1 day 9/26 10/2
140 Field trail 3 days October 16, 2018 October 18, 2018
141 DBM 2 days October 16, 2018 October 17, 2018 21,138 10/16 10/17
142 BC 1 day October 18, 2018 October 18, 2018 139,141 10/18 10/18
143 Post Construction Activities 90 days April 17, 2020 July 30, 2020
144 Miscellaneous Works (Road Marking, Plantation, Amenities, etc.) 60 days May 20, 2020 July 28, 2020 148FF+3 days 5/20 7/28
145 Quality Testing of Highway 45 days April 17, 2020 June 8, 2020 148FS-85 days 4/17 6/8
146 Testing of Toll Plaza working 15 days June 5, 2020 June 22, 2020 597FS-14 days 6/5 6/22
Page 5
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
148 Construction Activities 664 days May 3, 2018 July 24, 2020
149 Section-4 (69 Km to 89 Km) 579 days August 15, 2018 July 24, 2020
150 Road Works 579 days August 15, 2018 July 24, 2020
151 C&G & BC Excavation Works (BHS) 250 days August 15, 2018 June 17, 2019 4FS+7 days 8/15 6/17
152 Embankment (Cut / Fill) 528 days August 24, 2018 June 1, 2020
153 Embankment (NCW) 182 days August 24, 2018 April 4, 2019
154 69+000 to 70+000 LHS 20 days November 5, 2018 November 27, 2018 166 11/5 11/27
155 70+000 to 70+500 RHS 9 days November 28, 2018 December 7, 2018 154 11/28 12/7
156 70+500 to 71+000 LHS 8 days December 8, 2018 December 17, 2018 155 12/8 12/17
157 71+000 to 71+800 LHS 11 days December 18, 2018 December 29, 2018 156 12/18 12/29
158 71+800 to 72+600 LHS 19 days December 31, 2018 January 21, 2019 157 12/31 1/21
159 72+600 to 73+500 LHS 40 days October 22, 2018 December 6, 2018 164,74,29 10/22 12/6
160 73+500 to 73+900 LHS 2 days December 7, 2018 December 8, 2018 159 12/7 12/8
161 73+900 to 74+420 LHS 7 days December 10, 2018 December 17, 2018 160 12/10 12/17
162 74+610 to 75+300 LHS 13 days December 18, 2018 January 1, 2019 161 12/18 1/1
163 75+300 to 76+000 LHS 10 days August 24, 2018 September 8, 2018 32FS+3 days 8/24 9/8
164 76+000 to 77+000 LHS 40 days August 24, 2018 October 20, 2018 32FS+3 days 8/24 10/20
165 77+000 to 77+600 LHS 26 days September 10, 2018 October 16, 2018 163 9/10 10/16
166 77+600 to 78+700 LHS 40 days September 14, 2018 November 3, 2018 32FS+15 days 9/14 11/3
167 78+700 to 79+500 LHS 27 days November 22, 2018 December 22, 2018 211 11/22 12/22
168 79+500 to 80+300 LHS 21 days December 24, 2018 January 16, 2019 167 12/24 1/16
169 80+300 to 81+300 LHS 17 days January 17, 2019 February 5, 2019 168 1/17 2/5
170 81+300 to 82+200 LHS 10 days January 22, 2019 February 1, 2019 158 1/22 2/1
171 82+200 to 83+100 LHS 12 days February 2, 2019 February 15, 2019 170 2/2 2/15
172 83+100 to 83+600 LHS 5 days February 16, 2019 February 21, 2019 171 2/16 2/21
173 83+600 to 84+800 RHS 25 days February 22, 2019 March 22, 2019 172 2/22 3/22
174 84+800 to 85+500 RHS 25 days March 7, 2019 April 4, 2019 178 3/7 4/4
175 85+500 to 86+200 RHS-Toll plaza 8 days January 2, 2019 January 10, 2019 162 1/2 1/10
176 86+200 to 86+600 RHS 6 days January 11, 2019 January 17, 2019 175 1/11 1/17
177 86+600 to 87+300 RHS 29 days January 18, 2019 February 20, 2019 176 1/18 2/20
Page 6
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
179 88+100 to 89+000 LHS 10 days March 7, 2019 March 18, 2019 178 3/7 3/18
180 Embankment (ECW) 412 days January 18, 2019 June 1, 2020
181 69+000 to 70+000 LHS 20 days May 27, 2019 June 18, 2019 394,257 5/27 6/18
182 70+000 to 70+500 RHS 9 days July 16, 2019 July 25, 2019 395,186 7/16 7/25
183 70+500 to 71+000 LHS 8 days December 18, 2019 December 26, 2019 396,218 12/18 12/26
184 71+000 to 71+800 LHS 11 days July 30, 2019 August 16, 2019 397,256 7/30 8/16
185 71+800 to 72+600 LHS 19 days January 1, 2020 January 22, 2020 398,243 1/1 1/22
186 72+600 to 73+500 LHS 40 days May 6, 2019 June 20, 2019 159,508 5/6 6/20
187 73+500 to 73+900 LHS 2 days January 24, 2019 January 25, 2019 400,208 1/24 1/25
188 73+900 to 74+420 LHS 7 days February 11, 2019 February 18, 2019 401,247 2/11 2/18
189 74+610 to 75+300 LHS 13 days August 10, 2019 August 31, 2019 402,258 8/10 8/31
190 75+300 to 76+000 LHS 10 days January 18, 2019 January 29, 2019 403,269 1/18 1/29
191 76+000 to 77+000 LHS 40 days February 21, 2019 April 8, 2019 404,268 2/21 4/8
192 77+000 to 77+600 LHS 26 days March 7, 2019 April 5, 2019 405,263 3/7 4/5
193 77+600 to 78+700 LHS 40 days May 17, 2019 July 2, 2019 406,266 5/17 7/2
194 78+700 to 79+500 LHS 27 days February 17, 2020 March 18, 2020 407,262 2/17 3/18
195 79+500 to 80+300 LHS 21 days March 27, 2020 April 20, 2020 408,254 3/27 4/20
196 80+300 to 81+300 LHS 17 days June 29, 2019 July 18, 2019 409,241 6/29 7/18
197 81+300 to 82+200 LHS 10 days April 16, 2019 April 26, 2019 410,252 4/16 4/26
198 82+200 to 83+100 LHS 12 days July 15, 2019 July 27, 2019 411,253 7/15 7/27
199 83+100 to 83+600 LHS 5 days January 15, 2020 January 20, 2020 412,265 1/15 1/20
200 83+600 to 84+800 RHS 25 days December 9, 2019 January 6, 2020 413,246 12/9 1/6
201 84+800 to 85+500 RHS 25 days March 8, 2019 April 5, 2019 174SS+1 day 3/8 4/5
202 85+500 to 86+200 RHS-Toll plaza 8 days January 31, 2020 February 8, 2020 415FS+21 days,245 1/31 2/8
203 86+200 to 86+600 RHS 6 days February 25, 2019 March 2, 2019 416,248 2/25 3/2
204 86+600 to 87+300 RHS 29 days April 29, 2020 June 1, 2020 417,255 4/29 6/1
205 87+300 to 88+100 LHS 25 days February 8, 2019 March 8, 2019 178SS+2 days 2/8 3/8
206 88+100 to 89+000 LHS 10 days April 19, 2019 April 30, 2019 419,251 4/19 4/30
207 Embankment (SR / SLR) 51 days September 21, 2018 November 21, 2018
208 72+660 to 73+380 BHS 15 days September 21, 2018 October 10, 2018 151SS+21 days,29 9/21 10/10
Page 7
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
210 86+150 to 87+000 BHS 14 days October 11, 2018 October 26, 2018 208 10/11 10/26
211 87+200 to 88+030 BHS 16 days November 3, 2018 November 21, 2018 209,68 11/3 11/21
213 Sub Grade (NCW) 179 days September 8, 2018 April 11, 2019
214 69+000 to 70+000 LHS 10 days November 27, 2018 December 7, 2018 154FS-1 day 11/27 12/7
215 70+000 to 70+500 RHS 5 days December 7, 2018 December 12, 2018 155FS-1 day 12/7 12/12
216 70+500 to 71+000 LHS 5 days December 17, 2018 December 21, 2018 156FS-1 day 12/17 12/21
217 71+000 to 71+800 LHS 8 days December 29, 2018 January 7, 2019 157FS-1 day 12/29 1/7
218 71+800 to 72+600 LHS 8 days January 21, 2019 January 29, 2019 158FS-1 day 1/21 1/29
219 72+600 to 73+500 LHS 11 days December 6, 2018 December 18, 2018 159FS-1 day 12/6 12/18
220 73+500 to 73+900 LHS 4 days December 8, 2018 December 12, 2018 160FS-1 day 12/8 12/12
221 73+900 to 74+420 LHS 6 days December 17, 2018 December 22, 2018 161FS-1 day 12/17 12/22
222 74+610 to 75+300 LHS 7 days January 1, 2019 January 8, 2019 162FS-1 day 1/1 1/8
223 75+300 to 76+000 LHS 7 days September 8, 2018 September 19, 2018 163FS-1 day 9/8 9/19
224 76+000 to 77+000 LHS 10 days October 20, 2018 October 31, 2018 164FS-1 day 10/20 10/31
225 77+000 to 77+600 LHS 6 days October 16, 2018 October 22, 2018 165FS-1 day 10/16 10/22
226 77+600 to 78+700 LHS 11 days November 3, 2018 November 15, 2018 166FS-1 day 11/3 11/15
227 78+700 to 79+500 LHS 8 days December 22, 2018 December 31, 2018 167FS-1 day 12/22 12/31
228 79+500 to 80+300 LHS 8 days January 16, 2019 January 24, 2019 168FS-1 day 1/16 1/24
229 80+300 to 81+300 LHS 10 days February 5, 2019 February 15, 2019 169FS-1 day 2/5 2/15
230 81+300 to 82+200 LHS 9 days February 1, 2019 February 11, 2019 170FS-1 day 2/1 2/11
231 82+200 to 83+100 LHS 9 days February 15, 2019 February 25, 2019 171FS-1 day 2/15 2/25
232 83+100 to 83+600 LHS 5 days February 21, 2019 February 26, 2019 172FS-1 day 2/21 2/26
233 83+600 to 84+800 RHS 12 days March 22, 2019 April 4, 2019 173FS-1 day 3/22 4/4
234 84+800 to 85+500 RHS 7 days April 4, 2019 April 11, 2019 174FS-1 day 4/4 4/11
235 85+500 to 86+200 RHS-Toll plaza 7 days January 10, 2019 January 17, 2019 175FS-1 day 1/10 1/17
236 86+200 to 86+600 RHS 4 days January 17, 2019 January 21, 2019 176FS-1 day 1/17 1/21
237 86+600 to 87+300 RHS 7 days February 20, 2019 February 27, 2019 177FS-1 day 2/20 2/27
238 87+300 to 88+100 LHS 8 days March 6, 2019 March 14, 2019 178FS-1 day 3/6 3/14
239 88+100 to 89+000 LHS 9 days March 18, 2019 March 27, 2019 179FS-1 day 3/18 3/27
Page 8
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
241 69+000 to 70+000 LHS 10 days June 18, 2019 June 28, 2019 181FS-1 day 6/18 6/28
242 70+000 to 70+500 RHS 5 days July 25, 2019 July 30, 2019 182FS-1 day 7/25 7/30
243 70+500 to 71+000 LHS 5 days December 26, 2019 December 31, 2019 183FS-1 day 12/26 12/31
244 71+000 to 71+800 LHS 8 days August 16, 2019 August 28, 2019 184FS-1 day 8/16 8/28
245 71+800 to 72+600 LHS 8 days January 22, 2020 January 30, 2020 185FS-1 day 1/22 1/30
246 72+600 to 73+500 LHS 11 days June 20, 2019 July 2, 2019 186FS-1 day,219 6/20 7/2
247 73+500 to 73+900 LHS 4 days February 6, 2019 February 9, 2019 187FS-1 day,250 2/6 2/9
248 73+900 to 74+420 LHS 6 days February 18, 2019 February 23, 2019 188FS-1 day 2/18 2/23
249 74+610 to 75+300 LHS 7 days August 31, 2019 September 11, 2019 189FS-1 day 8/31 9/11
250 75+300 to 76+000 LHS 7 days January 29, 2019 February 5, 2019 190FS-1 day 1/29 2/5
251 76+000 to 77+000 LHS 10 days April 8, 2019 April 18, 2019 191FS-1 day 4/8 4/18
252 77+000 to 77+600 LHS 6 days April 5, 2019 April 11, 2019 192FS-1 day 4/5 4/11
253 77+600 to 78+700 LHS 11 days July 2, 2019 July 13, 2019 193FS-1 day 7/2 7/13
254 78+700 to 79+500 LHS 8 days March 18, 2020 March 26, 2020 194FS-1 day 3/18 3/26
255 79+500 to 80+300 LHS 8 days April 20, 2020 April 28, 2020 195FS-1 day 4/20 4/28
256 80+300 to 81+300 LHS 10 days July 18, 2019 July 29, 2019 196FS-1 day 7/18 7/29
257 81+300 to 82+200 LHS 9 days April 26, 2019 May 6, 2019 197FS-1 day 4/26 5/6
258 82+200 to 83+100 LHS 9 days July 27, 2019 August 9, 2019 198FS-1 day 7/27 8/9
259 83+100 to 83+600 LHS 5 days January 20, 2020 January 24, 2020 199FS-1 day 1/20 1/24
260 83+600 to 84+800 RHS 12 days January 6, 2020 January 18, 2020 200FS-1 day 1/6 1/18
261 84+800 to 85+500 RHS 7 days April 5, 2019 April 12, 2019 201FS-1 day 4/5 4/12
262 85+500 to 86+200 RHS -Toll Plaza 7 days February 8, 2020 February 15, 2020 202FS-1 day 2/8 2/15
263 86+200 to 86+600 RHS 4 days March 2, 2019 March 6, 2019 203FS-1 day 3/2 3/6
264 86+600 to 87+300 RHS 7 days June 1, 2020 June 8, 2020 204FS-1 day 6/1 6/8
265 87+300 to 88+100 LHS 8 days March 8, 2019 March 16, 2019 205FS-1 day 3/8 3/16
266 88+100 to 89+000 LHS 9 days April 30, 2019 May 9, 2019 206FS-1 day 4/30 5/9
267 Sub Grade (SR / SLR) 118 days October 26, 2018 February 20, 2019
268 72+660 to 73+380 BHS 8 days February 12, 2019 February 20, 2019 208FS-1 day,230 2/12 2/20
269 84+800 to 85+750 BHS 22 days October 27, 2018 November 21, 2018 209FS-1 day 10/27 11/21
270 86+150 to 87+000 BHS 20 days October 26, 2018 November 17, 2018 210FS-1 day 10/26 11/17
Page 9
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
273 GSB (NCW) 453 days December 18, 2018 June 17, 2020
274 69+000 to 70+000 LHS 5 days May 10, 2019 May 15, 2019 214,323 5/10 5/15
275 70+000 to 70+500 RHS 3 days June 22, 2019 June 25, 2019 215,277 6/22 6/25
276 70+500 to 71+000 LHS 3 days October 18, 2019 October 21, 2019 216,279 10/18 10/21
277 71+000 to 71+800 LHS 4 days June 18, 2019 June 21, 2019 217,317 6/18 6/21
278 71+800 to 72+600 LHS 4 days October 28, 2019 October 31, 2019 218,306 10/28 10/31
279 72+600 to 73+500 LHS 5 days October 12, 2019 October 17, 2019 219,302 10/12 10/17
280 73+500 to 73+900 LHS 2 days December 27, 2018 December 28, 2018 220,281 12/27 12/28
281 73+900 to 74+420 LHS 3 days December 24, 2018 December 26, 2018 221,283 12/24 12/26
282 74+610 to 75+300 LHS 4 days January 9, 2019 January 12, 2019 222,281 1/9 1/12
283 75+300 to 76+000 LHS 4 days December 18, 2018 December 21, 2018 223FS+30 days,330 12/18 12/21
284 76+000 to 77+000 LHS 5 days January 28, 2019 February 1, 2019 224,285 1/28 2/1
285 77+000 to 77+600 LHS 3 days January 24, 2019 January 26, 2019 225,296 1/24 1/26
286 77+600 to 78+700 LHS 6 days April 27, 2019 May 3, 2019 226,307 4/27 5/3
287 78+700 to 79+500 LHS 4 days November 1, 2019 November 5, 2019 227,278 11/1 11/5
288 79+500 to 80+300 LHS 4 days February 5, 2020 February 8, 2020 228,305 2/5 2/8
289 80+300 to 81+300 LHS 5 days May 25, 2019 May 30, 2019 229,312 5/25 5/30
290 81+300 to 82+200 LHS 5 days April 3, 2019 April 8, 2019 230,299 4/3 4/8
291 82+200 to 83+100 LHS 5 days May 31, 2019 June 5, 2019 231,289 5/31 6/5
292 83+100 to 83+600 LHS 3 days January 4, 2020 January 7, 2020 232,303 1/4 1/7
293 83+600 to 84+800 RHS 6 days September 27, 2019 October 3, 2019 233,304 9/27 10/3
294 84+800 to 85+500 RHS 4 days June 13, 2020 June 17, 2020 234,324 6/13 6/17
295 85+500 to 86+200 RHS -Toll Plaza 4 days October 4, 2019 October 8, 2019 235,293 10/4 10/8
296 86+200 to 86+600 RHS 2 days January 22, 2019 January 23, 2019 236,331 1/22 1/23
297 86+600 to 87+300 RHS 4 days April 1, 2020 April 4, 2020 237,314 4/1 4/4
298 87+300 to 88+100 LHS 4 days February 10, 2020 February 13, 2020 238,288 2/10 2/13
299 88+100 to 89+000 LHS 5 days March 28, 2019 April 2, 2019 239,329 3/28 4/2
300 GSB (ECW) 351 days April 20, 2019 June 22, 2020
301 69+000 to 70+000 RHS 5 days June 29, 2019 July 4, 2019 241,275 6/29 7/4
Page 10
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
303 70+500 to 71+000 RHS 3 days January 1, 2020 January 3, 2020 243,287 1/1 1/3
304 71+000 to 71+800 RHS 4 days September 20, 2019 September 25, 2019 244,309 9/20 9/25
305 71+800 to 72+600 RHS 4 days January 31, 2020 February 4, 2020 245,292 1/31 2/4
306 72+600 to 73+500 RHS 5 days October 22, 2019 October 26, 2019 246,276 10/22 10/26
307 73+500 to 73+900 RHS 2 days April 25, 2019 April 26, 2019 247,310 4/25 4/26
308 73+900 to 74+420 RHS 3 days May 4, 2019 May 7, 2019 248,286 5/4 5/7
309 74+610 to 75+300 RHS 4 days September 13, 2019 September 18, 2019 249,318 9/13 9/18
310 75+300 to 76+000 RHS 4 days April 20, 2019 April 24, 2019 250,328 4/20 4/24
311 76+000 to 77+000 RHS 5 days May 16, 2019 May 21, 2019 251,274 5/16 5/21
312 77+000 to 77+600 RHS 3 days May 22, 2019 May 24, 2019 252,311 5/22 5/24
313 77+600 to 78+700 RHS 6 days July 15, 2019 July 20, 2019 253,282 7/15 7/20
314 78+700 to 79+500 RHS 4 days March 27, 2020 March 31, 2020 254,319 3/27 3/31
315 79+500 to 80+300 RHS 4 days April 29, 2020 May 2, 2020 255,297 4/29 5/2
316 80+300 to 81+300 RHS 5 days July 30, 2019 August 5, 2019 256,313 7/30 8/5
317 81+300 to 82+200 RHS 5 days June 12, 2019 June 17, 2019 257,326 6/12 6/17
318 82+200 to 83+100 RHS 5 days August 10, 2019 August 17, 2019 258,316 8/10 8/17
319 83+100 to 83+600 RHS 3 days March 2, 2020 March 4, 2020 259,320 3/2 3/4
320 83+600 to 84+800 LHS 6 days February 24, 2020 February 29, 2020 260,322 2/24 2/29
321 84+800 to 85+500 LHS 4 days June 18, 2020 June 22, 2020 261,294 6/18 6/22
322 85+500 to 86+200 LHS Tollplaza 4 days February 19, 2020 February 22, 2020 262,325 2/19 2/22
323 86+200 to 86+600 LHS 2 days May 8, 2019 May 9, 2019 263,308 5/8 5/9
324 86+600 to 87+300 LHS 4 days June 9, 2020 June 12, 2020 264,315 6/9 6/12
325 87+300 to 88+100 RHS 4 days February 14, 2020 February 18, 2020 265,298 2/14 2/18
326 88+100 to 89+000 RHS 5 days June 6, 2019 June 11, 2019 266,291 6/6 6/11
327 GSB (SR / SLR) 135 days December 6, 2018 April 19, 2019
328 72+660 to 73+380 BHS 10 days April 9, 2019 April 19, 2019 268,290 4/9 4/19
329 84+800 to 85+750 BHS 10 days February 2, 2019 February 13, 2019 269,284 2/2 2/13
330 86+150 to 87+000 BHS 10 days December 6, 2018 December 17, 2018 270FS+15 days 12/6 12/17
331 87+200 to 88+030 BHS 10 days December 29, 2018 January 9, 2019 271,280 12/29 1/9
332 WMM TOP Layer 444 days January 4, 2019 June 24, 2020
333 WMM -Top layer (NCW) 437 days January 8, 2019 June 19, 2020
Page 11
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
335 70+000 to 70+500 RHS 2 days June 26, 2019 June 27, 2019 275,337 6/26 6/27
336 70+500 to 71+000 LHS 2 days October 22, 2019 October 23, 2019 276,339 10/22 10/23
337 71+000 to 71+800 LHS 3 days June 22, 2019 June 25, 2019 277,377 6/22 6/25
338 71+800 to 72+600 LHS 3 days November 1, 2019 November 4, 2019 278,366 11/1 11/4
339 72+600 to 73+500 LHS 3 days October 18, 2019 October 21, 2019 279,362 10/18 10/21
340 73+500 to 73+900 LHS 2 days January 12, 2019 January 14, 2019 280,341 1/12 1/14
341 73+900 to 74+420 LHS 2 days January 10, 2019 January 11, 2019 281,343 1/10 1/11
342 74+610 to 75+300 LHS 2 days July 8, 2019 July 9, 2019 282,361 7/8 7/9
343 75+300 to 76+000 LHS 2 days January 8, 2019 January 9, 2019 283,390 1/8 1/9
344 76+000 to 77+000 LHS 3 days February 2, 2019 February 5, 2019 284,345 2/2 2/5
345 77+000 to 77+600 LHS 2 days January 28, 2019 January 29, 2019 285,356 1/28 1/29
346 77+600 to 78+700 LHS 4 days May 4, 2019 May 8, 2019 286,367 5/4 5/8
347 78+700 to 79+500 LHS 3 days November 6, 2019 November 8, 2019 287,338 11/6 11/8
348 79+500 to 80+300 LHS 3 days February 10, 2020 February 12, 2020 288,365 2/10 2/12
349 80+300 to 81+300 LHS 3 days May 31, 2019 June 3, 2019 289,372 5/31 6/3
350 81+300 to 82+200 LHS 3 days April 9, 2019 April 11, 2019 290,359 4/9 4/11
351 82+200 to 83+100 LHS 3 days June 6, 2019 June 8, 2019 291,349 6/6 6/8
352 83+100 to 83+600 LHS 2 days January 8, 2020 January 9, 2020 292,363 1/8 1/9
353 83+600 to 84+800 RHS 4 days October 4, 2019 October 8, 2019 293,364 10/4 10/8
354 84+800 to 85+500 RHS 2 days June 18, 2020 June 19, 2020 294,384 6/18 6/19
355 85+500 to 86+200 RHS 0 days October 8, 2019 October 8, 2019 295,353 10/8
356 86+200 to 86+600 RHS 2 days January 24, 2019 January 25, 2019 296,391 1/24 1/25
357 86+600 to 87+300 RHS 2 days April 6, 2020 April 7, 2020 297,374 4/6 4/7
358 87+300 to 88+100 LHS 3 days February 14, 2020 February 17, 2020 298,348 2/14 2/17
359 88+100 to 89+000 LHS 3 days April 3, 2019 April 5, 2019 299,389 4/3 4/5
360 WMM- Top Layer (ECW) 349 days April 25, 2019 June 24, 2020
361 69+000 to 70+000 RHS 2 days July 5, 2019 July 6, 2019 301,335 7/5 7/6
362 70+000 to 70+500 LHS 2 days October 12, 2019 October 14, 2019 302,355 10/12 10/14
363 70+500 to 71+000 RHS 2 days January 4, 2020 January 6, 2020 303,347 1/4 1/6
364 71+000 to 71+800 RHS 2 days September 27, 2019 September 28, 2019 304,369 9/27 9/28
Page 12
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
366 72+600 to 73+500 RHS 2 days October 28, 2019 October 29, 2019 306,336 10/28 10/29
367 73+500 to 73+900 RHS 1 day April 27, 2019 April 27, 2019 307,370 4/27 4/27
368 73+900 to 74+420 RHS 2 days May 9, 2019 May 10, 2019 308,346 5/9 5/10
369 74+610 to 75+300 RHS 2 days September 20, 2019 September 21, 2019 309,378 9/20 9/21
370 75+300 to 76+000 RHS 2 days April 25, 2019 April 26, 2019 310,388 4/25 4/26
371 76+000 to 77+000 RHS 2 days May 22, 2019 May 23, 2019 311,334 5/22 5/23
372 77+000 to 77+600 RHS 2 days May 25, 2019 May 27, 2019 312,371 5/25 5/27
373 77+600 to 78+700 RHS 2 days July 22, 2019 July 23, 2019 313,342 7/22 7/23
374 78+700 to 79+500 RHS 2 days April 1, 2020 April 2, 2020 314,379 4/1 4/2
375 79+500 to 80+300 RHS 2 days May 4, 2020 May 5, 2020 315,357 5/4 5/5
376 80+300 to 81+300 RHS 3 days August 7, 2019 August 10, 2019 316,373 8/7 8/10
377 81+300 to 82+200 RHS 2 days June 18, 2019 June 19, 2019 317,386 6/18 6/19
378 82+200 to 83+100 RHS 2 days August 19, 2019 August 21, 2019 318,376 8/19 8/21
379 83+100 to 83+600 RHS 2 days March 5, 2020 March 6, 2020 319,380 3/5 3/6
380 83+600 to 84+800 LHS 3 days March 2, 2020 March 4, 2020 320,382 3/2 3/4
381 84+800 to 85+500 LHS 2 days June 23, 2020 June 24, 2020 321,354 6/23 6/24
382 85+500 to 86+200 LHS 0 days February 22, 2020 February 22, 2020 322,385 2/22
383 86+200 to 86+600 LHS 1 day May 11, 2019 May 11, 2019 323,368 5/11 5/11
384 86+600 to 87+300 LHS 2 days June 13, 2020 June 15, 2020 324,375 6/13 6/15
385 87+300 to 88+100 RHS 2 days February 19, 2020 February 20, 2020 325,358 2/19 2/20
386 88+100 to 89+000 RHS 2 days June 12, 2019 June 13, 2019 326,351 6/12 6/13
387 WMM-I (SR / SLR) 110 days January 4, 2019 April 23, 2019
388 72+660 to 73+380 BHS 3 days April 20, 2019 April 23, 2019 328,350 4/20 4/23
389 84+800 to 85+750 BHS 3 days February 14, 2019 February 16, 2019 329,344 2/14 2/16
390 86+150 to 87+000 BHS 3 days January 4, 2019 January 7, 2019 330FS+15 days 1/4 1/7
391 87+200 to 88+030 BHS 3 days January 15, 2019 January 17, 2019 331,340 1/15 1/17
393 DBM (NCW) 446 days January 16, 2019 July 8, 2020
394 69+000 to 70+000 LHS 2 days May 24, 2019 May 25, 2019 334FS+1 day,443 5/24 5/25
395 70+000 to 70+500 RHS 3 days July 12, 2019 July 15, 2019 335FS+1 day,397 7/12 7/15
Page 13
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
397 71+000 to 71+800 LHS 3 days July 9, 2019 July 11, 2019 337FS+1 day,437 7/9 7/11
398 71+800 to 72+600 LHS 2 days December 23, 2019 December 24, 2019 338FS+1 day,426 12/23 12/24
399 72+600 to 73+500 LHS 2 days December 12, 2019 December 13, 2019 339FS+1 day,415 12/12 12/13
400 73+500 to 73+900 LHS 3 days January 21, 2019 January 23, 2019 340FS+1 day,401 1/21 1/23
401 73+900 to 74+420 LHS 2 days January 18, 2019 January 19, 2019 341FS+1 day,403 1/18 1/19
402 74+610 to 75+300 LHS 4 days July 23, 2019 July 26, 2019 342FS+1 day,421 7/23 7/26
403 75+300 to 76+000 LHS 2 days January 16, 2019 January 17, 2019 343FS+1 day,450 1/16 1/17
404 76+000 to 77+000 LHS 4 days February 7, 2019 February 11, 2019 344FS+1 day,405 2/7 2/11
405 77+000 to 77+600 LHS 3 days February 4, 2019 February 6, 2019 345FS+1 day,416 2/4 2/6
406 77+600 to 78+700 LHS 3 days May 14, 2019 May 16, 2019 346FS+1 day,427 5/14 5/16
407 78+700 to 79+500 LHS 4 days December 25, 2019 December 28, 2019 347FS+1 day,398 12/25 12/28
408 79+500 to 80+300 LHS 3 days February 25, 2020 February 27, 2020 348FS+1 day,458 2/25 2/27
409 80+300 to 81+300 LHS 3 days June 7, 2019 June 10, 2019 349FS+1 day,432 6/7 6/10
410 81+300 to 82+200 LHS 2 days April 13, 2019 April 15, 2019 350FS+1 day,419 4/13 4/15
411 82+200 to 83+100 LHS 4 days June 22, 2019 June 26, 2019 351FS+1 day,465 6/22 6/26
412 83+100 to 83+600 LHS 3 days January 11, 2020 January 14, 2020 352FS+1 day,423 1/11 1/14
413 83+600 to 84+800 RHS 3 days December 5, 2019 December 7, 2019 353FS+1 day,462 12/5 12/7
414 84+800 to 85+500 RHS 1 day July 8, 2020 July 8, 2020 354FS+1 day,475 7/8 7/8
415 85+500 to 86+200 RHS 0 days December 11, 2019 December 11, 2019 355FS+7 days,422 12/11
416 86+200 to 86+600 RHS 3 days January 31, 2019 February 2, 2019 356FS+1 day,451 1/31 2/2
417 86+600 to 87+300 RHS 3 days April 10, 2020 April 13, 2020 357FS+1 day,434 4/10 4/13
418 87+300 to 88+100 LHS 3 days February 28, 2020 March 2, 2020 358FS+1 day,408 2/28 3/2
419 88+100 to 89+000 LHS 4 days April 8, 2019 April 11, 2019 359FS+1 day,509 4/8 4/11
420 DBM (ECW) 355 days May 6, 2019 July 11, 2020
421 69+000 to 70+000 RHS 6 days July 16, 2019 July 22, 2019 361FS+1 day,395 7/16 7/22
422 70+000 to 70+500 LHS 3 days December 9, 2019 December 11, 2019 362FS+1 day,413 12/9 12/11
423 70+500 to 71+000 RHS 3 days January 8, 2020 January 10, 2020 363FS+1 day,407 1/8 1/10
424 71+000 to 71+800 RHS 5 days November 20, 2019 November 25, 2019 364FS+1 day,429 11/20 11/25
425 71+800 to 72+600 RHS 5 days February 8, 2020 February 13, 2020 365FS+1 day,457 2/8 2/13
Page 14
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
427 73+500 to 73+900 RHS 3 days May 10, 2019 May 13, 2019 367FS+1 day,430 5/10 5/13
428 73+900 to 74+420 RHS 3 days May 17, 2019 May 20, 2019 368FS+1 day,406 5/17 5/20
429 74+610 to 75+300 RHS 4 days November 15, 2019 November 19, 2019 369FS+1 day,471 11/15 11/19
430 75+300 to 76+000 RHS 4 days May 6, 2019 May 9, 2019 370FS+1 day,508 5/6 5/9
431 76+000 to 77+000 RHS 6 days May 27, 2019 June 1, 2019 371FS+1 day,394 5/27 6/1
432 77+000 to 77+600 RHS 4 days June 3, 2019 June 6, 2019 372FS+1 day,431 6/3 6/6
433 77+600 to 78+700 RHS 6 days July 27, 2019 August 3, 2019 373FS+1 day,402 7/27 8/3
434 78+700 to 79+500 RHS 5 days April 4, 2020 April 9, 2020 374FS+1 day,439 4/4 4/9
435 79+500 to 80+300 RHS 5 days May 7, 2020 May 12, 2020 375FS+1 day,417 5/7 5/12
436 80+300 to 81+300 RHS 6 days August 14, 2019 August 23, 2019 376FS+1 day,433 8/14 8/23
437 81+300 to 82+200 RHS 5 days July 3, 2019 July 8, 2019 377FS+1 day,446 7/3 7/8
438 82+200 to 83+100 RHS 5 days August 24, 2019 August 31, 2019 378FS+1 day,436 8/24 8/31
439 83+100 to 83+600 RHS 3 days March 14, 2020 March 17, 2020 379FS+1 day,442 3/14 3/17
440 83+600 to 84+800 LHS 7 days March 6, 2020 March 13, 2020 380FS+1 day,445 3/6 3/13
441 84+800 to 85+500 LHS 3 days July 9, 2020 July 11, 2020 381FS+1 day,414 7/9 7/11
442 85+500 to 86+200 LHS 0 days March 13, 2020 March 13, 2020 382FS+7 days,440 3/13
443 86+200 to 86+600 LHS 3 days May 21, 2019 May 23, 2019 383FS+1 day,428 5/21 5/23
444 86+600 to 87+300 LHS 4 days June 17, 2020 June 20, 2020 384FS+1 day,468 6/17 6/20
445 87+300 to 88+100 RHS 3 days March 3, 2020 March 5, 2020 385FS+1 day,418 3/3 3/5
446 88+100 to 89+000 RHS 5 days June 27, 2019 July 2, 2019 386FS+1 day,411 6/27 7/2
447 DBM (SR / SLR) 112 days January 9, 2019 April 30, 2019
448 72+660 to 73+380 BHS 5 days April 25, 2019 April 30, 2019 388FS+1 day,410 4/25 4/30
449 84+800 to 85+750 BHS 7 days February 19, 2019 February 26, 2019 389FS+1 day,510 2/19 2/26
450 86+150 to 87+000 BHS 6 days January 9, 2019 January 15, 2019 390FS+1 day 1/9 1/15
451 87+200 to 88+030 BHS 6 days January 24, 2019 January 30, 2019 391FS+1 day,400 1/24 1/30
453 BC (NCW) 330 days June 17, 2019 July 24, 2020
454 69+000 to 70+000 LHS 2 days January 22, 2020 January 23, 2020 394FS+1 day,481 1/22 1/23
455 70+000 to 70+500 RHS 1 day January 24, 2020 January 24, 2020 395FS+1 day,482,454 1/24 1/24
456 70+500 to 71+000 LHS 1 day January 25, 2020 January 25, 2020 396FS+1 day,483,455 1/25 1/25
Page 15
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
458 71+800 to 72+600 LHS 2 days February 22, 2020 February 24, 2020 398FS+1 day,485,459 2/22 2/24
459 72+600 to 73+500 LHS 2 days February 20, 2020 February 21, 2020 399FS+1 day,486 2/20 2/21
460 73+500 to 73+900 LHS 1 day November 30, 2019 November 30, 2019 400FS+1 day,487 11/30 11/30
461 73+900 to 74+420 LHS 1 day December 2, 2019 December 2, 2019 401FS+1 day,488,460 12/2 12/2
462 74+610 to 75+300 LHS 2 days December 3, 2019 December 4, 2019 402FS+1 day,489,461 12/3 12/4
463 75+300 to 76+000 LHS 2 days June 17, 2019 June 18, 2019 403FS+1 day,490 6/17 6/18
464 76+000 to 77+000 LHS 2 days June 19, 2019 June 20, 2019 404FS+1 day,491,463 6/19 6/20
465 77+000 to 77+600 LHS 1 day June 21, 2019 June 21, 2019 405FS+1 day,492,464 6/21 6/21
466 77+600 to 78+700 LHS 2 days May 21, 2020 May 22, 2020 406FS+1 day,493 5/21 5/22
467 78+700 to 79+500 LHS 2 days May 23, 2020 May 25, 2020 407FS+1 day,494,466 5/23 5/25
468 79+500 to 80+300 LHS 2 days May 26, 2020 May 27, 2020 408FS+1 day,495,467 5/26 5/27
469 80+300 to 81+300 LHS 2 days November 8, 2019 November 9, 2019 409FS+1 day,496 11/8 11/9
470 81+300 to 82+200 LHS 2 days November 11, 2019 November 12, 2019 410FS+1 day,497,469 11/11 11/12
471 82+200 to 83+100 LHS 2 days November 13, 2019 November 14, 2019 411FS+1 day,498,470 11/13 11/14
472 83+100 to 83+600 LHS 1 day July 20, 2020 July 20, 2020 412FS+1 day,499 7/20 7/20
473 83+600 to 84+800 RHS 2 days July 21, 2020 July 22, 2020 413FS+1 day,500,472 7/21 7/22
474 84+800 to 85+500 RHS 2 days July 23, 2020 July 24, 2020 414FS+1 day,473 7/23 7/24
475 85+500 to 86+200 RHS-toll plaza 0 days July 7, 2020 July 7, 2020 415FS+21 days,502,476 7/7
476 86+200 to 86+600 RHS 1 day July 7, 2020 July 7, 2020 416FS+1 day,503,477 7/7 7/7
477 86+600 to 87+300 RHS 2 days July 4, 2020 July 6, 2020 417FS+1 day,504,478,589 7/4 7/6
478 87+300 to 88+100 LHS 2 days July 2, 2020 July 3, 2020 418FS+1 day,479 7/2 7/3
479 88+100 to 89+000 LHS 2 days June 30, 2020 July 1, 2020 419FS+1 day,506 6/30 7/1
480 BC (ECW) 330 days June 11, 2019 July 18, 2020
512 Structure Works 641 days May 3, 2018 June 27, 2020
513 Minor Bridge @ Ch: 72+680 (Length: 27 Mtr) 108 days April 3, 2019 August 9, 2019 520
514 Foundation 45 days April 3, 2019 May 24, 2019 515SF+26 days 4/3 5/24
515 Sub Structure 60 days April 3, 2019 June 11, 2019 219FF-60 days 4/3 6/11
516 Super Structure 75 days May 11, 2019 August 9, 2019 515SS+33 days 5/11 8/9
517 Minor Bridge(SR) @ Ch: 72+680 (Length: 27 Mtr) 125 days November 8, 2018 April 2, 2019
Page 16
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
519 Sub Structure 90 days November 8, 2018 February 20, 2019 268FF 11/8 2/20
520 Super Structure 90 days December 19, 2018 April 2, 2019 519SS+35 days 12/19 4/2
521 Minor Bridge(Recon) @ Ch: 72+680 (Length: 27 Mtr) 127 days July 9, 2019 December 23, 2019 508
522 Foundation 45 days July 9, 2019 September 13, 2019 516FS-25 days 7/9 9/13
523 Sub Structure 60 days July 31, 2019 October 28, 2019 522FS-26 days 7/31 10/28
524 Super Structure 75 days September 27, 2019 December 23, 2019 523SS+33 days 9/27 12/23
525 VOP @ Ch: 72+995 (Length: 30 Mtr) 90 days May 13, 2019 September 6, 2019 508,560
526 Foundation 90 days May 13, 2019 September 6, 2019 527SF+45 days 5/13 9/6
527 Sub Structure 90 days May 13, 2019 September 6, 2019 219FF-11 days 5/13 9/6
528 Super Structure 60 days May 14, 2019 July 22, 2019 527SS+1 day 5/14 7/22
529 Minor Bridge @ Ch: 73+360 (Length: 36 Mtr) 163 days April 5, 2019 October 31, 2019 536
530 Foundation 60 days April 5, 2019 June 13, 2019 536 4/5 6/13
531 Sub Structure 90 days April 29, 2019 August 16, 2019 530SS+20 days 4/29 8/16
532 Super Structure 90 days June 29, 2019 October 31, 2019 531SS+53 days 6/29 10/31
533 Minor Bridge(SR) @ Ch: 73+360 (Length: 36 Mtr) 162 days September 28, 2018 April 4, 2019
534 Foundation 60 days September 28, 2018 December 6, 2018 535SF+40 days 9/28 12/6
535 Sub Structure 90 days October 22, 2018 February 2, 2019 268FF-15 days 10/22 2/2
536 Super Structure 90 days December 21, 2018 April 4, 2019 535SS+52 days 12/21 4/4
537 Minor Bridge(Recon) @ Ch: 73+360 (Length: 36 Mtr) 161 days November 1, 2019 May 6, 2020 508
538 Foundation 60 days November 1, 2019 January 9, 2020 532 11/1 1/9
539 Sub Structure 90 days November 25, 2019 March 7, 2020 538SS+20 days 11/25 3/7
540 Super Structure 90 days January 23, 2020 May 6, 2020 539SS+51 days 1/23 5/6
541 Minor Bridge @ Ch: 74+985 (Length: 17.40 Mtr) 75 days April 5, 2019 July 1, 2019 536
542 Foundation 45 days April 5, 2019 May 27, 2019 543SF 4/5 5/27
543 Sub Structure 30 days April 5, 2019 May 9, 2019 162FF-53 days 4/5 5/9
544 Super Structure 45 days May 10, 2019 July 1, 2019 543 5/10 7/1
545 Minor Bridge(Recon) @ Ch: 74+985 (Length: 17.40 Mtr) 120 days October 7, 2019 February 22, 2020 402
546 Foundation 45 days October 7, 2019 November 27, 2019 556 10/7 11/27
547 Sub Structure 30 days November 28, 2019 January 1, 2020 546 11/28 1/1
548 Super Structure 45 days January 2, 2020 February 22, 2020 547 1/2 2/22
549 Minor Bridge @ Ch: 78+060 (Length: 8.10 Mtr) 105 days August 10, 2018 December 26, 2018
Page 17
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
551 Sub Structure 35 days September 22, 2018 November 3, 2018 166FF 9/22 11/3
552 Super Structure 45 days November 5, 2018 December 26, 2018 551 11/5 12/26
553 Minor Bridge(Recon) @ Ch: 78+060 (Length: 8.10 Mtr) 105 days May 17, 2019 October 5, 2019 406
554 Foundation 25 days May 17, 2019 June 14, 2019 552 5/17 6/14
555 Sub Structure 35 days June 15, 2019 July 25, 2019 554 6/15 7/25
556 Super Structure 45 days July 26, 2019 October 5, 2019 555 7/26 10/5
557 Minor Bridge @ Ch: 80+155 (Length: 8.10 Mtr) 80 days February 8, 2019 May 11, 2019 585
558 Foundation 25 days February 8, 2019 March 8, 2019 559SF 2/8 3/8
559 Sub Structure 35 days February 8, 2019 March 20, 2019 168FF-280 days 2/8 3/20
560 Super Structure 45 days March 21, 2019 May 11, 2019 559 3/21 5/11
561 Minor Bridge(Recon) @ Ch: 80+155 (Length: 8.10 Mtr) 45 days May 7, 2020 June 27, 2020 408
562 Foundation 15 days May 7, 2020 May 23, 2020 540 5/7 5/23
563 Sub Structure 15 days May 25, 2020 June 10, 2020 562 5/25 6/10
564 Super Structure 15 days June 11, 2020 June 27, 2020 563 6/11 6/27
565 Minor Bridge(Recon) @ Ch: 81+042 (Length: 21 Mtr) 108 days June 11, 2019 November 2, 2019 409,593
566 Foundation 45 days June 11, 2019 August 2, 2019 6/11 8/2
567 Sub Structure 35 days July 16, 2019 September 6, 2019 566SS+30 days 7/16 9/6
568 Super Structure 45 days September 4, 2019 November 2, 2019 567FS-2 days 9/4 11/2
569 Minor Bridge @ Ch: 84+295 (Length: 35.20 Mtr) 140 days February 8, 2019 July 20, 2019 585
570 Foundation 60 days February 8, 2019 April 18, 2019 571SF+40 days 2/8 4/18
571 Sub Structure 105 days February 8, 2019 June 10, 2019 173FF-117 days 2/8 6/10
572 Super Structure 90 days April 8, 2019 July 20, 2019 571SS+50 days 4/8 7/20
573 PUP @ Ch: 84+975 (Length: 7 Mtr) 269 days July 22, 2019 June 18, 2020 509,572
574 Foundation 30 days July 22, 2019 September 6, 2019 572 7/22 9/6
575 Sub Structure 30 days September 7, 2019 October 18, 2019 574 9/7 10/18
576 Super Structure 45 days October 19, 2019 December 10, 2019 575 10/19 12/10
577 Approaches (RE Wall Erection) 134 days January 15, 2020 June 18, 2020 174SS-15 days,321FF-3 days 1/15 6/18
578 Minor Bridge @ Ch: 86+836 (Length: 17.40 Mtr) 120 days November 4, 2019 March 21, 2020 568
579 Foundation 45 days November 4, 2019 December 25, 2019 568 11/4 12/25
580 Sub Structure 30 days December 26, 2019 January 29, 2020 579 12/26 1/29
581 Super Structure 45 days January 30, 2020 March 21, 2020 580 1/30 3/21
Page 18
NH13- SOLAPUR-BIJAPUR PROJECT
CONSTRUCTION PROGRAMME
583 Foundation 45 days September 17, 2018 November 13, 2018 584SF 9/17 11/13
584 Sub Structure 30 days November 13, 2018 December 17, 2018 330FF 11/13 12/17
585 Super Structure 45 days December 18, 2018 February 7, 2019 584 12/18 2/7
586 Major Bridge @ Ch: 87+105 (Length: 61.80 Mtr) 230 days June 14, 2019 March 27, 2020 544FS-15 days
587 Foundation 100 days June 14, 2019 October 28, 2019 544FS-15 days 6/14 10/28
588 Sub Structure 140 days July 13, 2019 January 11, 2020 587SS+25 days 7/13 1/11
589 Super Structure 170 days September 4, 2019 March 27, 2020 588SS+35 days 9/4 3/27
590 PUP @ Ch: 87+530 (Length: 7 Mtr) 296 days February 15, 2019 February 14, 2020 511
591 Foundation 30 days February 15, 2019 March 21, 2019 592SF 2/15 3/21
592 Sub Structure 30 days February 15, 2019 March 21, 2019 178FF-246 days 2/15 3/21
593 Super Structure 45 days March 22, 2019 May 13, 2019 592 3/22 5/13
594 Approaches (RE Wall Erection) 138 days August 28, 2019 February 14, 2020 325FF-3 days,178SS-15 days 8/28 2/14
595 Culverts & Misc. Works 500 days May 3, 2018 January 15, 2020 151FF+15 days 5/3 1/15
596 RE Wall Casting 365 days May 3, 2018 July 22, 2019 5/3 7/22
597 Toll Plaza Construction 270 days July 23, 2019 June 20, 2020
598 PQC / DLC 120 days February 3, 2020 June 20, 2020 355SS,502FF 2/3 6/20
599 Tunnel Construction 180 days July 23, 2019 March 7, 2020 598SS-150 days 7/23 3/7
600 Toll Booth Construction 150 days September 9, 2019 March 7, 2020 599SS+30 days 9/9 3/7
601 Toll Plaza Building Construction 220 days July 23, 2019 April 23, 2020 599SS 7/23 4/23
602 Canopy Erection & Fixing 30 days March 9, 2020 April 11, 2020 600 3/9 4/11
603 HTMS and All Ancillary Works 30 days February 14, 2020 March 19, 2020 600FS-20 days 2/14 3/19