SHIMIZU CORPORATION
Int’l Division – Engineering Department
Global Network
1804 1900 2000
Mode Gakuen
Cocoon Tower
Head Office of TOYOTA
Japan’s National Bank
Concept of Green Float
Offices in 21 countries
Employees: ~16,000
CONTENTS Duration
• Shimizu-Int’l Division BIM Implementation Roadmap 05mins
Shimizu has been using In-house 3D coordination software in Japan since 1984.
Shimizu đã tự phát hành và sử dụng phần mềm 3D coordination từ những năm 1984
2003
B
A
B C
A
2010. Thành lập Trung tâm CNTT Xây dựng giúp các cơ quan quản lý và công ty xây dựng
khởi động BIM
2011. Làm việc với các cơ quan quản lý về các dự án thí điểm
2017
2012. Làm việc với các cơ quan quản lý để chuẩn bị cho các chuyên gia tư vấn và nhà thầu
đảm nhận dự án khu vực công sẵn sàng cho BIM
2015
2013
PHASE-1
2003 ( General Function )
• 3D
• 4D
• Connection details
• Coordination ASME
• Shop drawing
PHASE-1
( General Function )
• 3D
• 4D
• Connection details
• Coordination ASME
• Shop drawing
PHASE-1
( General Function )
• 3D
• 4D
• Connection details
• Coordination ASME
• Shop drawing
PHASE-1
( General Function )
• 3D
• 4D
• Connection details
• Coordination ASME
• Shop drawing
PHASE-1
( General Function )
• 3D
• 4D
• Connection details
• Coordination ASME
• Shop drawing
PHASE-1
( General Function )
• 3D
• 4D
• Connection details
• Coordination ASME
• Shop drawing
PHASE-1
( General Function )
• 3D
• 4D
• Connection details
• Coordination ASME
• Shop drawing
2013. Bắt buộc áp dụng BIM- Kiến trúc cho tất cả các dự án xây dựng mới > 20,000 m2
2014. Bắt buộc áp dụng BIM cho tất cả các dự án xây dựng mới > 20,000 m2
2017
2015. Bắt buộc áp dụng BIM cho tất cả các dự án xây dựng mới > 5,000 m2
2015
2013
PHASE-2
(Automatic Function )
PHASE-1
2003 ( General Function )
• Clash detection
• Quantity take off
• Link to other
• 3D software schedule,
structural analysis,
• 4D etc
• Connection details
• Coordination ASME
• Shop drawing
PHASE-2
(Automatic Function )
• Clash detection
• Quantity take off
• Link to other software
schedule, structural
analysis, etc
PHASE-2
(Automatic Function )
• Clash detection
• Quantity take off
• Link to other software
schedule, structural
analysis, etc
PHASE-2
(Automatic Function )
• Clash detection
• Quantity take off
• Link to other software
schedule, structural
analysis, etc Schedule software BIM Model
PHASE-2
(Automatic Function )
• Clash detection
• Quantity take off
• Link to other software
schedule, structural
analysis
PHASE-2
(Automatic Function )
• Clash detection
• Quantity take off
• Link to other software
schedule, structural
analysis, etc
2017
2015
PHASE-3
2013 ( Full Function )
PHASE-2 PHASE-1 + PHASE-2
(Automatic Function )
• Full BIM
PHASE-1
2003 ( General Function )
• Clash detection
• Quantity take off
• BIM for FM
• Common
collaboration platform
• Link to other software
schedule, structural
• 3D analysis
• 4D
• Connection details
• Coordination ASME
• Shop drawing
PHASE-3
( Full Function ) COBie data embedded in BIM Model
PHASE-1 + PHASE-2
• Full BIM
• BIM for FM Sample COBie Template
• Common collaboration
platform
PHASE-3
( Full Function )
PHASE-1 + PHASE-2
• Full BIM
• BIM for FM
• Common collaboration
platform
Collaboration
Platform
• Share BIM Project Information
remotely
• Clash results, Mark-ups, etc
• Model Interrogation
• 4D Planning Tools.
COPYRIGHT © SHIMIZU CORPORATION APPENDIX-(I) INTERNATIONAL DIVISION – BIM WORKING COMMITTEE
International Engineering Department
Conventional Process
Specialist / Sub-
cons Input
Reject Problem
Reject Found
BIM Process
Solutions 1
Specialist / Sub- Problem Solutions 2
cons Input Found Solutions 3
…
Construction Coordination /
Shopdrawing Construction
Drawing Collaboration
(MBC2)
Design & Build Office
Project with full BIM EXISTING
Implementation MAPLETREE
BUSINESS CITY II
MAPLETREE BUSINESS CITY
(MBC I)
(MBC II)
Client = MAPLETREE
*Artist’s impression
Project Sum = SGD$350 Mil.
Cost of drawings is
20% less than other
Non-BIM Project.
An increase of approx. 27
AR models 2.77 GB
times the original data
size STR models 1.40 GB
ME models 5.04 GB
AR models 341 MB
Total file size 9.21 GB
Complex structural
geometry & Site Execution /
Coordination can be
conducted with ease using
BIM-to-Field solutions.
BIM BOARD
Approximately 80 images were selected and plotted from different areas of the
BIM models to be displayed for use by the construction team, sub-contractors
and site workers.
AutoCAD
Export to Export
AutoCAD for
consultants
not equipped
with BIM
Uses:
Using “Point layout” add-in to identify the coordinate points and export information to surveyor for their input to the station. Surveyor can
easily able to select the points from the BIM model via the iPad.
Advantages:
• Improves the productivity of surveyor.
• Reduces discrepancies upon transfer of information.
COPYRIGHT © SHIMIZU CORPORATION INTERNATIONAL DIVISION – BIM WORKING COMMITTEE
International Engineering Department
1) Add points to the model 2) Export information to .txt file 3) Load file to Total station 4) Make measurement
(X , Y, Z coordination point)
KEY HIGHLIGHTS
This project actively
involved the Client and
End-user via the use of
BIM tools.
Routine BIM Collaboration Meeting in BIM room
BIM ROOM
IMMERSIVE VR
KEY HIGHLIGHTS
This project has to comply
with the Client’s use of BIM
Model for Facilities
Management via COBIE.
Frequency of maintenance
for both preventive &
predictive.
Modelling of Services
KEY HIGHLIGHTS
Invited to BCA and
consultant office to
participate in their BIM
workshop to share with
them the BIM Experience in
YCH Project.
Contributed to the YCH Shimz BIM Manager giving BIM YCH Shimz BIM Manager speaking at
publication of the BCA Orientation to BCA Management staff Project Consultant Office on BIM Use
BIM Essential Guide for
Collaborative Virtual Design
and Construction.
SHIMZ SHIMZ
Misc. Fire PSG Structural Roombook
(Lift, RDWP, etc)
BIM Team BIM Team
SHIMZ SHIMZ
ACMV ELECT M&E Archi VDC Session Area
BIM Team BIM Team
IN-PROGRESS AHEAD
DELAY COMPLETED
Resource Sharing
INTERNATIONAL DIVISION
International Engineering
Department
We propose step by step tools to secure Client consensus for Operating Theatre Design
We propose an effective Workflow for determining the factors for the Operation Theatre Installation of complex functions and construction
schedules by using our experiences.)
Chúng tôi đề xuất các công cụ theo từng bước để đảm bảo sự đồng bộ của khách hàng đối với thiết kế phòng mổ.
Chúng tôi, bằng kinh nghiệm thực tế của mình, sẽ đề xuất Quy trình triển khai các bước cho từng bộ phận chức năng và lịch
trình lắp đặt thiết bị phòng mổ.
Mô phỏng ảo
ROOM BOOK Virtual Mock Up
ROOM BOOK
For operating rooms that become complicated processes, clashes detection and check the process using the 4D BIM,
including the direct work and other package such as medical equipment of hospitals.
Đối với phòng mổ có quy trình phức tạp, dễ dàng phát hiện xung đột và kiểm tra quy trình bằng 4D BIM,
bao gồm cả việc phối hợp với công tác xây dựng và các gói khác như thiết bị y tế.
For operating rooms that become complicated processes, clashes detection and check the process using the 4D BIM,
including the direct work and other package such as medical equipment of hospitals.
Đối với phòng mổ có quy trình phức tạp, dễ dàng phát hiện xung đột và kiểm tra quy trình bằng 4D BIM,
bao gồm cả việc phối hợp với công tác xây dựng và các gói khác như thiết bị y tế.
For operating rooms that become complicated processes, clashes detection and check the process using the 4D BIM,
including the direct work and other package such as medical equipment of hospitals.
Đối với phòng mổ có quy trình phức tạp, dễ dàng phát hiện xung đột và kiểm tra quy trình bằng 4D BIM,
bao gồm cả việc phối hợp với công tác xây dựng và các gói khác như thiết bị y tế.
For operating rooms that become complicated processes, clashes detection and check the process using the 4D BIM,
including the direct work and other package such as medical equipment of hospitals.
Đối với phòng mổ có quy trình phức tạp, dễ dàng phát hiện xung đột và kiểm tra quy trình bằng 4D BIM,
bao gồm cả việc phối hợp với công tác xây dựng và các gói khác như thiết bị y tế.
VR system:
https://shimz-idd.shapespark.com/th_opt_room_1/
THANK YOU