MATERIAL INSPECTION REQUEST

PROJECT: Establishment of Kenya Advanced Institute ofScience and Technology (KAIST )


Ref. CONTRACTOR: BOMI E&C. Ref. ACT: K-AIST-BM-MIR-MEP-000
Sent by (name and company): BOMI E&C CO., LTD.
Sent to (Name and company): MINISTRY OF EDUCATION, (M.O.E)
We would like to request you to witness the following works:
Description of Work Material Name Location and Time

Inspection of material: CABLE TRAY (ST)/etc


TGBU6732895 / L1772844
HI - TBC TRAY/ etc
CMAU8997871 / L1772910
PVC CONDUIT PIPE COUPLINGS/etc KAIST -- Site
TCLU5779144 / L1772859

CMAU6894508 / L1772934 CABLE TRAY BOX CONNECTER/etc


APHU6691478 / L1772918
CD CONDUIT/etc

Note:This request must be submitted 24 hours before the inspection for in-site and 2 days in advance for off-site.
The contractor must submit method statement and/or detailed drawings, approved documents relevant for inspection. All forms
relative to the inspected activities must be attached to this form.
The Contractor shall give notice to the Engineer whenever any work is ready and before it is covered ip,put out of sight, or
packaged for storage or transport. The Engineer shall then either carry out the examination, inspection, measurement or testing
without unreasonable delay, or promptly give notice to the Contractor that the Engineer does not require to do so. If the
Contractor fails to give the notice, he shall, if and when required by the Engineer, uncover the work and thereafter reinstate and
make good, all the Contractor’s cost.
Inspection’s Results :
A. ProceedB. Proceed with commentsC. Revise & Resubmit  D. Rejected
Engineer’s Comments after inspection :

PACKING LIST

CONTRACTOR. ENGINEER / PM
Position: Position:

Signature: Signature:

Date: Date: