Installation
Guide
9.3. Filling, stabilizing, testing and It is strongly advised to test the line in sections, for
depressurizing example the length of one-day installation. The line is
temporarily closed using, e.g. a test plug and a flange at
9.3.1. Filling and stabilizing the end. The blind flange should be provided with an air
release valve.
Fill the pipeline at the lowest point with water using a
small diameter branch connection and vent the trapped
air at the highest point(s) of the system. Long straight
sections may be vented using an inflatable ball or foam
pig to expel any air and impurities.