Quality Control Plan in Medium Construction

Projects Case Study

Master of Science Thesis in Civil


Engineering Construction Project
Management

WALEED
ABD EL-RAHAMN
IBRAHEM
ELMALLAH

Student ID:
UM34553BPR43127

Department of Civil Engineering


Division of Construction Project Management
ATLANTIC INTERNATIONAL UNIVERSITY
Hawaii, Honolulu, USA 2014
Master’s Thesis
Quality Control Plan in Medium Construction Projects

ACKNOWLEDGMENTS
I’m deeply thankful to Allah by His Grace the present work was realized
I would like to express my best regards and appreciation to
ATLANTIC INTERNATIONAL UNIVERSITY specially the Advisor
Dr. Rosa Hilda and Tutors Mrs. Amaila Aldrett, Mr. Edward Lambert and
Mrs. Lourdes Puente for his instructive supervision, providing facilities,
continuous advice and encouragement.
I would like to express my deep and sincere gratitude and a special
acknowledgment to Eng. Abd Elrahman Elmallah my father and my
teacher for his encouragement, support and most of all his patience for
which I am truly grateful.
Grateful thanks to Prof. Dr. Eng. Ashraf Bastawisy, PhD the project
consultant, Professor of Architecture, National Center for Buildings
Research, for his fruitful help during the whole work of this thesis.
Can’t forget the preferred of Oryx Construction Industry team
specially Eng. Tamer Adham Oryx’s CEO.
My deep feelings towards my beloved mother, for her sincere help,
support and enduring the difficult times during this work.
A special debt of gratitude is gladly acknowledged to my wife Rania
for her help and encouragement and words could never express.
My gratitude is also extended to my Brother Eng. Amr Elmallah
CEO of Elmallah for Engineering & Contracting,
My deep feelings to my daughter Hana for helping and supporting
me and my baby Jana
Finally, I am also grateful to my Father and Mother in law for their
encouraging and supporting me.

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 1
Management
Quality Control Plan in Medium Construction Projects

PREFACE
In this thesis, Quality Control Plan have been investigated in a case study
which helped to realize how the construction industry works with this
concept. The research has been carried out from June 2014 to December
2014, at the Department of Civil Engineering, Atlantic International
University, USA.
The thesis has been carried out with Oryx Construction Industry,
a contracting company, where National Bank of Egypt VIP branch project
has been investigated in order to do this research. The research has also
been supervised by Atlantic International University and an examination
of the thesis regarding the language and formatting was made by Dr. Rania
Eltelbany, MSc. We appreciate for their help in this thesis.

Cairo, December 2014


Waleed Elmallah

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 2
Management
Quality Control Plan in Medium Construction Projects

TABLE OF CONTENT
Abstract
Abbreviations
Chapter 1
 Introduction
Chapter 2
 Project Description
Chapter 3
 Project Organization
Chapter 4
 Quality Control Method
Chapter 5
 Inspection
Chapter 6
 Field Testing Procedure
Chapter 7
 Submittals
Chapter 8
 Documentations
Chapter 9
 Revision to Work
Chapter 10
 Definable Features of Work
Chapter 11
 Pictures of the Project After & Before Implementation
Appendix
References

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 3
Management
Quality Control Plan in Medium Construction Projects

LIST OF FIGURE
Figure 1.1 The outline of the thesis

Figure 1.2: indicates the location of project

Figure 1.3: organization chart

Figure 1.7: submittal form (MRF)

Figure 1.11: Elevations before implementation

Figure 2.11: Elevations after implementation

Figure 3.11: Entrance before implementation

Figure 4.11: Entrance after implementation

Figure 5.11: Fence before implementation

Figure 6.11: Fence after implementation

Figure 7.11: Hall before implementation

Figure 8.11: Hall after implementation

Figure 9.11: second floor before implementation

Figure 10.11: second floor after implementation

Figure 11.11: Stairs before implementation

Figure 12.11: Stairs after implementation

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 4
Management
Quality Control Plan in Medium Construction Projects

ABSTRACT
Project Quality Management includes the processes and activities of the
performing organization that determine quality policies, objectives, and
responsibilities so that the project will satisfy the needs for which it was
undertaken. It implements the quality management system through
policy and procedures with continuous process improvement activities
conducted throughout, as appropriate.
The Project Quality Management processes include the following:
- Plan Quality: The process of identifying quality requirements
and/or standards for the project and product, and documenting how
the project will demonstrate compliance.
- Perform Quality Assurance: The process of auditing the quality
requirements and the results from quality control measurements to
ensure appropriate quality standards and operational definitions are
used.
- Perform Quality Control: The process of monitoring and recording
results of executing the quality activities to assess performance and
recommend necessary changes.
These processes interact with each other and with the processes in the
other Knowledge Areas. Each process can involve effort from one or
more persons or groups based on the project requirements. Each process
occurs at least once in every project and occurs in one or more of the
project phases, if the project is divided into phases. Although the
processes are presented here as discrete elements with well-defined
interfaces, in practice they may overlap and interact in ways not detailed
here.
Project Quality Management addresses the management of the project
and the product of the project. It applies to all projects, regardless of the
nature of their product. Product quality measures and techniques are
specific to the type of product produced by the project. While quality
management of software products uses different approaches and

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 5
Management
Quality Control Plan in Medium Construction Projects

measures than building a nuclear power plant, Project Quality


Management approaches apply to both. In either case, failure to meet
product or project quality requirements can have serious negative
consequences for any or all of the project stakeholders. For example
- Meeting customer requirements by overworking the project team
may result in increased employee attrition, errors, or rework.
- Meeting project schedule objectives by rushing planned quality
inspections may result in undetected errors.

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 6
Management
Quality Control Plan in Medium Construction Projects

ABBREVATIONS
NBE National Bank of Egypt Client

ACH Architectural Consulting House Consultant Representative

ORYX Oryx Construction industry Contractor Team

QC Quality Control

QCP Quality Control Plan

CEO ORYX Chief Executive Officer

CTO ORYX Chief Technical Officer

QCM ORYX Quality Control Manager

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 7
Management
Quality Control Plan in Medium Construction Projects

1. INTRODUCTION
This QCP (Quality Control Plan) will be implemented to ensure
remedial and construction procedures are performed in compliance with
the plans and specifications under the contract of The NBE (National
Bank of Egypt).
The quality control measures as presented herein include quality control
organization; methods of performing, documenting, and enforcing quality
control operations from ORYX (Oryx Construction industry)
(including inspection and testing); inspections to be performed; and
protocol describing corrective actions.
Overall management of the QCP (Quality Control Plan) will be the
responsibility of QCM (ORYX Quality Control Manager).
The QCM will have the authority to act in all matters and will be
responsible for ensuring that all materials and work comply with the
contract specifications. All inspection and testing firms will be at the
disposal of the QCM to ensure that all aspects of work are compliant with
the contract. The QCM will report any deviations from the QCP
independently to the On-site Project Manager. The resume of the ORYX’s
team designated attached.
1.1 Purpose
The purpose of this master thesis is to evaluate how the QCP process
is used in the construction industry and how the practitioners are
managing it every day. The theory of the quality control management
process will be compared to the actual practice in order to investigate
similarities and differences. In other words, the main idea is to see if
the construction industry is working with QCP as it is described in
the literature regarding the methods and techniques presented.
1.2 Limitations
The research focuses on the construction industry and is based on
theories of QCP described in the literature. The research was
complemented by a study of a construction project in Oryx

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 8
Management
Quality Control Plan in Medium Construction Projects

Construction Industry with some of the stakeholders involved in it.


Due to the limited research time of the thesis, the project was
investigated during the study of implementation bidding phase only.
1.3 Outline of the thesis
The research starts with a literature overview in order to provide the
theoretical context about the project in general terms with the focus on
the project life cycle. Further, a description of how the construction
industry is operating in the field of QC, including the definition of QC, a
descriptive part of the steps of the QCP, is then presented in order to
establish the foundation for this thesis.

DEFINABLE
REVISIONS FEATURES
TO WORK OF WORK

RESULT
INTRODUCTION THEORY

QUALITY CONCLUSION
PROJECT CONTROL
INFORMATION METHODS

Figure 1.1 The outline of the thesis

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 9
Management
Quality Control Plan in Medium Construction Projects

2. PROJECT DESCRIPTION
2.1 LOCATION
The building in Elmarghany St - Masr El-Jadeda – Cairo – Egypt.
Latitude: 30° 5'15.17"N Longitude: 31°20'2.98"E

Figure 1.2: indicates the location of project

2.2 PROJECT INFORMATION

PROJECT NAME: National Bank of Egypt – VIP Branch

DESCRIPTION: Renovation, Preparing & Finishing

FOOT PRINT: 450 M2

BUILTUP AREA: 1012 M2

LAND AREA: 4200 M2

PROJECT DURATION: 4 Months

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 10
Management
Quality Control Plan in Medium Construction Projects

3. PROJECT ORGANIZATION
The ORYX’s key personnel assigned to this project have possessed a
broad range of remedial action experience and skills. All have experience
dealing with the handling of contaminated wastes and should be familiar
with requirements of day-to-day work under this contract.
The ORYX’s proposed project organization for this project and the
resumes of key personnel, along with their job titles, will be submitted for
review and approval. A conceptual project
Organizational Chart is included in Appendix.
The functional responsibilities of key technical personnel are summarized
as follows.
President

CEO

On-Site
Project QCM
Manager

Technical Civil
Mechanical Elec.
Office
Engineer Engineer Engineer
Engineer

Staff Staff Staff Staff

Figure 1.3: organization chart

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 11
Management
Quality Control Plan in Medium Construction Projects

3.1 KEY PERSONAL




Oryx President


Oryx CEO


On-site Project Manager
Quality Control Manager

3.2 HOME OFFICE PERSONNEL


3.2.1 ORYX – President
The ORYX’s President will ultimately be responsible for the project's
success. He will provide the required resources to ensure that the project
is successfully executed. He will be kept informed of the project's
progress and maintain that the project is meeting its goals. The President
will resolve problems that cannot be resolved by the CEO.

3.2.2 ORYX – CEO


The ORYX’s Vice President and CEO will oversee the project at the
corporate level and report directly to the President. He will communicate
with the On-site Project Manager & CTO regarding all aspects of the
project including, but not limited to, project problems, progress,
payments, schedules, administrative duties, and QCM oversight. He will
also resolve problems that cannot be resolved by the On-site Project
Manager and will periodically visit the site and be acquainted with
personnel and procedures.

3.3 FIELD PERSONNEL


3.3.1 ORYX - On-site Project Manager
The ORYX’s On-site Project Manager, will be the primary contact person
at the site with ACH will interact on a daily basis under this contract.
The ORYX’s On-site Project Manager will ensure that:

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 12
Management
Quality Control Plan in Medium Construction Projects

• Appropriate resources are allocated to the project and balanced to


ensure best value.
• All tasks are conducted in accordance with the project
specifications.

The ORYX’s field personnel should rely on home office support


throughout the course of the project. The ORYX’s CTO and on-site
Project Manager will become and remain personally involved until each
problem is resolved and appropriate corrective measures are
implemented. They will typically communicate at least once daily on the
progress of the project.
The CTO will be present on the jobsite, to ensure that the project is
progressing as scheduled.
The On-site Project Manager is responsible for implementation and
support of the ORYX’s
QCP and will oversee all aspects of work under this contract for
remediation at the site, including:
• All procurements.
• Qualified Subcontractor resources are assigned to the project and
balanced to ensure jobs are aligned with project needs.
• The Site is maintained and secure.
• All tasks are carried out safely and in compliance with the project
specifications.
His responsibilities include:
• Subcontractors coordination.
• Acting as site liaison between the ORYX and Consultant.
• Maintaining charge of all field operations.

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 13
Management
Quality Control Plan in Medium Construction Projects

3.3.2 ORYX – QCM

The Quality Control Manager will report directly to the On-site Project
Manager with matters concerning quality control. He will have both the
authority and the duty to halt any operation appearing to be out of
compliance with contract specifications.
The QCM is responsible for keeping and maintaining all records related
to personnel, supplies, equipment use, and equipment calibration and
sampling. His function will be to ensure compliance with the contract
plans and specifications.

3.3.3 QCM responsibilities include:

• Performing and documenting field inspections.


• Preparing daily Quality Control Reports.
• Scheduling, reviewing, certifying, and managing project submittals.
• Maintaining the Submittal Register.
• Providing coordination of required quality control testing, reviewing
results, and submitting.
• Coordinating, documenting, and tracking preparatory, initial, and
follow-up inspections.
• Tracking construction deficiencies and ensuring timely corrective
action.
• Coordinating field sampling activities (as required).
• Reviewing calibration of test equipment (as necessary).
• Preparing addenda to the QCP as necessary when additional phases of
work are added.
• Maintenance of as-built drawings.
• Coordinating responses to vendors’ requests for information and
technical issues.

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 14
Management
Quality Control Plan in Medium Construction Projects

• Serving as main point of contact at the site for client questions and
discussions on quality and technical issues.
• Delegating duties to alternate QCMs and notifying consultant to whom
what duties have been delegated.
The QCM or an alternate will be on-site when work is being performed.

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 15
Management
Quality Control Plan in Medium Construction Projects

4. QUALITY CONTROL METHODS


The QCP will be implemented in order to ensure compliance with the
specifications for remedial action construction as detailed in the contract
specifications. The basis of the QCP is nationally recognized Egyptian
standards, Egyptian Code, the Project Specifications. In addition,
procedures utilized within the QCP should reflect the experience gained
by us in completing the project.
Quality control measures will extend to field sampling procedures;
staffing; types of material and equipment to be used; and methods of
performing, documenting, and enforcing quality control operations of
subcontractors (including inspection and testing).
As previously stated, maintenance of the QCP will be the responsibility
of the QCM. The QCM will be responsible for ensuring that all materials
and work comply with the contract specifications.
The QCM may have a field engineer at his disposal to assist him with the
on-site inspections.
Testing firms will be at the disposal of the QCM to ensure contract
compliance in all aspects of work. All reports from testing firms will be
forwarded to the QCM for his review and approval.

4.1 IMPLEMENTATION
The QCM will be responsible for implementing the QCP by ensuring that
quality materials and supplies are provided for the proposed project, and
that good workmanship is provided in all aspects of this contract. The
QCM will report directly to the On-site Project Manager and will
complete daily site inspections to ensure compliance with the quality
control specifications.

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 16
Management
Quality Control Plan in Medium Construction Projects

Daily reports will be completed listing all field testing and sampling
activities. These reports will be submitted to ACH on a daily basis. The
QCM will be responsible for ensuring that all materials and work comply
with the contract plans and specifications, and that all performance
standards are met.
It is anticipated that the ACH and the QCM will meet frequently in order
to forecast and/or prevent any potential problems from arising. An on-site
quality control meeting will be conducted on a weekly basis as part of the
weekly progress meeting in order to review performance during the
previous one-week period, and prepare for the upcoming two-week
period. It is anticipated that the ORYX’s On-site Project Manager, Health
and Safety
Officer and ACH will attend this meeting.

4.2 DOCUMENTING

The QCM will record project activities in a daily quality control report
maintained on site at all times. All site activities, site inspections, and
field testing of materials will be recorded on a daily basis, along with any
unacceptable site occurrences or deficiencies and their associated
corrective actions. Each daily entry into the report will be signed by the
QCM. Quality control reports will be submitted on a daily basis during
all field project activities.

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 17
Management
Quality Control Plan in Medium Construction Projects

5. INSPECTIONS
To ensure that all finishing and remedial activities comply with the
project specifications, the
QCM will complete, in conjunction with the subcontractors, three phases
of site inspections for each feature of work. These inspections will include
the following:

5.1 PHASE I - PREPARATORY INSPECTION


Preparatory inspections will be performed prior to beginning work on any
definable feature of the project and will include:
• Review of submittal requirements and all other Contract requirements
with the performance of the work;
• Check to assure that provisions have been made to provide required field
quality control testing;
• Examine the work area to ascertain that all preliminary work has been
completed;
• Verify all field dimensions and advise ACH of any discrepancies;
• Perform a physical examination of materials and equipment to assure
that they conform to approved shop drawings or submittal data and that
all required materials and/or equipment are on hand and comply with the
Contract requirements.
Subsequent to the preparatory inspection and prior to commencement of
work, ORYX shall instruct each applicable worker on the level of
workmanship required to meet contract specifications.

5.2 PHASE II - INITIAL INSPECTIONS


Initial phase inspections will be performed as soon as a representative
portion of the particular feature of work has been accomplished. Initial
inspections include, but are not limited to, examination of the quality of
workmanship; review of control testing for compliance with control

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 18
Management
Quality Control Plan in Medium Construction Projects

requirements; and identification of defective or damaged materials,


omissions, and dimensional requirements.
The initial phase inspection is the time to discuss and agree on the
required level of quality associated with a given work activity. Any
discrepancies relative to work quality should be addressed at this time.

5.3 PHASE III - FOLLOW-UP INSPECTIONS


Follow-up inspections will be performed daily as work progresses to
ensure continuing compliance with contract requirements, including
control testing, until completion of the particular feature of work. Final
follow-up inspections will be conducted and deficiencies corrected prior
to beginning new work.
The QCM will notify the ACH at least 24 hours in advance of any
inspections. Notification and meeting minutes of all inspections will be
recorded in the Daily Quality Control Report or visiting Minutes Report.
Examples of the inspection forms to be utilized are presented in
Appendix.

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 19
Management
Quality Control Plan in Medium Construction Projects

6. FIELD TESTING PROCEDURES


6.1 PURPOSE
This section establishes a system for the control of documentation and
records which provide objective evidence of the quality of items and
activites performed in accordance with the programmatic requirements.
The Quality Control Manager is responsible for the control, review,
verifications and maintenance of the documentation delineated in the
specifications.
6.2 REPORTING AND DISTRIBUTION OF REPORTS
Oryx will conduct field-testing to verify that control measures are
adequate to provide a product that conforms to contract requirements.
Field testing will be conducted under the auspices of the QCM and he or
his designee shall:
• Arrange for, or conduct, field testing in accordance with applicable test
parameters.
• Verify that facilities and testing equipment are available and comply
with testing standards and ensure that testing facilities are approved by
client and are validated.
• Check test equipment calibration data against certified standards.
• Verify that all tests are documented and submitted as part of quality
control system reporting.
• Review all test documentation prior to submittal.
Testing Agency Schedule
Project Name: Date: Project Number:
Agency Discipline Estimated Date of
Test

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 20
Management
Quality Control Plan in Medium Construction Projects

7. SUBMITTALS
This section describes the procedures for ACH processing of submittals.
The QCM will administer and control the processing of submittals.
After being reviewed for completeness, submittal documents will be
transmitted to the relevant project staff for review and verification for
compliance with contract requirements.
The submittal’s disposition will be noted on the submittal, which will be
signed, dated and returned. If required, ORYX will revise the submittal,
incorporating the comments and will resubmit it for review and
verification for compliance. Submittals will be logged and copies will be
retained in the project files. The ACH will follow standard procedures
concerning submittals, including the use of the QCM or ORYX
transmittal form. Each submittal form may contain more than one
submittal specific to that specification section.
This includes reviews of materials and suppliers’ catalog cuts, as well as
subcontractor submittals.
7.1 SUBMITTAL SCHEDULE
ORYX will submit and maintain a submittal schedule. The QCM will
review and after consulting ACH will approve the submittal schedule.
The schedule will be initially submitted within 14 days after the award
of the contract and then monthly with the monthly baseline schedule
updates.
The QCM shall work with the contractor to prioritize and sequence
submittals so that the most critical submittals are received and processed
first.
The submittal schedule will become the baseline against which receipt
of all required submittals will be compared. The approved submittal
schedule will be forwarded to NBE.

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 21
Management
Quality Control Plan in Medium Construction Projects

Figure 1.7: submittal form (MRF)

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 22
Management
Quality Control Plan in Medium Construction Projects

8. DOCUMENTATION
All testing results will be recorded on the daily quality control report. A
sample Daily QC report is included in Appendix. Any concerns or
deviations from the required material specifications and the actions taken
to correct the problems will be noted on the report. Information recorded
on the daily quality control report will include:
• Definable features of work that was addressed.
• Description of trades working on the project.
• Numbers of personnel.
• Types and numbers of tests performed.
• Results of testing.
• Nature of defects or cause for rejection.
• Proposed corrective action(s).
• Corrective action taken and date.
• Delays encountered.
• Directions received from the Engineer and actions taken.
• Health and safety issues or deficiencies and how they were
resolved.
• Deficiencies.
As example Pre-Final Inspection Checklist include:-
- Electrical
1. All lights
2. All outlets
3. Exhaust fans
4. Ceiling fans, attic fans
5. Breaker panel is properly labeled
6. Electrical system is properly grounded

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 23
Management
Quality Control Plan in Medium Construction Projects

- Plumbing
1. Each fixture has a shut off valve
2. Fixture drains properly
3. Floor drains work correctly
- Smoke detectors
1. Smoke detectors installed per plans
2. Smoke detectors work properly
3. Batteries installed in each unit
- Tempered glass
1. Tempered glass installed in proper locations (bathroom
tub surrounds, in doors, windows, next to doors, etc.)
- Windows and doors
1. All exterior doors close and lock
2. All openable windows open and lock

- Grading and drainage


1. The land has been graded
2. The earth slopes away from the foundation for 10’ @ 5%
slope
3. All water is directed to drain to the street or public property
as shown on drainage plan
4. Earth is a minimum of 6” below the top of the foundation

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 24
Management
Quality Control Plan in Medium Construction Projects

9. REVISIONS TO WORK
ORYX will be responsible for ensuring total compliance of field work to
the project specifications. Should modifications or revisions to the
specifications become necessary, ORYX will make the request, in
writing, to ACH Approval from ACH must be received prior to allowing
the modifications or revisions to be made in the field. The QCM will be
informed of and record all such requests in his daily log and on the daily
quality control report.
9.1 Design Review
Before starting implementation the entire design was reviewed by the
technical office Department it reviewed all of the design documents, the
QC plan and require compliance and documentation.
All major reconstruction projects will be reviewed by the Department at
key stages of development. These “Phase” reviews will take place at the
plan submittal.

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 25
Management
Quality Control Plan in Medium Construction Projects

10. DEFINABLE FEATURES OF WORK


Listed below are the general categories and types of work that will be
performed under the contract. These items, known as Definable Features
of Work, have been grouped into the various categories in which work
will be performed, and correlate to measurement and payment. Suitable
quality control methods and procedures will be utilized in order to ensure
that all work is performed to the standards and quality required by the
specifications.
The following are the definable features of work that will be performed
under the contract :
 Mobilization
 Site Preparation
 Plain concrete
 repair concrete for all structural elements
 Masonry work
 Water and Thermal Proofing
 Doors and windows work
 Finishing work
 Plastering work
 Flooring work
 Marble and Granite work
 Painting work
 False celling work
 Special work
 Special construction methods

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 26
Management
Quality Control Plan in Medium Construction Projects

 Mechanical work
 Pluming work
 AC work
 Firefighting Work
 Electrical work
 Low current electricity work
 CCTV work
 Demobilization
According to project BOQ
Construction Activities Contractor Primary Contact

☐ Trenching & layout


☐ Concrete

☐ Force Mains

☐ Masonry

☐ HVAC

☐ Plumbing

☐ Electrical

☐ Proofing

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 27
Management
Quality Control Plan in Medium Construction Projects

11. PICTURE OF PROJECT AFTER &


BEFORE IMPLEMNTAION

Figure 1.11: Elevations before implementation

Figure 2.11: Elevations after implementation

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 28
Management
Quality Control Plan in Medium Construction Projects

Figure 3.11: Entrance before implementation

Figure 4.11: Entrance after implementation

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 29
Management
Quality Control Plan in Medium Construction Projects

Figure 5.11: Fence before implementation

Figure 6.11: Fence after implementation

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 30
Management
Quality Control Plan in Medium Construction Projects

Figure 7.11: Hall before implementation

Figure 8.11: Hall after implementation

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 31
Management
Quality Control Plan in Medium Construction Projects

Figure 9.11: second floor before implementation

Figure 10.11: second floor after implementation

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 32
Management
Quality Control Plan in Medium Construction Projects

Figure 11.11: Stairs before implementation

Figure 12.11: Stairs after implementation

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 33
Management
Quality Control Plan in Medium Construction Projects

APPENDIX
TYPICAL CONSTRUCTION FORMS
Construction QC/QA Plan
The following typical forms are used:

 ORQ1: Daily Inspection Report Format

 ORQ2: Field Inspection Check List for Earth Work

 ORQ3: Daily Concrete Inspection Report

 ORQ4: Concrete Placement Check list

 ORQ5: Field Inspection Checklist Cement Brick or Block Work

 ORQ6: Field Inspection Checklist Plastering Work

 ORQ7: Field Inspection Checklist for Tilling

 ORQ8: Field Inspection Checklist for Painting

 ORQ9: Electrical Inspection Check List for Cable & Cable

Accessories / PanelBoard / Wiring Devices

 ORQ10: Electrical Inspection Test Sheet for Electrical Service and

Distribution System

 ORQ11: Electrical Inspection / Test Sheet for Light Installation

 ORQ12: Field Inspection Checklist Sanitary and Sewerage

 ORQ13: Water Supply Piping Inspection Checklist

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 34
Management
Quality Control Plan in Medium Construction Projects

 ORQ14: Project Punch List

 ORQ15:Pre-Final Inspection Checklist

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 35
Management
Quality Control Plan in Medium Construction Projects

Appendix ORQ1: Daily Inspection Report Format

PROJECT NAME:

CONTRACTOR: WEATHER CONDITION:

PRECIPITATION: INCH(S)

CONTRACTOR’S SUPERINTENDENT: GROUND CONDITIONS:

SUBCONTRACTORS (*): TIMES: START STOP

NAME / COMPANY CLASSIFI CATION HOURS

EQUIPMENT TIMES: START STOP

MEETING:

WORK BEING INSPECTED:

PROBLEM/DELAYS/CORRECTIVE ACTION TO BE TAKEN:

CONSTRUCTION ACTIVITIES COMPLETED AND /OR IN PROGRESS:

TYPE AND RESULTS OF INSPECTIONS:

TYPE AND LOCATION OF TESTS PERFORMED AND RESULTS:

HEALTH AND SAFETY OBSERVATIONS OR ACTIONS TAKEN:

SPECIAL SITE VISITORS:

Certification: I certify that the above report is complete and correct and that I, or my representative, have
inspected the work performed this day by the Subcontractors and have determined that all materials,
equipment, and workmanship are in strict compliance with the Contract Documents, Plans
and Specifications. Any exceptions to these contract requirements will be noted above.

Site Quality Control

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 36
Management
Quality Control Plan in Medium Construction Projects

Appendix ORQ2: Field Inspection Check List for Earth Work


Field Inspection Checklist Job Number Project Page of
Earthwork 1/2

CONTRACTOR: CONTR ACT NO:

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE):

ATTRIBUTE YES NO N/A


GENERAL

Is area released for work?


Is equipment adequate?
Are existing structures and utilities adequately protected?
Is removed material properly dispositional?
Dust and dirt control:

a) Haul routes maintained for dust control – by water or chemicals?

b) All paved areas kept clean?

EXCAVATION OF TRENCHING

Does completed depth and configuration comply with drawings and

Required shoring and bracing in place?


Existing utilities protected?
PLACING AND COMPACTING FILL

Excavation properly compacted and verified by test lab?

a) All sleeves, pipe cable, grounding, conduit installed and approved?

b) Approved fill material is used?

Is fill being placed in level lifts within thickness limits?


Is proper compaction attained and verified by test lab?
Have contaminated (and spongy) areas been cut out, filled and compacted with approved
material?
BEDDING AND BACKFILL OF PIPE AND UTILITY TRENCHES

Approved bedding and backfill material is used?

a) Is bedding fully compacted to support pipe or utility at line, grade, and slope required and
verified by inspector?

QC SIGNATURE: DATE:

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 37
Management
Quality Control Plan in Medium Construction Projects

Appendix ORQ3: Daily Concrete Inspection Report


Job Number Project Page
Daily Concrete Inspection Report of
1/1

CONTRACTOR:-------------------------------------------------------------------------------------------------------------------------

SPECIFIC LOCATION AREA/BUILDING-----------------------------------------------------------------------------------------

STATION: -------------------------- TO STATION:------------------------- OFFSET:--------------------------------

T/OFFS:------------------------------ ELEVATION:------------------------- TO ELEV:-------------------------------

CONCRETE TYPE:---------------- MIX NO:----------------------- ADDITIVES:--------------------------

TYPE OF DELIVERY:----------------------------------------------------------------------------------------------------------------

DELIVERY EQUIPMENT IDENTIFICATION/NUMBER:--------------------------------------------------------------------

PLACEMENT STARTED: DATE ----------------------- TIME------------------- SHIFT------------------


PLACEMENT COMPLETED: DATE----------------------- TIME------------------- SHIFT------------------

WEATHER CONDITIONS:----------------------------------------------------------------------------------------------------------

TOTAL CONCRETE PLACED: -------------------------------------------------------------------------------------------------

TOTAL CONCRETE WASTED:------------------------- REASON: --------------------------------------------------

AVERAGE SLUMP:--------------- TEMPERATURE:------------------ % AIR CONTENT:----------------

TEST CYLINDERS PREPARED:--------------------------------------------------------------------------------------------------


TRUCK IDENT:------------------- TOTAL CYLINDERS:------------- CYL IDENT: ----------------------
SURFACE CONDITION PRIOR TO PLACING:--------------------------------------------------------------------------------

MAXIMUM FREE FALL OF CONCRETE:------------ PROPER CONSOLIDATION: ---------------------------

AMOUNT VIBRATORS:---------------------------------- VIBRATORS IDENT/RPM:------------------------------

REINFORCING DISTURBED/REPLACED/REPAIRED: ---------------------------------------------------------------------

TYPE FINISH SPECIFIED: ---------------------------------------------------------------------------------------------------------

FINISHING STARTED: DATE----------------------- TIME--------------- SHIFT-------------

FINISHING COMPLETED: DATE----------------------- TIME ------------- SHIFT -------------

CONDITION OF FINISH:----------------------------------------------------------------------------------------------------------

DELAYS (INDICATE TYPE AND REASON: PERSONNEL, EQUIPMENT OR PLANNING):-------------------------

----------------------------------------------------------------------------------------------------------------------------------------------
OBSERVATIONS/REMARKS:-------------------------------------------------------------------------------------------------------

CONCRETE INSPECTOR:------------------------------------- DATE:----------------------------------------------------------

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 38
Management
Quality Control Plan in Medium Construction Projects

Appendix ORQ4: Concrete Placement Check list

Concrete Placement Checklist Job Number Project Page of


1/2
CONTRACTOR------------------------------------------------------------------------------------------------------------------------------

SPECIFIC LOCATION: AREA OR BUILDING------------------------------------- SHIFT -----------------------------

STATION-------------------------- TO STA. --------------------------------- OFFSET-----------------------------------

T/OFFS. --------------------------- ELEVATION-------------------------- TO ELEV.---------------------------------

CONCRETE TYPE------------------ MIX NO------------ ADDITIVES---------------- COMPUTED QTY----

LOCATION SKETCH – PROVIDE SPECIAL DIRECTIONS, DETAILS, FLOW DIRECTION, ETC.

REPLACEMENT VERIFICATION
1. ELECTRICAL SUPERVISOR: ITEMS TO BE CHECKED
CABLES/GROUND WIRE CONDUIT BOXES OTHER
COMPLETE/ACCEPTABLE TO DRAWING ---------- REV-----------------
-------------------- ---------------
SIGNATURE DATE
2. MECH./PIPING SUPERVISOR: ITEMS TO BE CHECKED
MECHANICAL INSERTS PIPING SLEEVES MECH. FRAMES OTHER
COMPLETE/ACCEPTABLE TO DRAWING---------- REV. -------------
--------------------- --------------
-------------------------------------------------------------- SIGNATURE DATE
3. CIVIL/STRUCT. SUPERVISOR: ITEMS TO BE CHECKED
ROCK CROSS SECTIONS TAKEN ROCK SURFACES PREPARED
SCREEDS SET LINE AND GRADE ESTABLISHED
FORMS REINFORCING STEEL
ALIGNMENT BRACING/SHORING CORRECT SIZE/GRADE LOCATION
INTERIOR SURFACE RELEASE AGENT LAPS. ADEQ. SECURED LEAN
CONSTRUCTION JOINTS PREPARED WATER STOPS WIRE TIES/FORM RODS
PLACEMENT/CONSOLIDATION EQUIPMENT AVAILABLE/ADEQUATE
SAFETY PRECAUTIONS OBSERVED FINAL CLEANING ACCEPTABLE
ACCEPTABLE TO DRAWING REV.--------------- ---------------------- ----------------------------

SIGNATURE DATE
QUALITY CONTROL INSPECTION VERIFICATION ---------------------------- ----------------------------

SIGNATURE DATE
OBSERVATIONS/REMARKS -------------------------------------------------------------------------------------------------------------
AUTHORIZATION FOR PLACEMENT -------------------------------------------- ----------------------------------

QC MANAGER: DATE

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 39
Management
Quality Control Plan in Medium Construction Projects

Appendix ORQ5: Field Inspection Checklist Cement Brick or Block Work


Job Number Project Page of
Field Inspection Checklist
Structural brick or block work 1/2

CONTRACTOR: CONTRACT NO:

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE):

ATTRIBUTE YES NO N/A


STORAGE OF MATERIAL

Covers and protection from weather

Set on pallet or dunnage to prevent contact with the ground or rain water?
Isolated from other material to prevent contamination?
MATERIALS

Are Bricks standard sizes and strength according to specification?


Is cement Portland?
Water quality good?

Is fine aggregate free from mud and impurities?


Is used equipment are adequate?
Is mixing proportion of Mortar ok and match with specification?

BRICK WORKING

Is Mortar type and mixed design match with specification?

Is work procedure according to brick working specification?


Is Damp proofing located?
Is Mortar mixing process and application correct?
Is Bond pattern ok?
Mortar joint thickness ok?

Is Mortar joint type, size, and alignment of head pattern ok?


Are Flashing weeps and vents correct?
Is Brick wall locations align with shop drawings?

Are Wall thickness and opening locations match with shop drawings?
Are Grade and walls within tolerance?
Continuing Raising of wall height acceptable and or within allowable limit?

REMARKS:
QC SIGNATURE: DATE:

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 40
Management
Quality Control Plan in Medium Construction Projects

Appendix ORQ6: Field Inspection Checklist Plastering Work

Field Inspection Checklist Plastering work Job Number Project Page of


1/2

CONTRACTOR: C ONTRACT NO:

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE):

ATTRIBUTE YES NO N/A


STORAGE OF MATERIAL

Cover and protection from weather damage?

Cover to prevent contact with the ground or rain water?


Isolated from other material to prevent contamination?
MATERIALS
Is cement Portland?
Water quality good?
Is fine aggregate free from mud and impurities?
Is used equipment are adequate?
Is mixing proportion of Mortar ok and match with specification?
PLASTERING WORKING
Is Mortar type and mixed proportion match with specification?

Is work procedure according to plastering specification?


Is Mortar mixing process and application correct?
Is check all conduits and other installation under the plaster?
Is wet and clean the wall surface before plastering?
Is plaster thickness ok?

Is Mortar type and mixed design match with specification?


Check the alignment of finishing surface?
Curing process provided?

Covers and protection from weather damage?


Provide proper curing after finish?
Used required material?
Use specified tile, grouts?
Is the surface finish within tolerable?

REMARKS:
QC SIGNATURE: DATE:

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 41
Management
Quality Control Plan in Medium Construction Projects

Appendix ORQ7: Field Inspection Checklist for Tilling

Field Inspection Checklist - Tilling Job Number Project Page of


1/2

CONTRACTOR: CONTRACT NO:

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE):

ATTRIBUTE YES NO N/A


STORAGE OF MATERIAL

Covers and protection from weather damage?

Cover to prevent contact with the ground or rain water?


Isolated from other material to prevent contamination?
Provide proper damage protection to tile?
MATERIALS

Is cement Portland?
Water quality good?
Is fine aggregate free from mud and impurities?
Is used equipment are adequate?
Is cement slurry thickness and mix ok?

Is grouted material according to specification and match with tile color?


Is tilling material according to specification and requirement?
TILING WORKING

Is tile bed ready for tiling?

Is work procedure according to tilling specification?

Is cement slurry mixing process and application correct?


Is clean tile bed before tiling?
Is mark tile grove line?

Is used adequate and required tools?

Is finishing level according to approved drawings?

Tile color and grout color according to architectural requirement?


Provide proper coverage to finishes until hardened?

REMARKS:

QC SIGNATURE: DATE:

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 42
Management
Quality Control Plan in Medium Construction Projects

Appendix ORQ8: Field Inspection Checklist for Painting

Field Inspection Checklist Job Number Project Page of


Painting 1/2

CONTRACTOR: CONTRACT NO:

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE):

ATTRIBUTE YES NO N/A


STORAGE OF MATERIAL
Covers and protection from weather?
Separately storage each type of paints?

MATERIALS
Types of paints are according to specification?
Is corresponding color?
All required equipment’s are available?

PAINTING
Check wall surface is ready for painting?
Applicable color and finishing type are ok?
Used materials are match with specification?
Provide adequate equipment?
Colors are match with required?
Finishing processes are according to requirement?
Weather condition good for process?
Painting materials have required concentration?
Applied surfaces are free from brush marks?
Finishing surfaces are according to approved drawings?
REMARKS:

QC SIGNATURE: DATE:

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 43
Management
Quality Control Plan in Medium Construction Projects

Appendix ORQ9: Electrical Inspection Check List for Cable & Cable
Accessories / Panel
Board / Wiring Devices

Electrical Inspection Check List Job Number Project Page of


Cable & Cable Accessories / Panel board / Wiring Devices 1/1

CONTRACTOR: CONTRA CT NO:

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE):

ATTRIBUTE YES NO N/A


Panel board installed at proper elevation and circuit breaker accessories provided are per
approved drawings and submittals?
Installed wiring devices and plates with approved material submittals?
Cable wire correct size and type?

Low voltage power cable in outlet box and panel board properly connected?
Cable size color code is correct and identification tags are installed at panel board/outlet
boxes?
Installed terminal lugs are correct size and application?
All conduit and outlet boxes and panel board properly grounded?
Continuity and grounding test complete?

Circuit index directory installed inside panel board?


REMARKS:

QC SIGNATURE: DATE:

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 44
Management
Quality Control Plan in Medium Construction Projects

Appendix ORQ10: Electrical Inspection Test Sheet for Electrical Service and Distribution System

Electrical Inspection Test Sheet Job Page of


Project
Electrical Service and Distribution System Number 1/1
CONTRAC
CONTRACTOR: T NO:
REFERENCES (DRAWING, SPECIFICATION, PROCEDURE):

MOLDED CASE CIRCUIT BREAKER RECORD


PANEL BOARD LOCATION
No: :
CABLE
CABLE NO: SIZE :
1.0 CERCUIT BREAKER DATA:
1.1 MANUFACTURER
1.2 TYPE AMPERE
1.3 THERMAL STRIP SETTING AMPERE
INSTANTANTANEOUS MAGNETIC TRIP
1.4
RANGE
2.0 CONNECTED LOAD DATA:
2.1 MANUFACTURER
2.2 NUMBER OF MOTOR / TRANSFORMERS
2.3 TOTAL KVA / KW / HP
2.4 VOLTAGE VOLTAGE
2.5 RATED FREQUENCY HZ
2.6 FULL LOAD CURRENT (FLC) AMPERE
3 TRIP SETTINGS:
3.1 THERMAL ( ) FIXED
( ) VARIABLE
3.2 MAGNETIC ( )% FLC
( ) AMPERES

REMARKS:

QC SIGNATURE: DATE:

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 45
Management
Quality Control Plan in Medium Construction Projects

Appendix ORQ11: Electrical Inspection / Test Sheet for Light Installation


Electrical Inspection / Test Sheet Job Number Project Page of
Light Installation 1/1

CONTRACTOR: CONTRA CT NO:

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE):

ATTRIBUTE YES NO N/A


Installed lighting fixtures comply with fixture schedule drawing?
Lighting fixture location is correct as shown on the design approved shop drawing?

Lighting fixture and fittings are installed correctly and tightly as specified in
the specification?
Lighting fixture fitted with fuse holder and enclosure cover?

Cable wire color code is correct and identification tags installed at panel
board? Continuity and grounding test completed?
All wire entries are sealed with a non-setting sealant?
Lighting photo cell control is correctly installed?

REMARKS:

QC SIGNATURE: DATE:

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 46
Management
Quality Control Plan in Medium Construction Projects

Appendix ORQ12: Field Inspection Checklist Sanitary and Sewerage

Field Inspection Checklist Job Number Project Page of


Sanitary and sewerage 1/1

CONTRACTOR: CON TRACT NO:

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE):

ATTRIBUTE YES NO N/A


Work site is ready for inspection.
All connections to equipment, pipe supports, joints bends etc. are accessible.
Work place safety guaranteed?

Latest revisions of the drawings are available at site?

Proper workmanship practice is used?

Pipe sizes, types, makes are as specified in material schedules /AFC


drawings/specifications?
Slopes of the sewerage lines are properly maintained as specified in AFC drawings?
Distance between manholes and ridding points are correct and according AFC drawings?
Benching of the manholes are correctly done as per AFC manhole detail drawings?

All sanitary appliances are as specified in material schedules, specifications and AFC
drawings?
Pipe ends are properly cleaned before applying the solvent cement and joining ?
Pipes are properly stored and free of debris?
All tests as specified are proposed in the sewerage piping network and test packs are
signed off?
REMARKS:

QC SIGNATURE: DATE:

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 47
Management
Quality Control Plan in Medium Construction Projects

Appendix ORQ13: Water Supply Piping Inspection Checklist

Water Supply Piping Inspection Checklist Job Number Project Page of


1/1

CONTRACTOR: CONTRACT NO:

REFERENCES (DRAWING, SPECIFICATION, PROCEDURE):

ATTRIBUTE YES NO N/A


Work site is ready for inspection?
All connections to equipment, pipe supports, joints bends etc. are accessible?
Work place safety guaranteed?

Latest revisions of the drawings are available at site?


Proper workmanship practice is used?

Pipe sizes, types, makes are as specified in material schedules /AFC drawings/specifications

Valves are installed properly, can be accessed easily, no obstructions for turning valve
handles?
Pumps are installed with all accessories, slope of suction pipe is maintained properly as given
in AFC drawing and specifications, proper workmanship practice are used so that no air
entrapped in the suction pipe?
Materials of pipe supports are used as specified in project specifications?

Distance between supports is as per close 5.3 of Section 3 (Water supply and sewerage) of
project specification?
Pipes are stored properly and internal surface is free of debris?
Pipe ends are properly cleaned and prepared before applying solvent cement and joining?

Visual inspection of pipe joints, all joints are solvent cement bonded?

Specified testing is in the water supply piping network is performed and test packs are signed
off?
REMARKS

QC SIGNATURE: DATE:

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 48
Management
Quality Control Plan in Medium Construction Projects

Appendix ORQ14: Project Punch List


Project

Name:

Project

No:

Date of

Inspection:

Inspector:

Punch
Description of Completion or Correction
Item
Acceptance

Prepared By:………………………… Reviewed By:…………………………

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 49
Management
Quality Control Plan in Medium Construction Projects

Appendix ORQ15:Pre-Final Inspection Checklist

Date / _/ Time Address_


Inspected by

Electrical
1. All lights
2. All outlets
3. Exhaust fans
4. Ceiling fans, attic fans
5. Breaker panel is properly labeled
6. Electrical system is properly grounded

Notes:

Plumbing
1. Each fixture has a shut off valve
2. Fixture drains properly
3. Floor drains work correctly
Notes:

Smoke detectors
1. Smoke detectors installed per plans
2. Smoke detectors work properly
3. Batteries installed in each unit
Notes:

Tempered glass
1. Tempered glass installed in proper locations (bathroom tub
surrounds, in doors, windows, next to doors, etc.)
Notes:

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 50
Management
Quality Control Plan in Medium Construction Projects

Windows and doors


1. All exterior doors close and lock
2. All openable windows open and lock

Notes:

Grading and drainage


1. The land has been graded
2. The earth slopes away from the foundation for 10’ @ 5% slope
3. All water is directed to drain to the street or public property as shown on
drainage plan
4. Earth is a minimum of 6” below the top of the foundation
Notes:

Miscellaneous
1.

2.

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 51
Management
Quality Control Plan in Medium Construction Projects

References

1- A GUIDE TO THE PROJECT MANAGEMENT BODY OF


KNOWLEDGE
(PMBOK® Guide)—Fourth Edition
An American National Standard ANSI/PMI 99-001-2008
Project Management Institute Licensed To: waleed elmallah PMI Member

2- Construction Management
(second edation) – By Daniel W Halpin Purdue University - Ronald W.
Woodhead University of New south Wales 1998.

3- Construction Program Management and Inspection Guide


FEDERAL HIGHWAY ADMINISTRATION August 2004 King W. Gee
Associate Administrator Office of Infrastructure

4- ISO 9000 Quality Standers in Construction By Abdulaziz A. Bubshilt


Member ASCE and Tawfiq H. Alaiq

5- American Society of Civil Engineers, "ASCE Professional Grade


Descriptions"
ASCE Guide to Employment Conditions for Civil Engineers, ASCE -
Manuals and Reports on Engineering Practice, 2nd Edition, 1980, pp. 5-7.

6- American Concrete Institute, "Qualifications of Personnel for


Inspection and Testing Duties"
Guide for Concrete Inspection, ACI 311.4R-88, Manual of Concrete
Practice, 1988, pp. C-12 and C-13.

Waleed Abd El rahman Ibrahem Elmallah


Master of Science Thesis in Civil Engineering Construction Project 52
Management