PROJECT : SIERRA VALLEY GARDENS

LOCATION : Ortigas Ave. extension corner Suburban Drive


DATE : 13-Apr-23
SUBJECT : Production & Installation Work Schedule 2023-24

item Description Qty unit Start Finish

A Production
Tower 1
Grnd Flr 56 panels 15-May-23 30-May-23
2nd Flr 56 panels 31-May-23 14-Jun-23
3rd Flr 56 panels 12-Jun-23 25-Jun-23
4th Flr 56 panels 26-Jun-23 9-Jul-23
5th Flr 56 panels 10-Jul-23 23-Jul-23
6th Flr 56 panels 24-Jul-23 6-Aug-23
7th Flr 56 panels 7-Aug-23 20-Aug-23
8th Flr 56 panels 21-Aug-23 3-Sep-23
9th Flr 56 panels 4-Sep-23 17-Sep-23
10th Flr 56 panels 18-Sep-23 1-Oct-23
11th Flr 56 panels 2-Oct-23 15-Oct-23
12th Flr 56 panels 16-Oct-23 29-Oct-23
14th Flr 56 panels 30-Oct-23 12-Nov-23
15th Flr 56 panels 13-Nov-23 26-Nov-23
16th Flr 56 panels 27-Nov-23 10-Dec-23
17th Flr 56 panels 11-Dec-23 24-Dec-23
sub-total 896 panels

Tower 2
Grnd Flr 56 panels 15-May-23 28-May-23
2nd Flr 56 panels 29-May-23 11-Jun-23
3rd Flr 56 panels 12-Jun-23 25-Jun-23
4th Flr 56 panels 26-Jun-23 9-Jul-23
5th Flr 56 panels 10-Jul-23 23-Jul-23
6th Flr 56 panels 24-Jul-23 6-Aug-23
7th Flr 56 panels 7-Aug-23 20-Aug-23
8th Flr 56 panels 21-Aug-23 3-Sep-23
9th Flr 56 panels 4-Sep-23 17-Sep-23
10th Flr 56 panels 18-Sep-23 1-Oct-23
11th Flr 56 panels 2-Oct-23 15-Oct-23
12th Flr 56 panels 16-Oct-23 29-Oct-23
14th Flr 56 panels 30-Oct-23 12-Nov-23
15th Flr 56 panels 13-Nov-23 26-Nov-23
16th Flr 56 panels 27-Nov-23 10-Dec-23
17th Flr 56 panels 11-Dec-23 24-Dec-23
sub-total 896 panels
B Installation
Tower 1
Grnd Flr 56 panels 22-Aug-23 30-Aug-23
2nd Flr 56 panels 8-Sep-23 16-Sep-23
3rd Flr 56 panels 21-Sep-23 29-Sep-23
4th Flr 56 panels 6-Oct-23 14-Oct-23
5th Flr 56 panels 21-Oct-23 29-Oct-23
6th Flr 56 panels 5-Nov-23 13-Nov-23
7th Flr 56 panels 20-Nov-23 28-Nov-23
8th Flr 56 panels 5-Dec-23 13-Dec-23
9th Flr 56 panels 20-Dec-23 2-Jan-24
10th Flr 56 panels 4-Jan-24 12-Jan-24
11th Flr 56 panels 19-Jan-24 27-Jan-24
12th Flr 56 panels 3-Feb-24 11-Feb-24
14th Flr 56 panels 18-Feb-24 26-Feb-24
15th Flr 56 panels 5-Mar-24 13-Mar-24
16th Flr 56 panels 14-Mar-24 22-Mar-24
17th Flr 56 panels 23-Mar-24 31-Mar-24
sub-total 896 panels

Tower 2
Grnd Flr 56 panels 18-Jul-23 27-Jul-23
2nd Flr 56 panels 25-Jul-23 3-Aug-23
3rd Flr 56 panels 9-Aug-23 18-Aug-23
4th Flr 56 panels 24-Aug-23 2-Sep-23
5th Flr 56 panels 8-Sep-23 17-Sep-23
6th Flr 56 panels 23-Sep-23 2-Oct-23
7th Flr 56 panels 8-Oct-23 17-Oct-23
8th Flr 56 panels 23-Oct-23 1-Nov-23
9th Flr 56 panels 7-Nov-23 15-Nov-23
10th Flr 56 panels 22-Nov-23 30-Nov-23
11th Flr 56 panels 7-Dec-23 15-Dec-23
12th Flr 56 panels 22-Dec-23 3-Jan-24
14th Flr 56 panels 8-Jan-24 16-Jan-24
15th Flr 56 panels 21-Jan-24 29-Jan-24
16th Flr 56 panels 30-Jan-24 8-Feb-24
17th Flr 56 panels 9-Feb-24 17-Feb-24
sub-total 896 panels

C Delivery of PC panels 1792 panels 7-Jul-23 31-Mar-24


D Sealant application 1-Sep-23 7-Apr-24
E Rectification / Retouching 15-Aug-23 21-Apr-24
PRODUCTION & INSTALLATION WORK
May Jun Jul Aug Sept Oct
Duration
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

14-Jan-00
13-Jan-00
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days

14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
9 days
9 days
9 days
9 days
9 days
9 days
9 days
9 days
14 days
9 days
9 days
9 days
9 days
9 days
9 days
9 days

9 days
9 days
9 days
9 days
9 days
9 days
9 days
9 days
9 days
9 days
9 days
13 days
9 days
9 days
9 days
9 days
LLATION WORK SCHEDULE 2023 - 24