 HAZZARD IDENTIFICATION PLAN

 CONSTRUCTION SAFETY MANUAL


DRAWINGS

Work permits shall be secured prior to commencement of anchor bolt installation,


Proper egress and working platform shall be provided,
Form work where the anchor bolts are going to be installed shall be fixed firmly with the
supports,

Center of the template shall be marked on the template itself

Fig:1

With reference to the approved drawings marked the bolt locations on top of the templates,
Considering the center lines of template as the grid locations mentioned in the drawings
Fig:2

With respect to the dia of anchor bolt that is going to be used , the marked up locations on the
template for anchor bolts have to drilled 3 to 4mm more than the dia of anchor that is going to be
fixed ,
(i.e for bolt of dia 27mm ,the hole on the template shall be made up to 31mm),
This extra 3 to 4mm of the hole dia shall be used for fixing the bolt in precious location with help
of surveyor prior to concreting,

Fig:3
Fix the bolts in the template and insert in to the pedestal , the template shall be supported
adequately with supports to take load of the bolts without any sagging and keep the template
firmly fixed inits position during concreting
Anchor Bolts

Supports for template

The nuts for the anchor shall be fixed one at the bottom of the template and other at the top of
the template as shown in the below figure , this type of arrangement facilitates the adjustment of
bolt levels during setting out of anchor bolts prior to concrete pouring

Anchor Bolt Nuts fixed at top & Bottom

Fig:4

As per the approved drawings drawings mark up the grid lines for anchor bolts on top of the
shuttering ,
Fix the templates with the anchor bolts exactly on top of the survey guide lines, major
adjustments shall be made by shifting the template ,minor adjustments by shifting the anchor
bolts with in the dia provided in the template ,
Once its made sure that the template is in exact location, fix the position of the template firmly,

With the help of the surveyor start adjusting levels of the anchor bolts , the anchor bolts shall be
lowered or raised by turning the nuts at the bottom of the template ,
The bottom of anchor rods shall be secured to prevent movement or tilting of the anchor rods
during concrete placement.
Anchor bolt threads shall be covered with duct tape or other suitable means to keep them clean
and to prevent any damage that might occur during concreting of the foundation until completion
of grouting

Tolerances Unless otherwise specified in the contract documents, embedments shall be installed
in accordance with the tolerances shown in Table 1. The term “bolt group” used in Table 1 is
defined as the set of anchor bolts for a single fabricated steel shipping piece, or a single piece of
equipment or skid