The document outlines the stakeholders and their descriptions for a reconstruction project of the CBA Building at Bulacan State University. The key stakeholders include Bulacan State University, the College of Business Administration, CBA students and professors/instructors, the government, and other users. President Gascon is also identified as a stakeholder as the current head of the university.
The document outlines the stakeholders and their descriptions for a reconstruction project of the CBA Building at Bulacan State University. The key stakeholders include Bulacan State University, the College of Business Administration, CBA students and professors/instructors, the government, and other users. President Gascon is also identified as a stakeholder as the current head of the university.
The document outlines the stakeholders and their descriptions for a reconstruction project of the CBA Building at Bulacan State University. The key stakeholders include Bulacan State University, the College of Business Administration, CBA students and professors/instructors, the government, and other users. President Gascon is also identified as a stakeholder as the current head of the university.
– Approve or deny scope change requests as appropriate
Sponsor – Evaluate need for scope change requests – Accept project deliverables
– Measure and verify project scope
– Facilitate scope change requests Project Manager – Facilitate impact assessments of scope change requests – Organize and facilitate scheduled change control meetings – Communicate outcomes of scope change requests – Update project documents upon approval of all scope changes
– Measure and verify project scope
– Validate scope change requests Team Leader – Participate in impact assessments of scope change requests – Communicate outcomes of scope change requests to team – Facilitate team level change review process – Participate in defining change resolutions Team Members – Evaluate the need for scope changes and communicate them to the project manager as necessary Design Deliverables Location (size/height/ distance) Benches In front of the building Curb Drops Both sides of the building
Tactile Paving Sidewalk and hallway
Comfort Room First floor Handrails Stairs and comfort Room Visual and Braille Signage Walls and doors
Audio-visual Alarm All levels of the buidling
Purpose
– to provide waiting area for all students including PWDs
– to provide accessible curb drops for wheelchair users – to provide proper pathways for visually impaired – to help visually impaired to navigate – to provide rest room that is compatible for PWDs – to help PWDs to move from one place to another
– to help visually impaired to navigate
– to help people with hearing-impairment to be notified in case of emergency
Deliverables Location
Automatic Door Middle Entrance
Visual and Braille Signage Walls and doors
Tactile Paving Hallway
Most right side Curb Drop of the building Handrails Walls and comfort room Comfort Room Ground floor
Audio-visual Alarm Entire hall
Design (size/height/ Purpose distance) – to provide easy-access door for PWDs
– to help visually impaired to navigate
– to provide proper pathways for visually impaired – to help visually impaired to navigate
– to provide accessible curb drop for wheelchair users
– to help PWDs to move from one place to another – to provide rest room that is compatible for PWDs – to help people with hearing-impairment to be notified in case of emergency
Nature of Project: Reconstruction Project
CBA Building Included Sidewalk Garden area Hallway Stairs Comfort room First floor ure of Project: Reconstruction Project CBA Building Valencia Hall Excluded Included Excluded Second to fourth floor Hallway Stage Existing trees Sidewalk High-level bleachers Non-PWD comfort room Low-level bleachers Parking area Classrooms Comfort room Entrance door Stakeholders Description Bulacan State University BulSU will be a stakeholder of the project since the project is within the scope of the said universi College of Buisness Administration CBA will be a beneficiary of the project because the reconstruction are mainly to CBA Building. W CBA Magnates CBA Magnates are called for the students of College of Business Administration. They are mostly Students in general Studends of Bulacan State University will be a beneficiary of the project since they will be using t Professors/Instructors Professors/Instructors are benefiaries as well especially those with disability. Government Since BulSU is a semi-government university, government is a beneficiary of the project as well w Other users Other users include the parents or guardian of the students, visitors, outsiders, other colleges, other the scope of the said university. President Gascon will be recognized as a user and beneficiary of the project for she currently runs the school. are mainly to CBA Building. With this, the college will be able to enrol all students; with or without disability. ministration. They are mostly beneficiary since magnates with disability will be able to cope up with their friends without disability. ject since they will be using the facilities that would be reconstructed.
ficiary of the project as well when it comes on public relations.
outsiders, other colleges, other universities, etc. Column1 Column2 Column3 Column4
Human Resource Department
Operations Department Finance Department ently runs the school.