14-FEB - JSA - SA - GHWP - Relay Module Connection Change Work

You might also like

You are on page 1of 1

PROJECT ELEPHANT

JOB SAFETY ANALYSIS


Name of Contractor: M/s Canter Engineers Pvt. Ltd.

JSA For workpermit Number:

Date Valid from:

Work permit time: 09 Am To 09 Pm

Location of work: 0 mtr. Level, Grid 09-25 (F-I), Welding Room and Dai/Mould Clean room.

Nature of activity: FAS Relay Module Connection Change work. by scaffolding (05 mtr. Height)

Sr. No. Description of work Hazard associated with the job Action Taken

* Only inducted worker shall be deputed at the workplace.


* Untrained Worker. * All the engaged workers should be medically examined as per the BOCW state
1 Manpower Engage * Un-fit worker rule 2007 rule 250C.
* Un Trained person * TBT must be conduct prior to start the work.
* Only trained & physically fit personals will be allowed to execute the activity.

Manual Material shifting to the work place *Housekeeping should be done before starting the work.
2 *Slip, Trip & Fall hazard
(Scaffolding Material, Hand tools, Relay Module Etc.) *Area should be clean & free from any obstruction before starting of the activity.

*On or above 1.2 meter height, every one should use double lanyard FBSH while erection of scaffolding.
*Fall from height
*Scaffolding should be properly erected, inspected by the job supervisor & tagged before use.
3 Scaffolding erection (Max height 05 mtr.) *Scaffolding colapes
*If scaffolding is not in use same should be red tagged.
*Improper scaffolding
*1.3 ratio should be maintained, while erection of the scaffolding.

*Only trained and fit workers shall be deploying for work at height.
* Area to be barricaded to restrict unwanted personnel entry.
* Use inspected FBSH with safe and proper anchor point.
* Provide toe board to protect fall of materials.
* Provide Top rail on 1 meter and mid rail 500mm height and 150mm toe board to prevent falling object.
* Provide proper access to scaffold.
* Fall of person
* Provide outriggers to protect of scaffold to collapse.
* Fall of materials
* Platform shall be fully covered and tied.
* Collapse of scaffold
FAS Relay Module Connection Change work. * Don’t put over weight on scaffold platform.
4 * Overhead obstructions
By scaffolding (Max height 05 mtr.) * Ensure overhead obstruction while move of scaffold.
* Over weight
* Wheel should be always locked while work is going on scaffold.
* Over reaching on scaffold
* Don’t overreach on scaffold.
* Unsafe scaffold
* Material shall not be thrown, Rope shall be providing to shift the materials.
* Inspection shall be done by job supervisor.
* Scaffolding shall not be pulled /pushed when workmen present on the scaffolding. Don’t allow any
unknown party near to scaffold.
* Green tag shall be display on safe scaffold.
* Area shall be barricade; Sign board shall be displayed.

*Area should be clean, housekeeping should be done after completing the activity.
After the work *All the unwanted material(Scaffolding material, pipe cut piece, Cutting dust, hand tools etc.) should be
5 Area Housekeeping *Slip, Trip & Fall hazard removed from the work place.
Unwanted material remove *After compleating the work area housekeeping should be done & pictures should be shared in whatsapp
group as instructed by PTdCS Safety.

* Emergency Path way & Assembly Point shall be clean, clear& communicated.
* Panic situation * Access should be clear from obstruction.
6 In Case of Emergency
* Confusion * Ensure emergency vehicle is readily available at all time.
* Awareness of emergency contact.

Remarks:

Signature: Signature: Signature: Signature:

Name: Name: Name: Name:

Job Initator(PTdCS) Project Manager (contractor) Section Incharge (Datwyler) Safety Manager(PTdCS)

Signature: Signature: Signature: Signature:

Name: Name: Osama Zakir Name: Name:

Contractor Job supervisor Safety Manager(Contractor) Area owner(Datwyler) Safety Manager(Datwyler)

You might also like