You are on page 1of 1

PROJECT NAME: TWO STOREY RESIDENTIAL BUILDING

LOCATION:

OWNER:

WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12 WEEK 13

1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6
ITEM NO. ITEM DESCRIPTION/ACTIVITIES QTTY UNIT AMOUNT % NO. OF DAYS

I. EARTHWORKS 12.00 cu.m ₱ 17,244.00 5.00 4

II. CONCRETE WORKS 34.8 cu.m ₱ 307,281.93 26.25 21

III. FORMWORKS AND SCAFOLDING 1.00 I.s ₱ 40,355.00 11.25 9

IV. MASONRY WORKS 265.00 sq.m ₱ 75,156.65 6.25 5

V. STEEL WORKS 1.00 I.s ₱ 47,188.25 11.25 9

VI. ROOFING WORKS 62.00 sq.m ₱ 62,649.76 5.00 4

VII CEILING WORKS 1.00 I.s ₱ 30,000.00 6.25 5

VIII. TILE WORKS AND PLASTER FINISH 370.00 sq.m ₱ 72,750.00 6.25 5

IX DOOR AND WINDOWS 1.00 l.s. ₱ 40,000.00 6.25 5

X ELECTRICAL WORKS 1.00 l.s. ₱ 39,613.02 5.00 4


XI PLUMBING WORKS 1.00 ₱ 36,875.00 4
l.s. 5.00
XII PAINTING WORKS 1.00 I.s ₱ 25,000.00 5
6.25
TOTAL ₱ 794,113.61 100.00 80 DAYS

TOTAL % OF WORK PER WEEK 7.50% 7.50% 6.88% 7.50% 7.50% 8.75% 9.37% 7.50% 7.50% 7.50% 7.50% 7.50% 7.50%

CUMMULATIVE % OF WORK PER WEEK 7.50% 15.00% 21.88% 29.38% 36.88% 45.63% 55.00% 62.50% 70.00% 77.50% 85.00% 92.50% 100%