AEN (TMC),
HWH/SDAH/ASN/MLDT
In recent past, BRANHS of UTV machine was detached during block, resulting rolling
down up to one KM followed by derailment by four wheels at TRR side. The above incident
has been taken very seriously by the Railway Board.
To avoid such type of unwanted incidents, it is hereby decided that –
1. All UTVs are to be inspected in details to find out deficiencies, if any. A PPT is also
attached herewith for your ready reference and wide circulation.
2. Check list for different kind of machines are also attached for working with track
machines. The same should adhere without any violation.
3. Check list of break system is also attached for your ready reference. All the
machines should be inspected in terms of the above check list within next 10 days.
4. Availability of KE valve. If not, action taken for procurement is initiated or not.
On completion of the above, a summery sheet in the following format is to be
prepared and submitted to HQ.
Description General pneumatic system Direct brake system Indirect brake system
of machine Available Working Available Working Available Working
(Yes /No) (Yes /No) (Yes /No) (Yes /No) (Yes /No) (Yes /No)
(Manoj Khan )
Chief Engineer/TMC
Eastern Railway/Kolkata
Copy to:-
1. PCE – for kind information please.
2. Dy. CE/TMC/HQ: for information and necessary action.
UTILITY TRACK VEHICLE
➢Introduction
Utility Track Vehicle (UTV) is a self propelled bi-directional
vehicle .
100
80
60
40
20
9 8 8 10 11 9 8
6 6 4 5 5 5 6 6 7 4 1 1
0
➢UTV – Crane Capacity
64
63
62
60
58
56
56
54
52
10 MT Crane 15 MT Crane
➢ Maintenance
1.Engine :
Daily check:-
❖ Oil level in engine sump
❖ Fuel level in tank
❖ Proper working of alternator and all control panel indicator
❖ Coolant level in radiator
• Weekly check:-
❖ Check and clean air filter element.
❖ Check the battery terminal.
❖ Check and fill the electrotype level in battery.
❖ Check all the joints for oil, fuel, water, air for leakage. Rectify if noticed.
Periodic check:-
❖ Change engine oil after first 500 km run and there after at every 4000 km run.
❖ Change the lub oil filter element after every 4000 km run.
❖ Change fuel filter element after every 8000 km run.
2. Transmission :
For a efficient transmission performance the oil temp should be maintained
between 80°C to 135°C.
4. Cardan shaft :
Attend as follows
❖ Greasing of slew system bushing, hinge pins and sliding pads --Every 120 hrs of
operation
❖ Cleaning of crane and greasing of all individual parts after cleaning--Every 750 hrs of
operation
❖ Replace bushing, hinge pins and sliding pads--Every 1500 hrs of operation
6. Air brake system :
9. Battery :
❖ Keep the terminal clamp clean. Apply Vaseline to prevent corrosion.
❖ Keep the top vent plug tight to avoid evaporation of electrolytes.
❖ Battery top should be kept clean and dry. Moisture and dirt cause
surface current leak resulting the battery running down.
❖ Check the electrolyte level regularly.
❖ Keep the cable connection tight, loose connection cause power loss.
❖ Always use distilled water.
10. Ultrasonic testing of axle :
❖ To ensure safety and reliability of rolling stock, the axles
should be examined periodically for detection of any fatigue
cracks by ultrasonic test using ultrasonic flaw detector.
❖ Testing of axles should be carried out by trained and certified
personnel only. Under no circumstances testing should be
carried out by any other personnel not meeting the
requirement.
❖ UTV is provided with two types of hose connections at either end. The upper hose is for vacuum brake and
lower hose for pressure brake. Connect vacuum hose to trailing wagon at attached end and non-attached ends
of UTV as well as trailing wagon hoses to be kept closed by uses of dummy coupling.
❖ At left side of control panel inside UTV cabin, 2 air shut off cocks have been provided, which is one for vacuum
brake and other for pressure brake application.
❖ Now ensure that vacuum brake shut off cock is opened and the pressure brake shut off cock is closed.
❖ For vacuum brake application auxiliary engine mounted on UTV floor to drive the vacuum pump should be in
running condition and vacuum gauge fitted on control panel in side cabin should give a reading of around 25
inches of Hg for complete release of trailing wagon vacuum brake.
❖ Get released parking brake as well as serving brake of UTV for free rolling. Now UTV with trailing wagon is
ready for traction.
❖ If the gauge is not showing the required vacuum, it indicates there is leakage of air in between hose couplings or
from any other place of vacuum line.
Braking Procedure :
❖ If SA-9 brake is applied to stop the UTV, this signal will also go to
vacuum control valve to disconnect the vacuum path from exhauster
and allow to connect the vacuum line to atmosphere through air
filter. As soon as vacuum drops, trailing wagon vacuum brake gets
applied.
❖ Now ensure that pressure brake shut off cock is opened and the
vacuum brake shut off cock is closed.
Move the single pressure optional brake lever from R to L to charge the air tank of
trailing wagon as well as to get release of spring actuated brake of trailing wagon. A
pressure of 5 kg/cm2 is required to release the brake of trailing wagon.
Get released parking brake as well as serving brake of UTV for free rolling. Now UTV
with trailing wagon is ready for traction.
To apply the brake, first apply the brake to trailing wagon by moving the optional brake
lever from L to R and then to UTV by SA-9 valve.
When optional brake lever moved from L-R to apply the brake on trailing wagon, the air
pressure drops below 5 kg/cm2 and distributor valve of trailing wagon comes in action
and exhaust brake chamber air of trailing wagon to atmosphere and also it disconnect the
charging of air tank.
To release the brake, bring back both optional brake lever and SA-9 valve lever to its
previous position.
Vaccum brake :
(I) Ensure that transmission range cum direction selector lever is in neutral
position.
(ii)Start the engine and allow the air tank pressure to build up to 2 to 2.5
kg/cm2 , At this pressure the engine throttle becomes operational.
(iii)Raise the engine speed by moving the throttle to build up the air pressure.
(iv)Ensure that service brake is in applied condition. Move the parking brake
lever to release condition once the air pressure reaches to 3.5 kgs/cm2 the
parking brake get released automatically.
1. When by-pass switch is operated the indicator does not change a. Loose connection in by-pass Tighten all terminals.
from RED to GREEN in low lube oil pressure. switch.
Check and replace.
b. Fault in by-pass switch.
Replace server.
c. Faulty server
2. The engine does not stop low lube oil pressure indicator glow a. Faulty relay. Check and Replace relay.
red.
b. Diode faulty Check and replace.
3. The hooter doesnot operate a. Faulty hooter Check and replace.
b. Loose connection or wire Check and tightened the terminals.
disconnected.
4. When ignition switch is switched ‘ON ’ The low lube oil a. Defective by-pass switch. Check and replace.
pressure indicator shines green.
b. Defective lube oil pressure Check and replace.
switch.
5. Radiator water temperature indicator illuminates red, even a. Short circuit between two wires Check and replace the wire.
when engine is stationery and cool. from sensor
Check and replace.
b. Defective sensor
6. During operation the red indicator of low oil pressure is not a. Faulty oil pressure switch Check and replace.
changing over to green and engine trips.
b. Two wire from oil pressure Check and replace the wire.
switch, get short circuit.
7. The radiator water level indicator remains red even when the a. Water level sensor cable Check and replace
radiator in filled. broken
Check and replace
b. Level sensor faulty
!!! THANK YOU!!!
Checklist of Brake system
Condition of compressor----
Pneumatic tank fill-up tirne-- (4-6 mins approx.)
OK Need to be replaced
1
Pressure setting ok Need Calibration
Overflow valve----
Setting pressure is 3.8 to 4
Reducing valve----
Setting pressure is 3.8bar (D brake) & 5bar (lndirect brake) ---
Safety valve----
Setting pressure is 9bar ---
ok Not Ok
2
Pressure setting of switches----
ZF drive disengage when b pressure reaches 3bar.
Yes No
3
Condition of Auxiliary brake ves Zb-03 ----
Working Not w ng
4
o Condition of brake pressure
Working Not
4. Emergency brake :
5. Safety brake :
Working Not I
5
6 b rake :
Working Not
a Other----
Date: Signature
Place: (lnspecting Official)
6
tr6rr crvlcrlv I PF€csEal r lltaLa&JYi Pl€ra€€r lrrdaa
BRAKE SYSTEM
Type
BOGIES
Pneumatic block brakes acting on all wheels according to U lc-regulations, one block per wheel.
CONTROL
During transfer under its own power the brakes are operated by a hand controlled valve. During work: direct hydraulic brakes
automatically operated by working control.
Parking brake
l\4echanical brake, activated by a hand wheel over a spindle, a chain pull, and levers, applying on the wheels of both bogies. The
parking brake is suitable for holding the self- propelled machine on a maximum gradient up to 20%.
Safety brake
The machine is equipped with a safety brake system which is deactivated in hydrodynamic travel drive mode and applied automatically when
the operator switch off the ZF dtive.
Emergency brake
For emergency situations, two separale emergency brake valves are provided at both cabins allowing the machine to be braked during
transfer. lt is located in such a place that it can be accessed both by the driver and his co-pilot.
ttctt <l,acrt,r MEcrst aa r Frf Lr.l€arfY trteor lrtdls
WATER
SEPRATER
Bt{,\tir.r P.\\lir.
(DIRECT + INt)IREC'T)
AIR OILER
,\IR I.\\]E ]
-
s'l oP a()cl{ 2-\vA VAI,VE BRAKE HOSE
F!
COUPLING
rds
!
2-\\'4',t',\',\t-\'E S.t.OP COCK
I I f -....,---- I'
ttcrt caErtcrtY I P&cr$€6a r ,t(tt &rrtl PlEo-Lrda-
PNEUMATIC CIRCUIT DIAGRAM
Ii
!t
l-"
lrl
II
t)l ll !,1 1l
lr1
ilrl ?r:
"11 il
it 5
ilrl
I
N!II:
,4.
@@'-*- (6) ,ri
5!
@
EI]J]E
Faecr|rl.ras
BRAKE
During the cycle of service of a brake block its play has to be re-adjusted for at least one time. lf the brake cylinder piston throw is
on its limit, the brake force decreases (as the brake-block play increases continuously) so that finally the brake cannot apply.
Usually the break block play (distance betvveen the brake block bottom and the wheel tread) is approximately 5-7mm. lf the value
exceeds the tolerances, check the brake piston stroke and adjust it, if necessary.
-
The brake block play has to be re-adjusted, when
NOTE: There is no need to disassemble the truss bar head and the brake leversll
xcrr c PAcrtY I PRLCrSrOta t t{LLaBa.rtY Pae-€r lrrdaa
Brake block
tt/t N
r I
I
LJ
I
I
I
(
Brake blocks:
Please pay attention to the decreased braking effect after replacing the brake blocks, if these are unworked or not run in
Therefore do not change all brake blocks at once (e.9. in two stages).
ra(lrl caPnorY I PREOSTOIa I F[af.a*.rtY Flc€- arrdaa
INDIRE BRAKB
RtrLEASE PTPPLY
POSITION POSITION
Ng i''{.AL
PO ITION
lr$rr cahclrY r PRE(ttil)i.. | ,rt rr...afrtl Fa&aae- l"rclat
il, '
I
i
I
L 5,r.
- I
\ ,'Dar
I' Sl# VCw
,t
mI
i'tl
LAP POSITION
racai c rlAaarY r PRei!€oaa a tEu/i6at:y Ptcle- ar.dla
Brakts PiFB
c Ht Dt,!v
Feed rSro[ve
-a_
AIr:ilifrr\, ftesEft|]ir
TRIFLE VP.LVE
I;
Slide Valri
L
L 5 Dar
\r!hEel
PrfrkE Blnrk
I Dat
BRAIlE Ci'LII.]DEF
--------------+
m Br8ke Pipe AiI - increasing in pressure
lo recharge Auxiliary Reservoir
and release brakes
Piston
Brfrh:e f,,,,lln':lEr gir rBduDin! in prersure
Sprin$ LU Ifltd!u LrrHliE:.
BRAKE RELEASE
rt(rt c{nAcrrY I Pr*crs&aa r ft(LtA8l,rry J'IE-- artda-
BrakE PIFE
,: -L :'..
Feed Groove
AuxiJienr Reserl,:rir
TRIPLE i'!LVE
3.8 lve
L 5 bar
\,",IEEI
BraliE Elo,lk Exhaust
I Eaa
BRAKE TYLINOER
Pirtorr
'rflnl!f, Breke Cylinder
BRAKE APPLY
g
i
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAILWAY BOARD
New Delhi, dL.22 .06.2015
No.201 S/Track'llUTK/2
,hrl'
Director Track(MC)
RailwaY Board
Encl:As above
CETMC NOTE No.3/13
NORTHERN RAILWAY
HEADQUARTERS OFFICE,
BARODA HOUSE, NEW DELHI.
Dy. C.E./TMC/Line,
Northem RailwaY,
State Entry Road,
New Delhi.
DA: As above
Copy to:
A. Personal
SN Item Authority Possible
Answer
1 Is valid Track Machine competency certificate SR4.65/3(a) Yes
available?
2. Is valid Medical fitness certificate available? sR4.65/3 (b) (iii) Yes
3 Is valid route leaming certificate of the sectionsR3.78(6) & JPO Yes
available? issued on 27-06-
2012
4 Is the machine staff self declared that liquor / sR 2.09 (1&2) Yes
intoxication not taken by him prior to report ON
Duty?
B. Yard.
I Is Track Machine stabled (normally) on a non- sR4.6sl7(iD Yes/No
running line?
2 Is the shunting order T-806 issued from SM/ASM sR4.65/5(i) Yes
to bring the machine in running line from the siding sRs. l3l2(i)
/ stabling line?
3 Is shunting staff with proper shunting order sRs.13( l ) Yes
available during shunting of machine?
4. ls T-465 (Machine following permit) issued for SR4.6sl1(x) Yes
movement of more than 1 machine & max. 3
machines for light path from one station to another
station?
5 Is T-409 issued to work all machines (max. 5 track SR4.6sl1(vii) Yes
machines)?
6 ls facing point locked by clamp for movement of SR5.l411(a) Yes
machine?
7 Is hand brake applied in machine to prevent rolling SR4.6sl7(iv) Yes
in siding?
8. Is brake feel test conducted before proceeding from SR4.31/1(a)(ii) Yes
siding?
C. Block Section Working.
I Is JE/SE of P.way available on machine for IRTMM-2OOO- Yes
working in block section? 4.2.2 & SR
4.6s(2)(b)
2 Is protection perfom.red at work site in block section rRTMM-2000- Yes
by SE/JE (P.way) 4.2.2 SR
4.6s(2Xb)
3 Is PTW issued by OHE supervisor for working of IRTMM-2OOO- Yes
machine in electrified area? 3.64(viii)&SR
17.04(l) (aXb)
4. Are all physical locking of working unit of As per inspection Yes
machines checked after availing block? check list issued
by RDSO
5 Are all the safety items checked for working IRTMM-2000-c s Yes
condition'l no. 15
6 Is JE/SE of P.way travel on last machine in work & SR4.6sls e(i) Yes
proceed mode & first machine in work & retum
mode?
sR4.6sls i(i)
7 Is 369-3b issued to pass the last stop signal at sR4.6sls f(i) Yes
DANGER position while returning?
8. Are all restriction followed as detail given in sR4.09( l ) Yes
caution order?
9 Is continuous whistling being done while IRTMM-2OOO- Yes
approaching to L-xing? 4.6.4 & SR 4.65(1)
(h)
10. Is the machine moving cautiously at very low speed GRe.07(5) Yes
which shall under no circumstances exceed 10
kmph in foggy weather / poor visibility/dust storm
etc?
11. Is minimum 120 meter distance kept machine to sR 4.6sll/x (i) Yes
machine while travelling & 50 meter while And SR 4.651 6/iii
working?
t2. Is speed of machine kept up to 40 kmph when sR4.6sl1,'( (i) Yes
moving in a convoy?
13. Is TTM working in same direction as of BCM? As per check list Yes
for tampers issued
bv HQ
14. Is temporary whistle board is provided by IRTMM-2OOO- Yes "
Note:-
NOR
HEADQUARTERS OFFICE,
BARODA HOUSE, NEW DELHI.
Sr. DEN/Co.ord.
Northern Railway,
DLI, FZR, LKO MB & UMB
You are advised to circulate these check lists right upto JE/P.Way level for their
guidance. ADEN of the section must ensure the implementation of the same whenever
the particular machine is working in his section. Sr. DENs should test check the same
during their trolley inspections. I am sure that the quality, progress of the work by the
track machines shall definitely improve after these check lists are followed by your
divisions.
Dl.. 6 Nos.
alc- ,*ro*J.
(Alok Kansal) l1'.','r-
Chief Engineer/Ttr/lC
Copy to:
S Item Yes/
No No
01 Whether layout including spacing of sleepers as per
relevant drawings ensured?(Daily)
02 Has the nose of the crossing may battered or wom or
the sleepers below it may get warped or bent. In such
cases, whether the crossing reconditioned or replaced
and sleepers below the crossing should be attended ?
(Daily)
03 Whether high points on the tum out and approaches
determined and general lift decided ? General lift of
minimum l0 mm must be given. (Daily)
04 Has during and before tamping, S&T and Electrical
staff e associated to complete their portion of work?
(Daily)
05 Has glued joint marked & made clear of S&T cable from
tarnping zone? Glued joint to be attended manually after
passing of machine?(Advancc)
06 Has wooden block & joggled fish plates if any
removed in advance? (Advance)
07 Has minimum cushion of 150 mm been ensured?
(Advance)
08 Whether sleepers uniformly spaced & squired?
(Advance)
09 Whether Hogged, battered and low joints attended?
4.0 TRT-P-WAY
S YES/
No. Dcscription of Work No
Has proper loading of PRC on BRN/BRH(before loading, floor free from
ballast,wooden batten 75mmx75mm in full length of 20 PRC,each layer
I
consist 20 PRC) in base depot ? (Daily)
Has all the 4 dowels in bridge rail and hold the locking pin in base depot?
2
Dail
Has long /broken/extremely rough bottom surface PRCs removed in base
J
t? Dail
4 Has em t crib ballast 4"to 5"from of sle rs? ail
Has shoulder ballast (cess side) preferably keep bottom level of
5
PRC(especially the locations at broken PRC? (Daily)
6 Has fastenin ERC's are free to move/ not ammed? (Advance
7 Has s uarin of sle rs ensured? Advance
8 Has the broken sl are removed? Advance
Has any lateral obstruction min. 50 cms from the end of PRC removed?
9 Dail
Has Water Pipes etb. burried in the ballast Lowered down 10" to I 2"
r0 below the bottom of PRC./ or Removed? (Advance)
ll Has lon size fish Iatc bolts/Jo le late removed? Dail
Has during night working Halogen at interval of 30 mts in Operator side,
12 in the length of work to be targeted + the length of Rake provided?
ail
l3 Has SEJ fell in len to be tar etcd removed ? Advance)
t4 Has isolated locations of hard bed overhauled ? Advance
Is the contractor Supervisor and sufficient work force available to depute
l5 the articular locations? Dail
Has the ramping out at thc tinte of closing the work with the 7 Woodcn
l6
Slee ers ? Dail
t7 Has prior block removed the Crib ballast completely, between the
previously laid 7 Wooden Sleepers for ramping? (Daily)
l8 Are Rail Cutting disc type Equipment/Gas cutting equipment set
complete-2 Sets, with operator/blacksmiths to work at two isolated
locations simultaneously available? (Daily)
20 Has reverse Jaw cut down in all the CST-9 Sleepers? (Daily)
S. Itcm Yes/No
No.
0l Has the requisite survey carried out and the
longitudinal profile and alignment shall be finished
well in advance ? (Advance)
02 Has track deep screened one or two days in advance
ofrelaying ? The ballast section should be built up to
the bottom of sleepers to facilitate relaying ?
(Advance)
03 Has auxiliary track laid at 3400 mm gauge on CST-9
or wooden blocks with spacing at 1.5 to 2.0 meters ?
(Daily)
04 Has auxiliary track of sufficient length in advance to
match with the delay progress of work. the auxiliary
track should be more than 50 mm higher than the
existing track ? (Daily)
05 Has the level of track not be more than 50 mm higher
than the existing track and have proper alignment
and cross level to avoid derailment of portal crane?
(Daily)
06 Has removal of ballast from the crib and shoulders
upto the bottom level of the sleepers ensured. (Daily)
07 Have full fittings of the old sleepers ensured avoid
their falling off while lifting released panels? (Daily)
08 Has sleepers are in single piece? All broken sleepers
should be removed or replaced in advance?
Advance )
09 Has on girder bridges, the guard rails at the
approaches on both ends removed temporarily?
Advance )
l0 Has level crossing opened properly in advance?
(Advance)
1l Has Proper planning and insertion of Switch
Expansion Joints at correct locations cnsured ?
(Advance)
12 Has availability of under noted equipments ensured
at site?
a) One set ofeach ofrail cutting and gas cutting
equipments in good working condition.
(Daily)
b) Two sets of rail closures of the each rail
section being laid in various sizes from 0.5m
to3mlengths.(Daily)
4 sets ofjunction fish plates with bolts(Daily)
r3 Has portable walkie-talkie sets available at site rn
working order? (Daily)
t4 Has proper protection of worksite done with banner
flag & detonators during block & follow the look out
caution on adjacent line? (Daily)
l5 Has cutting of LWR/SWR to single rails ensured for
lifting released panels? Otherwise, replace the
existing running rail by service rails for the stretches
which are to be re laid during the next day ? (Daily)
t6 Has temporarily disconnect or remove any other
permanent obstructions such as cables, signaling
rods and other obstructions like embedded rail piece,
tie bar etc to allow unhindered progress of work ?
(Advance)
l7 Has extra number of track panels fabricated in the
base depot to maintain a buffer stock for one or two
days of relaying work so that work at site does not
suffer for want of depot working ? (Advance)
CHECK LIST FOR TRACK MACHINES
6.0 T-28(P-WAY)
S Itcm Yes/No
No.
0l Has fumout assembled using Jib Crane near the site of tumout
replaced? The fittings of assembled tumout should be complete and
proper tightened & clamp also to be fitted on location If suitable
location is not available nearby, assembly may be done on nearest site
and transportation can be done with the help of trolleys available
with T-28 machine. (Advance)
02 Has infringements on the way checked in advance and movement
with slewin accordin I lanned ? Advance
03 Has rails on either side of existing tumout of the same section as that
of new tumout ? Advance
04 Has deep screening of tumout portion done? Ensure required cushion
and r er draina Advance
05 Has rail level taken for sufficient length on either side ofturnout?
(Advance
06 Has the layout calculation checked & correction if any done along
with la lt of turnou Advance
07 Has point machine disengaged and turn out non -interlocked before
takin its lacements? Advance
08 Has ballast from crib and shoulder ofsleepers removed upto sleeper
bottom for full tumout le ? ail
nq Has 60 wooden blocks, each approximately 60 cm long kept ready
for facilitatin assa e of crawler on the obstacles? (Dailv)
10 Has 4 nos. of rail pieces, each 70 cm long kept ready for housing
below the rail wheels of the crane? (Dail
ll Has Jumpering of both ends of the tumout done by OHE staff before
liftin and removin of existin turnout ? Dail
12 Has adequate arrangements made for protection of the line involved
and ad acent lines while the machine is workin ,) Dail
13 Has fish bolts should be lubricated and worked to facilitate easy
removal durin block. Advancc
t4 Has location where clamp of each crane will hold thc crossing and
switch rtions for liftin marked on the assembled turnout? (Dailv)
'r\
NORTHERN RAILWAY
HEADQUARTERS OFFICE,
BARODA HOUSE, NEW DELHI.
A self contained note on the above subjecl was put up to GMINR through Pr.CE
(copy enclosed). 12 No. of check lists have been issued for the various group of track
machines. You are advised to comply with the conlents of last para of this note. The
check list pertaining to SE/P.Way, TRD & S&T should also be submitled to this office in
lhis week for approval of undersigned.
DA: One
S. N. Iterrr Yes,tJo
0l Has the oil level in Hydraulic tank checked and topped up?
02 Has the lube oil level in engine checked and topped up?
03 Whether the gauges are in working order?
04 Is the emergency back up system in working order and has it
been checked as per laid down frequency i.e. in 200 hours
schedule?
05 Have all parts which are connected to machine becn secured
a nst tiltin & shift )
06 Has the oil level in the diesel tank checked & topped up?
07 After filling the HSD Oil tank, has it been ensured that
,/
cn ine is not started before 2 hours offil
08 Is the oil pressure safety circuit of engine in working order?
09 Has it been ensured that the tamper is working in the same
direction of BCM workin ?
l0 Has the L-Xing been opened in the width of 3 Mtrs in
advance for deploying machine for continuous working &
avoid time loss?
ll Has it been ensured that the data for design mode made
available for design mode tamping?
t2 Has it been ensured that the machine is working with
complete tamping tools and these are not worn-out by more
than20oh of its ori inal area?
l3 Has it been ensured that the adequate distance of l20M
maintained in between machines in block section while
,)
runnln
t4 Arc all the safety items available with machine as per Para
No.4.4.3 of IRTMM and its correction sli No.l5?
15 Has it been ensured that the proper lighting arrangement is
there in ni t workin ?
16 Have you ensured proper physical & electronic locking
before departure from site?
t7 Whether OHE block taken before permitting any person on
t of machine?
Iu Whether the tumout side sleepers supported on wooden
wedges while tarnping main line side?
l9 Whether S&T & electrical staff presenVassociated during the
block while workin in vicinit of d?
Check List for critical items of BCM
SN Itern Yes/No
01 Has thc oil level in Hydraulic tank chcckcd?
02 Ilas thc lube oil lcvcl in engirrc checked?
03 Whether the gauges are in working order?
04 Is the emergency back up system in working order?
05 Have all parts which are connected to the machine been secured
against tilting & shifting?
06 Has the gas cutting equipment been readily available and loaded
by SE/Pway with the machine?
07 Is the oil pressure safety circuit of engine in working order?
08 Are TTM & DGS working in same direction of BCM behind
BCM?
09 Has it been ensured that the adequate distance of l20M
maintained in between machines in block section while running?
l0 Whethcr TTM is following the BCM or Not?
l1 Has it been ensured that the proper lighting arrangement is there
in night working as well as on RE Mast?
t2 Has the L-Xing been opened in advance lbr deploying BCM for
continuous working in 4350mm width?
l3 Has the cutter bar (which is being left in the track on previous
day) been properly protected?
t4 Has it been ensured that the RE Mast protection device opened
before starting the work?
Check List for critical iterns of FRM
SN Item Yes/
01 Has the oil lcvel in Hydraulic tank checked and topped up?
02 Has the lube oil level in engine checked and topped up?
03 Whether the gauges are in working order?
04 Is the emergency back-up system in working order and has it been checked
as per laid down frequency i.e. in 100 hours schedule?
05 Have all parts which are connected to the machine been secured against
tilting & shifting?
06 Has the oil level in Diesel tank checked and topped up?
07 After filling the HSD Oil tank, has it been ensured that engine is not started
before 2 hours of filling?
08 Are the oil pressure & temperature safety circuits of engine in working
order?
09 Has it been ensured that adequate distance of 120 Meters maintained by the
following machine from TRT Rake in block section while running?
r0 Has the L-Xing been opened in the width of 3 Meters in advance for
deploying of TRT to avoid time loss?
l1 Whether speed certificate of 4OKMPH has been given to Supervisor P.Way
Inch. By Track Machine Inch.?
t2 Whether the sleepers loaded on BFR properly on 75 x 75mm cross section
wooden battens & are not eccentric before movement of rake?
( This is Joint responsibility of P.way & Machine Incharge)
13. Whether it has been ensured that the rails has been fixed on the BFRs for
loading of Ist layer of sleepers and BFRs are iiee from ballast?
t4 Are all the safety items available with machine as per Para No. 4.4.3 of
IRTMM and its correction slip No. l5?
l5 Have you ensure for proper physical locking before departure from site?
16 Has it been ensured that emergency air brake of machine is working properly
for stopping the rake/machine in case of emergency?
17. Has it been ensured that the proper lighting arrangement is there in night
working?
18. Has it been ensured that all 4 dowells and 2 locks of each rail bridge between
BFRs are not broken and has been fixed?
l9 Has the gas cutting equipment been readily available and loaded by SE/Pway
with the rnachinc?
20 Has it been ensured that 7 wooden sleepers for opening and closing of TRT
work site been made the part of TRT?
21 Has OHE Block been taken besides traffic block?
ZZ Whcthcr OHE block takc n before penqitting any person on top of machine?
Check List for Critical items of PORS Machine
SN ltgn Yes/No
0l Has the oil level in Hydraulic tank checked and topped up?
02 Has the lube oil level in enginc checked and topped up?
03 Whether the gauges are in working order?
04 Is the ernergency back up system in working order and has it
been checked as per laid down frequency?
05 Have all parts which are connected to the machine been
secured against tilting & shifting?
06 Has the oil lcvel in Dicscl tank checkcd and topped up?
0l After filling thc HSD Oil tank, has it been ensured that
engine is not started before 2 hours of filling?
08 Is the oil pressure safety circuit of engine in working order?
09 lf TTM is following PQRS, whether TTM had n.raintained
adequate distance of 120 Meters from PQRS Rake?
l0 Has the L-Xing been opened up to ends of sleepers in
advance for deploying of PQRS?
t1 Has the Auxiliary track been prepared as per laid down
instructions and as per Para 3.5.3 of IRTMM-2000 or not?
12 Whether wooden blocks are properly stabled on BFR & are
oil free?
l3 In case there is curved track, whether the portals have been
brought to straight track before unloading/loading?
t4 Whether speed certificate of 4OKMPH has been given to
Supervisor P.Way Inch. by Track Machine Inch.?
t5 Whether the panels loaded on BFR properly & are not
eccentric before movement of rake? ( This is Joint
responsibility of P.way & Machine Incharge)
t6 Are all the safety items available with machine as per Para
No. 4.4.3 of IRTMM and its correction slip No.15?
17 Has you ensure for proper physical locking before departure
from site?
It3 Has OHE block been taken bcsides traffic block in
electrified section?
t9 Whether OHE block taken before permitting any person on top
of machine?
Chcck List for Critical items of T 28 machine
S. N. Itcm Yes,t',lo
0l Has the oil level in Hydraulic tank checked and topped up?
02 Has the lube oil level in enginc checked and topped up?
03 Whethcr the gauges are in working order?
04 Is the emergency back up system in working order and has
it been checked as per laid down frequency i.e. in 100 hours
schedule?
05 Have all parts which are connected to machine been
secured against tilting & shifting?
06 Has the oil level in Diesel tank checked and topped up?
07 After filling the HSD Oil tank, has it been ensured that
engine is not started before 2 hours of filling?
08 Is the oil pressure safety circuit of engine in working order?
09. Has the location of laying of tumout jointly checked by
SSE/P way and SSE/TMC machine incharge?
10. Has the approach path or movement of T-28 crawlers is
adequately prepared to avoid settlement turn out been
assembled to the nearest available site?
1t. If the distance of assembled turnout is more than I00
meters, has it been ensured that hauling trolleys are in
working order?
t2 Has the sufficient arrangement of wooden blocks been
made in advance for crawler movement and placing of
tumout on uneven area?
l3 Has it been ensured that the propcr lighting arrangement is
there in night working?
t4 Has the gas cutting equipment been readily available and
loaded by SE/Pway with the machine?
l5 Are all the safety items available with machine as per Para
no.4.4.3 of IRTMM and its correction slip No. l5?
16 Has you ensure for proper physical locking before
departure from site?
t1 Whether the locations from where clamps of crane shall lift
the assembled tumout been rnarked/identified?
Iu Whether OHE block taken before permitting any person on
top of machine?
Check List for critical items of BRM
S Itern Yes/No
No.
0l Has the oil level in Hydraulic tank checked and topped
up?
02 Has the lube oil level in engine checkcd and topped up?
03 Whether the gauges are in working order?
04 Is the emergency backup system in working order and
has it been checked as per laid down frequency i.e. 200
hours schedule?
05 Have all parts which are connected to the machine been
secured against tilting & shifting?
06 Has the oil level in Diesel tank checked and topped up?
01 After filling the HSD Oil tank, has it been ensured that
engine is not started before 2 trours of filling?
08 Is the oil pressure safety circuit of engine in working
order?
09 Has it been ensured that the adequate distance of 120m
maintained in between machines in block section while
running?
t0 Has it been ensured that DGS is working only behind
TTM?
ll Are all the safety items available with machine as per
Para No. 4.4.3 of IRTMM and its conection slip
No.15?
l2 Has it been ensured that the proper vertical pressure i.e.
be tween 40 to 100 bars is being maintained?
13 Has it been ensured that the proper lighting
arranSemen t is there in night working'?
t4 Have you ensured proper physical & electronic locking
of machine bcfo re departure from site?
t5 Whether OHE block taken before permitting any person
on top of machine?
Check List for Critical items of UTV machine
S Ite m Yes/No
No.
01 Has the oil level in Hydraulic tank checked and topped up?
o2 Has the lube oil level in engine checked and topped up?
03 Whether the gauges are in working order?
o4 ls the emergency back up system in working order and has
it been checked as per laid down frequency i.e. in 200 hours
schedule?