You are on page 1of 2

REQUEST FOR INSPECTION (RFI) FORM

BOMI E&C CONSORTIUM

ESTABLISHMENT OF KENYA ADVANCED INSTITUTE OF SCIENCE AND


TECHNOLOGY
CONTRACTOR’S REQUEST FOR RFI Number:
INSPECTION RFI Issue Date:
Inspection Requested by Date:

I have inspected and the quality of the following works is adequate: (tick appropriately)
PART 1: TO BE FILLED BY CONTRACTOR STAFF (In accordance with GC Clauses 4.9 and 7.3)

Building Req. for Inspection No.


Element
Drawing No.
Material/s
I have inspected the works ☐ Inspection ☐ Testing ☐ Measurement ☐ Concreting
described here below and found
☐ other (Specify):
it ready for (tick appropriately)
Date ready for Inspection
Reinforcement Structural steel Formwork Civil works Electro-Mechanical
Sizes Sizes Tightness Levels Shafts sizes
Spacing Alignment Stability Compaction Embedded items
Alignment Surface Finishing Alignment Cable sizes
Wire brushing Welds Levels Pipe sizes Joints
Laps Joints Embedded items Joints Locations
Ties Surface Spacers Depths Ducts
Water bars Adaptable boxes
Bonding agent chambers
Dowels
Other (Specify)

Contractor staff Name Signature Name Signature


Surveyor
QA/ QC Engineer
Electrical Engineer
Mechanical Engineer
Civil Engineer
Construction Manager

SUBMITTED BY: __________________________ RECEIVED BY: ________________________________


Signature: ______________ Date: ____________ Signature: _______________Date: _______________
For Contractor – BOMI E&C CONSORTIUM Consultant: __________________________________

1
INSPECTION REMARKS
Comments: ………………………………………………………………………………………………………………………………………………….

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

…………………………………………………………………………………………………………………………………………………..……

With reference to the above request, you are hereby informed that after our inspection/ test/ measurement,
the section is:

Approved [ ] Approved with comments [ ] Address comments and request for Re-inspection [ ]

INSPECTED BY: CHECKED BY: RECEIVED BY:


____________________________ Kim Heon ____________________________
CONSULTANT ENGINEER SITE SUPERVISION TEAM LEADER BOMI E&C CONSORTIUM

Signature: _______________ Signature: _______________ Signature: _______________


Date: ___________ Date: _______________ Date: _______________

You might also like