Culture Documents
Prepared By:
2. Add the computed volume of concrete to the allowance for wastage (varies/ say 10 % foundation, 5% for others).
COLLEGE OF ENGINEERING
3. Check the strength of concrete (“class”), then Multiply the design factor.
4. Compute the amount of sand , gravel and cement.
Concrete Volume Estimate Autodesk Revit – Structural
Example 1:
Determine the Volume of concrete in cubic
CIVIL ENGINEERING DEPARTMENT
of cement, sand and gravel assuming class B concrete mix for columns.
COLLEGE OF ENGINEERING
DIMENSIONS
b h Please see Foundation Plan
C1 400 400
for your additional reference
C2 375 375
Concrete Volume Estimate Autodesk Revit – Structural
Example 2:
Determine the Volume of concrete (in cubic meter) needed for structural
columns in a 2-storey with roofdeck residential building. Also estimate
CIVIL ENGINEERING DEPARTMENT
the quantity of cement, sand and gravel assuming class B concrete mix
COLLEGE OF ENGINEERING
for columns.
COLUMNS class B
Vol (C1 – T.O.F to 2nd Floor) = b x h x H = 0.4 x 0.4 x 6.3 = 1.008 cu. m.
Vol (C1 – T.O.F to Roofdeck) = b x h x H = 0.4 x 0.4 x 9.6 = 1.536 cu. m.
Vol (C2 – T.O.F to Roofdeck) = b x h x H = 0.375 x 0.375 x 9.6 = 1.350 cu. m.
Total Volume (with Wastage Factor) = 16.476 + 16.476 x 0.05 = 17.300 cu.m.
Total Volume (with Wastage Factor) = 2.201 + 2.201 x 0.05 = 2.421 cu.m. Columns DIMENSIONS Beams DIMENSIONS
b h b h
Cement = 2.4211 cu. m. x 6.49 = 15.713; say 16 bags of cement C1 400 400 B1 350 425
Sand = 2.4211 cu. m. x 0.44 = 1.065 cu.m.; say 1.5 cu.m.
Gravel = 2.4211 cu. m. x 0.87 = 2.106 cu.m.; say 2.5 cu.m. C2 375 375 B2 325 450
Concrete Volume Estimate Autodesk Revit – Structural
Example 4:
Determine the Volume of concrete (in cubic meter) needed for Footing Tie
Beams (FTB) in a 2-storey with roofdeck residential building. Also
CIVIL ENGINEERING DEPARTMENT
Length (FTB for Grid A and C) = 16.00 – 0.20 - 0.40 – 0.4 – 0.20 = 14.80 m
Length (FTB for Grid B) = 16.00 – 0.2 – 0.375 – 0.375 – 0.20 = 14.85 m
Length (FTB for Grid 1 and 4) = 9.00 – 0.20 – 0.40 – 0.20 = 8.20 m
Length (FTB for Grid 1 and 4) = 9.00 – 0.20 – 0.375 – 0.20 = 8.225 m
Total Length = 46.075 m
Total Volume (with Wastage Factor) = 7.660 + 7.660 x 0.10 = 8.426 cu.m.
Columns DIMENSIONS
Cement = 8.426 cu. m. x 7.85 = 66.144; say 67 bags of cement b h
Columns DIMENSIONS
Sand = 8.426 cu. m. x 0.42 = 3.539 cu.m.; say 4 cu.m. b h
C1 400 400
Gravel = 8.426 cu. m. x 0.84 = 7.078 cu.m.; say 7.5 cu.m. FTB 350 475
C2 375 375