You are on page 1of 27

Method Statement

Outline Demolition Method Statement


34 Springvale Avenue
Walsall
WS5 3QB

Company Issuing Integrated Company Carrying TBA


statement Designs & out Demolition
Associates Ltd.
Method Statement No. AS-101-TW-01 Revision No. 02
Title Demolition of Building
Start of Works Date TBA Duration TBA

Revision History
Doc No. Rev No. Issue Date Author Description of Modifications
AS-101-TW-01 01 06/04/18 ANS Draft copy issued for comments
AS-101-TW-01 02 11/04/18 ANS Draft copy sent to client

This Revision
Print Name Position Description of Modifications
Author Ashish Sehdeva Building Surveyor Draft copy sent to client
Checked by Paramjit Sehdeva C. Director

Status of Revision 02
Overall Approval Status Yes No Date
Cat A - Accepted for Implementation. Work may proceed planned
Cat B - Not Accepted for Implementation. Resubmission Required
Date Returned to Contractor

Signed by Print Name Signature Date


DEMOLITION METHOD STATEMENT | Springvale Ave

Contents
Risk Assessment Index ........................................................................................................................... 3
COSHH Assessment Index ...................................................................................................................... 4
Demolition Details ................................................................................................................................. 4
1. Introduction ................................................................................................................................... 5
2. Scope of Works .............................................................................................................................. 6
3. Enabling Works .............................................................................................................................. 6
4. Method of Works ........................................................................................................................... 7
5. Control Measures (Permits, Exclusion Zones, PPE etc) ............................................................... 10
6. Resources ..................................................................................................................................... 11
7. Training & Supervision ................................................................................................................. 11
8. General Considerations................................................................................................................ 12
9. Environmental Procedures .......................................................................................................... 12
10. Control of Substances Hazardous to Health (COSHH) .............................................................. 12
11. Quality Control .......................................................................................................................... 13
12. Health & Safety Risk Assessment .............................................................................................. 14
13. Appendix A – Risk Assessments ................................................................................................ 16
14. Appendix B – COSHH Assessments: .......................................................................................... 23

Page 2 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

Risk Assessment Index


Number Title Required for this MS
001 Lifting Operations
002 Drilling concrete and masonry
003 Breaking using electric tools Y
004 Breaking using compressed air tools
005 Working at height Y
006 Cutting steel
007 Loading wagons Y
008 Wagon movements Y
009 Using cut off grinders Y
010 Demolition with hand tools Y
011 Cutting timber using chain saws
012 Working around holes and leading edges
013 Supervision of work Y
014 Excavating trial holes in footways
015 Breaking concrete/masonry using excavators c/w breaker Y
016 Erection of protection scaffold & monaflex Y
017 Excavator movement around site
018 Using mechanical & electrical hand tools Y
019 Breaking Concrete using Hand Held Breakers Y
020 Young Person
021 Scaffolding Y
022 Work in Confined Space
023 Working in the Sun
024 Dismantling Fuel Lines
025 Fire (Office)
026 Fire (Site)
027 Demolition Using Long Reach Excavator
028 Using Vehicular Plant at Height
029 Excavator Operations and Quick Hitch Operations
030 Noise at Work Y

Page 3 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

COSHH Assessment Index


Number Operation / Process / Substance Required for this MS
001 Diesel Y
002 Oxygen
003 Propane
004 Grease
005 Hydraulic Oil
006 Hydraulic Fluid
007 Welding
008 Petrol Y
009 Concrete
010 Soft Wood Y
011 Hard Wood Y
012 Hilti HIT-HY50
013 ALBI Guard
014 Linemarking Aerosol
015 Ferromaxx 7
016 Sun Lotions
017 Concrete Dust Y
018 Rockwool Y
019 Leptospirosis
020 Fairy Washing-up Liquid

Demolition Details
Demolition Phase Key Factors
Design • Structural knowledge of the structure and site surveys/assessments
• Structural knowledge of any adjacent structure
• Deconstruction Sequence and Methods used
Planning • Site knowledge
• Health and Safety risk assessment
• Development of safe sequences of demolition activities
Execution • Workforce Supervision
• Control of method statements implementation
• Communication of unplanned discoveries
• Safety information and training selection

Page 4 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

1. Introduction
This document describes how (Enter contractor here) will undertake the de-construction of the
buildings currently known as 34 Springvale Avenue.

The existing property is located on of a small side road located on the south side of Springvale
Avenue, next to a small park.

The project itself consists of the demolition of a 2 storey house, with a single storey garage
located to the side and protruding forward of the property.

The site is located within the Walsall District, bordering Birmingham, with residential pedestrian
foot path and residential traffic.

This method statement will cover: the scope of works, principles, practices & arrangement for the
demolition phase.

(Enter contractor here) will be the principle contractor for the demolition phase of the works and will
manage the deconstruction of the building.

This method statement will make reference to and should be read in conjunction with the
following appendices located at the end of this report:

• General Considerations
• Environmental Procedures
• Quality Control
• H & S Risk Assessment
• COSHH

Due to the type of building structure, it is intended to deconstruct the building by hand means
only.

The methodology is based upon a mixture of demolition techniques; including the use of hand
held tools for a floor-by-floor demolition down to Ground floor slab level.

This demolition statement is based upon the most up to date scheme and the minor amendments
made since grant of planning consent as appendix C. The changes proposed do not impact the
demolition methodology.

Page 5 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

2. Scope of Works
• Set up Site Welfare and offices on pavement loading gantry.
• Erect site hoardings with illuminated walkway & site access door for operatives and visitors.
• Set up site monitoring requirements. (SWL)
• Carry out surveys on existing structures
• Erect demolition protection scaffolding to rear elevation to roof level.
• Erect demolition protection scaffold to front elevation.
• Progressive clearing of arising’s

3. Enabling Works

In order to comply with our programme, the following activities will be required to be
provided/actioned

• Statutory Notifications and Consents.


• Section 80 Notification.
• Section 60 Agreements/Consents.
• Scaffold licences.
• Services terminations/disconnections at boundaries to the building and associated
documentation.
• Approval of all relevant Method Statements including Temporary Works Design and
Installation.
• Provision of temporary service supplies (power, water, supplies and drainage).

Prior to the commencement of the structural demolition works the following works will have been
carried out:

• Erection of hoarding/ temporary barriers/ control measures and signage to prevent


unauthorised access, where required.
• Identification and protection / termination of any live services.
• Installation of temporary services.
• Erection of fully Monarflexed scaffold in accordance with design.
• Erection of temporary Welfare facilities that includes toilets, canteen and office.
• Method Statement briefings and tool box talks.

Page 6 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

4. Method of Works

General Site Practises

• All site operatives to be given site induction and Method Statement briefings and to
attended regular toolbox talks (at least weekly).
• CITB, CSCS, CCDO certification or equivalent as a minimum requirement for all personnel
on site.
• Access platforms, scaffolding, cranes, and lifting equipment will be checked regularly in
accordance with current regulations.
• All machinery, compressors, pneumatic tools etc will be fitted with silencers of approved
types.
• All of the works are to be under the direct control of experienced demolition foremen and
managers.
• Warning signs and notices are to be prominently displayed in and around site.
• Debris and materials will be cleared from floors to prevent excessive build up.
• All works at height, as far as reasonable practicable will be carried out utilising either
scaffolding or alloy towers in full compliance with current regulations.
• All scaffolding will be erected by trained, competent scaffolders in accordance with a
separately issued Scaffold Method Statement. All alloy towers will be erected by PASMA
trained operatives and scaff tagged.
• First Aiders, appointed Persons and First Aid kit(s) commensurate with the total number
of site personnel will to be maintained on site. The names of First Aiders will be displayed
in prominent locations.
• Firefighting equipment (carbon dioxide and foam fire extinguishers) under the control of
operatives, trained in the use of the same, will be positioned in and around the works.
• The site will be left in a structurally stable manner at the end of each shift.
• Any future changes to the Method Statement will be agreed with the Project Manager
prior to execution and the Method Statement reviewed, amended and approved
accordingly.

Sequence of Works

The demolition will be carried out top down on a floor by floor basis.

1. Remove roof finishes


2. Remove timber structure to floor level.
3. Remove brick walls to floor level
4. Remove timber floor finishes, joists etc.
5. Remove brick walls to floor level.
6. Follow above to ground level.

Page 7 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

Remove roof structures:

The roof(s) and mounted structures are predominantly timber and tile and therefore require
removing prior to the demolition of the structure to in order to minimise contamination of the
hardcore.
• Only suitably trained operatives will undertake roof works.
• The roof structure will be removed using electric hand-held breakers.
• Operatives will remove the tiles by hand prior to dropping the timber work to the floor
below.
• The operatives will cut from below in a “sit cut / drop cut fashion” by using mobile towers
the materials will be progressively cleared of the buildings or stock pilled in an
appropriate location until a well hole is available.
• All operatives working at height whist removing the roofs will have undertaken sufficient
training in working at height and utilise rope fall arrest equipment.
• Where possible operatives will work from the floor below utilising mobile towers.

Repetitive Floor-by-floor demolition

This section describes the procedure by which the building is reduced top-down one floor at a
time.

This method utilises hand held plant with suitable attachments, and material will be loaded away
by hand.
• The structures will be demolished using reciprocating saws and suitable breakers.
• The debris will be broken down and cut onto the floor below and processed and
separated to increase the efficiency of debris removal.
• If applicable, once any concrete encased steal members have been severed from the
structure any remaining concrete will be removed from the member utilising hand held
breakers.
• The removal of concrete encasing steal members will only be undertaken by same as
above
• The debris will be loaded into tipper wagons that will be parked near the working face.
• Ceiling hangers, pipe work, trunking, conduit and other non-structural metalwork will be
cut by operatives using reciprocating saws.
• The external brickwork will be demolished in sections and folded onto the floor slab by
operatives. The operation will be executed in a controlled manner, ensuring the brick
work being pulled over is not excessive in size and weight.
• The arisings will then be cleared from all floor areas to the working face by operatives
with wheel barrows.

Page 8 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

• The building will be demolished down to the top foundation this is when we will have
safely completed the works.
• Careful consideration will be given to the stability of the building at all times. Any load
bearing walls will be identified prior to demolition commencing to ensure that they are
maintained until redundant.
• Whilst demolition is in progress, adequate provision will be provided to inspect and
survey the existing structure.
• All static noise sources will be sited (as far as reasonable practicable) well away from
Party Walls and neighbouring properties to prevent excessive disturbance.
• Dust emissions will be controlled at the working face and loading away area by a fine
water spray. The quantity of water emitted by the sprays will be regulated and controlled
to prevent any flooding at ground level.
• (Enter contractor here) will take all reasonable steps to avoid the outbreak of fire. It will be
impressed on the workforce that no smoking is allowed on site and the accumulation of
rubbish must be prevented.
• Dedicated traffic marshals will be deployed at the site entrance to control all pedestrian
and traffic movements. They will be dressed in High Visibility clothing (Orange).
• Stringent fire precautions will be implemented and the material arisings regularly cleared
to minimise floor loading.
• Operative walkway routes at the working floor will be kept clear at all times. The works
will be undertaken from the highest floor downwards, strictly one floor at a time per
building.
• PPE requirements for all operatives will be assessed in accordance with specific Risk and
COSHH assessments and enforced accordingly.
• Throughout the works, fine-mist water sprays will be used to control the soft-strip dust
emissions at source, at ground level and the lift shaft/well hole.

Page 9 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

5. Control Measures (Permits, Exclusion Zones, PPE etc)


Permits Required Yes No Assessments (Attach If Yes) Yes No
Hot works X COSHH X
Crane check list X Noise X
Excavation X Manual handling X

Confined space entry X Electrical Isolation X


Riser shafts X
Further Control Measures / Security Requirements.
As stated above, due to the highly dangerous nature of the works being carried out on the
site, no personnel are to enter the building without express permission for the site manager
or the supervisor in charge of that are of works.
As indicated above prior to the works being carried out an electrical isolation certificate will be
required for the building.
Personal Protective Yes No Yes No
Equipment
Safety Helmet X Gloves X
Protective Footwear X Hearing Protection X
High Visibility Clothing X Overalls X
Eye protection X Body Harness X
Face Respirator X Other

Equipment to be Used Yes No Equipment to be Used Yes No

Lifting X Cradle X
Mechanical hoist X Excavation shoring X
MEWP X Ventilation Equipment X
Ladder X CAT X
Hoist X Mechanical tools X
Test Equipment X Excavation shoring X
Task Lighting X Lifting slings/chains X
Scaffolding X Mechanical plant X
Mobile scaffolds X

Page 10 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

6. Resources
Management / Supervision

(Project Manager)

(Site Manager)

• Labour • Plant & Equipment


• Operations director (visiting) • Hand tools including, mattocks, nail bars,
• Project surveyor (visiting) sledge hammers and screw drivers.
• Integrated Designs Engineer (visiting) • Wheelie bins and wheel barrows.
Environmental monitoring officer • Electric and pneumatic hand tools
(visiting) Safety officer (visiting) including breakers fitted with vibration
• Projects manager reduction devices, petrol saws and
• Site Manager grinders.
• Up to 10 demolition operatives, • All electrical equipment must have
banksmen etc current PAT test certification.
• Up to 8 scaffolders
• Security Welfare
• 1 Admin staff

7. Training & Supervision


Training Certificates Required
Yes No Yes No
Mobile Elevating
Scaffold X Platform X
Forklift Mobile Access Towers X
Dumper Banksman
Excavator X Abrasive Wheels X
Others (Please state):
Low Moderate Substantial High
Overall Assessment X
of Risk after the
Implementation of
Control Measures

Page 11 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

8. General Considerations
• A copy of the letter sent to the occupants of nearby noise sensitive properties informing
them of the demolition works, including the hours of work, the measures taken to protect
their amenity and a contact number should they require further information or wish to
make a complaint. A copy of this letter will be sent to the LA Council for information;
• During all stages of the demolition works the best practicable means shall be employed to
minimize noise and vibration produced by demolition operations and regard shall be had
to the recommendations in the British Standards referred to in The Control of Noise
(Codes of Practice for Construction and Open Sites) (England) Order 2002.

9. Environmental Procedures
• No burning of any material at any time shall take place anywhere on site;
• All wastes will be stored in designated areas which are isolated from surface drains;
• Mobile plant will be refuelled in a designated area, away from drains and watercourses;
• Special care will be taken during deliveries, particularly when fuels are being handled; and
• A contingency plan will be put in place to deal with any incidents.

10. Control of Substances Hazardous to Health (COSHH)


• Prior to work commencing, senior site supervision will liaise with the client's resident
engineer. They will provide identification tabs outlining possible types of residue which
are likely to be present within any vessels that are to be breached.
• All U bends and traps which are present in pipe lines will be flushed through with suitable
dispersant. Flange joints will be unbolted prior to flushing and/or similar fines will be
placed at the mouth ready to receive the flushing agent.
• All residual materials will be disposed to a licensed agent unless advised otherwise.
• Hot cutting of ferrous metals where paint has been applied will be samples for lead
content. Any nasal respiration and washing facilities will be issued as standard modes of
operation.
• Haulage vehicles to have their loads cocooned in Visqueen or similar approved sheets,
unless containers have fully enclosed bodies. Subject to requirements.

Page 12 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

11. Quality Control


• All surfaced and un-surfaced site access roads shall be watered as necessary and surfaces
kept in good order.
• All vehicles carrying loose aggregate and workings shall be sheeted at all possible times.
• Dampening of exposed soil and materials stockpiles shall take place, if necessary, using
sprinklers and hoses.
• All stockpiles of soils and materials shall be located as far as possible from sensitive
properties, taking account of prevailing wind.
• Windbreak netting shall be positioned around materials stockpiles and vehicle
loading/unloading areas, as well as exposed excavation and material handling operations.
• Completed earthworks shall be covered as soon as is practicable.
• Regular inspection of and, if necessary, cleaning of local highways and site boundaries
shall take place to check for dust deposits (and removal if necessary).
• Visual inspection of site perimeter shall be undertaken to check for dust deposition
(evident as soiling and marking) on vegetation, cars and other objects and taking remedial
measures.
• if necessary; Surface areas of stockpiles shall be minimized (subject to health and safety
and visual constraints regarding slope gradients and visual intrusion) to reduce area of
surfaces exposed to wind pickup.
• The use of dust-suppressed tools for all operations shall be considered;
• The location of vehicle compounds away from the site boundary, where possible.
• Only sound-reduced compressors shall be used, with properly lined and sealed acoustic
covers, fitted in accordance with manufacturer's instructions and kept closed whenever
the machines are in use, and all ancillary pneumatic percussive tools shall be fitted with
mufflers or silencers of the type recommended by the manufacturer.
• All construction/demolition plant and equipment shall be maintained in good working
order and sited away from sensitive properties;

Page 13 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

12. Health & Safety Risk Assessment


Falls from Height • All manual worked faces above 2 metres in height will have scaffold
cladding and/or edge protection/hydraulic platform.
• Any exposed internal dropping zones will receive edge protection.
• In the event of exposed roof top traverse, crawling board, safety
lines and static anchorage will be utilised.

Protection Against • All structures will be progressively worked from one common face.
Collapse of Care will be taken so as not to de-stabilise the main supports.
Structures • At the end of each shift, inspections by the supervisor in charge will
determine as to what temporary measure, if any, will have to be
implemented until the commencement of the next shift.
• Any suspended structure will not be used as temporary storage
decks. All materials will be placed directly onto the adjacent ground
levels (unless adequate temporary support is introduced).

PPE • All personnel must wear safety helmets at all times within the
building and on site.
• Those involved in the use of flame cutting equipment or straight
sided cutting of wheels must wear eye protection.
• Those involved in the use of, or working in close proximity to,
equipment such as pneumatic hammers and cutting of wheels must
wear hearing protection.
• Breaking out operations will produce high levels of nuisance dust
and all personnel involved in breaking out and removal of rubble are
to wear dust masks.
• Waterproof overalls to be worn in areas of high concentrates of
acidic water, pressure cleaning and general cleaning of haulage
vehicles.
Unauthorised • Entire site perimeter to be fully enclosed with suitable security
Access by fencing/scaffold gantry as considered necessary by the site
Members of The supervisor.
Public
• Warning notices displayed at vantage points.
• Employ suitable third parties or in-house security to patrol site
during hours of darkness (subject to client's requirements)

Page 14 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

Injury Caused by • Designated access routes through site for haulage vehicles to be
Working Plant adhered to.
• Heavy plant to have Banksmen in constant attendance.
• Reverse horns and lights to be implemented in confined pedestrian
areas.
• Pedestrian and traffic management during heavy plant accessing
and egressing the site.
Injury Caused by • Identify underground service lines and mark clearly.
Live Services Etc. • Check with Utility Engineer in respect of disconnections.
• In the event of works close to live service lines, all work modes to be
undertaken by hand techniques.
• Exercise common sense and good housekeeping at all times.
• External perimeter to be policed during sensitive manoeuvres.
• Areas beneath demolition to be cordoned off.
• Constant evaluation of site safety.

General • Implement an effective practicable fire drill for use in the event of
an emergency.

Page 15 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

13. Appendix A – Risk Assessments

Page 16 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

Hazard/Risk Assessment
RA Number: 1 Sheet: 1 of 1
Operation/Task: Breaking using electrical hand tools MS Name: Demolition
MS No: AS-101-TW-01 RA Written by: A Sehdeva
Location/Area: Springvale Avenue Name of person completing Assessment: ……..
Risk Rating Risk Rating Monitoring
Responsibility
Item Activity Hazards/Risks Identified S L RR Control S L RR Responsibility
1 Drilling concrete using electric Electric shock 4 4 12 *Inspect cables & tools to ensure in good 4 1 4 Site Manager
Drilling operatives
tools condition before use. PAT equipment
Eye damage from flying 3 4 12 *Establish exclusion zone limiting access using 3 1 3 Drilling operatives Site Manager
debris/dust barriers and signage
*All personnel working within exclusion zone to wear & Supervisor
eye protection, BS EN 166B grade 1 impact
Damage to hearing 3 4 12 *Establish exclusion zone limiting access using 3 1 3 Drilling operatives Site Manager
barriers and signage
*All personnel working within exclusion zone to & Supervisor
wear hearing protection. (generic noise level
102DbA) to BS EN 352.
Inhalation of concrete dust (silica) 3 4 12 *Damp down dust 3 1 3 Drilling operatives Site Manager
*Clear dust/slurry regularly
*All within exclusion zone to wear particle filter & Supervisor
mask to BS EN 143
Cuts and abrasions to hands 3 3 9 *Wear protective gloves to BS EN 374 3 1 3 Drilling operatives Site Manager

& Supervisor
Vibration white finger 4 4 16 *Use modern, well-maintained equipment (anti- 4 1 4 Drilling operatives Site Manager
vibration mountings etc)
*Select operatives (non-smokers) & Supervisor
*Rotate labour
*Provide anti-vibration gloves(where applicable)

KEY
Severity Likelihood Risk Rating Catastrophic Extremely Harmful Harmful Slightly Harmful
4 Very severe 4 Very high 13-16 Intolerable Very likely 16 12 8 4
3 Severe 3 High 8-12 Substantial Likely 12 9 6 3
2 Minor 2 Moderate 5-7 Moderate Unlikely 8 6 4 2
1 Negligible 1 Low 1-4 Tolerable Highly unlikely 1 3 2 1

Approved by: P Sehdeva Signature: Date: 10/04/18

Page 17 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

Hazard/Risk Assessment
RA Number: 2 Sheet: 1 of 1
Operation/Task: Working at height MS Name: Demolition
MS No: AS-101-TW-01 RA Written by: A Sehdeva
Location/Area: Springvale Avenue Name of person completing Assessment: ……..
Risk Rating Risk Rating Monitoring
Responsibility
Item Activity Hazards/Risks Identified S L RR Control S L RR Responsibility
1 Working at height Personnel falling 4 4 16 *Work off appropriate working platform, handrails, 4 1 4 Operatives & Site Manager
toe-boards, debris netting as required Supervisor
*Scaffold erecting by CITB scaffolders + scaff tag
*Alloy towers erected by trained operatives
*Suitably trained operatives using MEWP's
*Work involving leaning out or if working outside
appropriate working platform (i.e. Open leading edge),
full body safety harness must be worn at
all times connected to appropriate anchor point
Falling materials/equipment 4 4 16 *Toe-boards, brick guards, debris netting/ 4 1 4 Operatives & Site Manager
monaflex fitted the scaffold Supervisor
*Platforms sheeted to prevent materials falling
through gaps
* Exclusion zones set up to prevents persons accessing
area below work using solid barriers and signs

*Keep working platforms clear of any obstructions

KEY
Severity Likelihood Risk Rating Catastrophic Extremely Harmful Harmful Slightly Harmful
4 Very severe 4 Very high 13-16 Intolerable Very likely 16 12 8 4
3 Severe 3 High 8-12 Substantial Likely 12 9 6 3
2 Minor 2 Moderate 5-7 Moderate Unlikely 8 6 4 2
1 Negligible 1 Low 1-4 Tolerable Highly unlikely 1 3 2 1

Approved by: P Sehdeva Signature: Date: 10/04/18

Page 18 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

Hazard/Risk Assessment
RA Number: 3 Sheet: 1 of 1
Operation/Task: Loading wagons using an excavator MS Name: Demolition
MS No: AS-101-TW-01 RA Written by: A Sehdeva
Location/Area: Springvale Avenue Name of person completing Assessment: ……..
Risk Rating Risk Rating Monitoring
Responsibility
Item Activity Hazards/Risks Identified S L RR Control S L RR Responsibility
1 Loading wagons Persons being trapped hit by 4 4 16 *Exclude all pedestrian movement from loading area. 4 1 4 Operatives & Site Manager
wagon or excavator Pedestrian areas barrier off and signed Supervisor
*Only trained/competent operators to be used (CITB)
*All vehicle movements controlled by dedicated trained
banksman
Injury to wagon driver 4 4 16 *Wagon driver must not remain in cab if bucket travels 4 1 4 Operatives & Site Manager
over cab. Supervisor
*Wagon driver must not stand on top of lorry during
loading
*Wagon driver must wear correct PPE when out of cab
Injury/damage through failure of 4 4 16 *Ensure that machinery is in good repair and well 4 1 4 Operatives & Site Manager
equipment maintained with weekly checks up to date Supervisor
Dust created during loading 2 4 12 *Ensure stockpile is damped down using water spray 2 1 2 Operatives & Site Manager
Supervisor

KEY
Severity Likelihood Risk Rating Catastrophic Extremely Harmful Harmful Slightly Harmful
4 Very severe 4 Very high 13-16 Intolerable Very likely 16 12 8 4
3 Severe 3 High 8-12 Substantial Likely 12 9 6 3
2 Minor 2 Moderate 5-7 Moderate Unlikely 8 6 4 2
1 Negligible 1 Low 1-4 Tolerable Highly unlikely 1 3 2 1

Approved by: P Sehdeva Signature: Date: 10/04/18

Page 19 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

Hazard/Risk Assessment
RA Number: 4 Sheet: 1 of 1
Operation/Task: Wagon movements MS Name: Demolition
MS No: AS-101-TW-01 RA Written by: A Sehdeva
Location/Area: Springvale Avenue Name of person completing Assessment: ……..
Risk Rating Risk Rating Monitoring
Responsibility
Item Activity Hazards/Risks Identified S L RR Control S L RR Responsibility
1 Wagon movements onto, off and Persons being trapped or hit by 4 4 16 *Wherever possible provide pedestrian free traffic 4 1 4 Operatives & Site Manager
around site wagons route Supervisor
Traffic Marshall
*Wagon drivers to be briefed on site rules slinger
*All vehicle movements controlled by dedicated
trained signaller
*All vehicles observe 5mph speed limit on site
Mud carried onto public highway 4 4 16 *Wagon wheels must be cleaned when leaving 4 1 4 Operatives & Site Manager
site Supervisor
*All vehicle movements controlled by dedicated
trained banksman
*Provision should be made for mechanical road
sweeping, especially during wet weather.
Drivers must deploy easy covers prior to leaving
site
Injury to members of public 4 4 16 *All vehicle movements controlled by dedicated 4 1 4 Operatives & Site Manager
trained banksman Supervisor

KEY
Severity Likelihood Risk Rating Catastrophic Extremely Harmful Harmful Slightly Harmful
4 Very severe 4 Very high 13-16 Intolerable Very likely 16 12 8 4
3 Severe 3 High 8-12 Substantial Likely 12 9 6 3
2 Minor 2 Moderate 5-7 Moderate Unlikely 8 6 4 2
1 Negligible 1 Low 1-4 Tolerable Highly unlikely 1 3 2 1

Approved by: P Sehdeva Signature: Date: 10/04/18

Page 20 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

Hazard/Risk Assessment
RA Number: 5 Sheet: 1 of 1
Operation/Task: Using cut off grinder MS Name: Demolition
MS No: AS-101-TW-01 RA Written by: A Sehdeva
Location/Area: Springvale Avenue Name of person completing Assessment: ……..
Risk Rating Risk Rating Monitoring
Responsibility
Item Activity Hazards/Risks Identified S L RR Control S L RR Responsibility
1 Using cut off grinder Injury from flying debris/blade 4 4 16 *Ensure only trained, experienced operatives are 4 1 4 Operatives & Site Manager
shattering used. Supervisor
*Abrasive wheels register in place
*Whenever possible, establish exclusion zone,
limiting personnel acess in the area
Eye injury 3 4 12 *Eye protection to be worn at all times to BS EN 3 1 3 Operatives & Site Manager
166B impact grade 1 Supervisor
Damage to hearing 3 4 12 *Hearing protection to be worn to BS EN 352 at all 3 1 3 Operatives & Site Manager
times while operating the tool Supervisor
Inhalation of dust 3 4 12 *Good ventilation or forced ventilation. 3 1 3 Operatives & Site Manager
*All personnel working within exclusion zone to wear Supervisor
particle filter mask to BS EN 143
Cuts and abrasions 3 4 12 *Wear protective gloves to BS EN 374 3 1 3 Operatives & Site Manager

*Keep area clear of all obstructions ie ropes, wires Supervisor


Fire/Explosion - particularly during 4 4 16 *Hot work permit requested and issued 4 1 4 Operatives & Site Manager
fuelling *Fire watchman in place with fire extinguisher Supervisor
*Minimise combustible materials
*Store petrol in correct type of containers
*Establish safe refuelling system with fire
extinguisher to hand
Vibration 4 4 16 *Ensure well maintained tools/equipment 4 1 4 Operatives & Site Manager
*Know HAVs threshold values Supervisor
*Rotation log - HAV Register in place
* Non-smoking operatives
KEY
Severity Likelihood Risk Rating Catastrophic Extremely Harmful Harmful Slightly Harmful
4 Very severe 4 Very high 13-16 Intolerable Very likely 16 12 8 4
3 Severe 3 High 8-12 Substantial Likely 12 9 6 3
2 Minor 2 Moderate 5-7 Moderate Unlikely 8 6 4 2
1 Negligible 1 Low 1-4 Tolerable Highly unlikely 1 3 2 1

Approved by: P Sehdeva Signature: Date: 10/04/18

Page 21 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

Hazard/Risk Assessment
RA Number: 6 Sheet: 1 of 1
Operation/Task: Demolition with hand tools MS Name: Demolition
MS No: AS-101-TW-01 RA Written by: A Sehdeva
Location/Area: Springvale Avenue Name of person completing Assessment: ……..
Risk Rating Risk Rating
Responsibility Monitoring Responsibility
Item Activity Hazards/Risks Identified S L RR Control S L RR
1 Demolition with hand tools Injury from poorly maintained, 3 4 12 *Ensure only trained, experienced operatives are 3 1 3 Operatives & Site Manager
wrongly used tools carrying out the works Supervisor
*Operatives given briefing on work to be carried
out MS and RA.
*Daily inspection of all tools to be carried out.
Eye injury from flying debris 3 4 12 *Eye protection to be worn to BS EN 166B impact 3 1 3 Operatives & Site Manager
grade 1. Supervisor
Inhalation of dust 3 4 12 *Damp down to suppress dust 3 1 3 Operatives & Site Manager
*Good ventilation - if not then forced ventilation Supervisor
*All personnel working within work area to wear
particle filter mask to BS EN 143
Cuts and abrasions 3 4 12 *Wear protective gloves to BS EN 374 3 1 3 Operatives & Site Manager
Supervisor
*Ensure that access/egress are kept clear at all times Operatives &
Slips and trips 3 3 12 3 1 3 Site Manager
*Ensure that materials are stored correctly and Supervisor
removed as soon as practicable
*Ensure a good level of lighting
* Cover slippery walkways with non-slippery

KEY
Severity Likelihood Risk Rating Catastrophic Extremely Harmful Harmful Slightly Harmful
4 Very severe 4 Very high 13-16 Intolerable Very likely 16 12 8 4
3 Severe 3 High 8-12 Substantial Likely 12 9 6 3
2 Minor 2 Moderate 5-7 Moderate Unlikely 8 6 4 2
1 Negligible 1 Low 1-4 Tolerable Highly unlikely 1 3 2 1

Approved by: P Sehdeva Signature: Date: 10/04/18

Page 22 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

14. Appendix B – COSHH Assessments:

Page 23 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

COSHH Risk Assessment Record Ref: CAR_001

Project / Premises Springvale Ave Project Number AS-101-TW-01

Manufacturer / Supplier Generic Substance / Material Diesel


Hazardous Contents Hydrocarbon mixture

Process: Pumping/Pouring

Activity: Fuel

Location:
Harmful
Exposure Frequency Once a day Exposure Duration Once a day

Risk to Health
Harmful by inhalation. Harmful if swallowed. Irritating to eyes. Skin irritation and dermatitis may result from
prolonged contact.

Control Measures
Wear Nitrile Gloves. Keep skin covered (over-alls). Wear eye goggles if splash is likely. Work in well ventilated
area. No smoking, eating or drinking. Wash after contact. Change clothes if heavily soiled.
Storage: Store away from heat and source of ignition. Disposal: Dispose of as Hazardous waste
Containers should not be left unsealed. Wear hand
protection
Spillage: Ventilate area. Shut off at source. Eliminate all Fire Information: Toxic fumes are produced if
sources of ignition. Absorb in sand/spill kit. Collect in product burns. Wear self-contained breathing
container and keep sealed. apparatus. Powder-Foam-Carbon Dioxide. Do Not
Use Water.

First Aid
Eye Contact: Irrigate with plenty of water for at least 15 Inhalation: Remove to fresh air and rest.
minutes. If irritation persists seek medical advice.
After significant exposure call for medical assistance.
Skin Contact: Wash with soap/cleanser and rinse with plenty Ingestion: Do not induce vomiting. Drink plenty of
of water. water. Get prompt medical attention.

Other Controls Monitoring Health Surveillance


Record Attached Not Applicable Record Attached Not Applicable
No No No No

Training / Instruction
Required
Verbal Instruction X Written Instruction
Tool Box Talk Specialist Training

Assessed By: Ashish Sehdeva Designation: Building Surveyor Date: 10/04/18

Page 24 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

COSHH Risk Assessment Record Ref: CAR_002

Project / Premises Springvale Ave Project Number AS-101-TW-01

Manufacturer / Supplier Generic Substance / Material Wood (Soft)


Hazardous Contents Wood Dust

Process: Handling, Cutting


and Machining
Activity: Using as a construction
material
Location:

Up to 8 hours per 8
Exposure Frequency Daily Exposure Duration
hour period

Risk to Health
Do not breathe dust

Control Measures
Disposable face mask (EN 149 FFP2S). Eye goggles. Cover skin. Damp down then sweep up.
Storage: Not Applicable Disposal: Dispose of waste for recycling
Spillage: Do not dry sweep. Damp down and vacuum to Fire Information: Clear waste regularly. Powder-
clear. Foam-Water-Carbon Dioxide can be used in the fire.

First Aid
Eye Contact: Irrigate with plenty of water for at least 15 Inhalation: Remove to fresh air and rest
minutes. If irritation persists seek medical advice.
Skin Contact: Not Applicable Ingestion: Not Applicable

Other Controls Monitoring Health Surveillance


Record Attached Not Applicable Record Attached Not Applicable
No No No No

Training / Instruction Required


Verbal Instruction x Written Instruction
Tool Box Talk Specialist Training

Assessed By: Ashish Sehdeva Designation: Building Surveyor Date: 10/04/18

Page 25 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

COSHH Risk Assessment Record Ref: CAR_003

Project / Premises Springvale Ave Project Number AS-101-TW-01

Manufacturer / Supplier Generic Substance / Material Wood (Hard)


Hazardous Contents Wood Dust

Process: Handling, Cutting


and Machining
Activity: Using as a construction
material
Location:

Up to 8 hours per 8
Exposure Frequency Daily Exposure Duration
hour period

Risk to Health
May cause cancer. May cause sensitisation by inhalation

Control Measures
When using do not eat or drink. Avoid contact with eyes and skin. Eye goggles. Cover skin. Do not breathe dust, use
disposable face mask (EN 149:FFP2S). Damp down and then sweep up.
Storage: Not Applicable Disposal: Dispose of waste for recycling
Spillage: Do not dry sweep. Damp down and vacuum to Fire Information: Clear waste regularly. Water- Carbon
clear. Dioxide can be used in the fire.

First Aid
Eye Contact: Irrigate with plenty of water for at least 15 Inhalation: Remove to fresh air and rest
minutes. If irritation persists seek medical advice.
Skin Contact: Wash with soap/cleanser and rinse with plenty Ingestion: Do not induce v o m i t i n g . If irritation
of water. persists seek medical advice.

Other Controls Monitoring Health Surveillance


Record Attached Not Applicable Record Attached Not Applicable
No No No No

Training / Instruction Required


Verbal Instruction x Written Instruction
Tool Box Talk Specialist Training

Assessed By: Ashish Sehdeva Designation: Building Surveyor Date: 10/04/18

Page 26 of 27
DEMOLITION METHOD STATEMENT | Springvale Ave

COSHH Risk Assessment Record Ref: CAR_004

Project / Premises Springvale Ave Project Number AS-101-TW-01

Manufacturer / Supplier Generic Substance / Material Concrete dust


Hazardous Contents Cement, Aggregate

Process: Breaking

Activity: Breaking with hand held tools

Location:
Irritant
Exposure Frequency Daily Exposure Duration Up to 4 hours

Risk To Health
Can cause allergic dermatitis through contact with chromates. Can cause burns/skin ulceration. Contact can cause irritant
contact dermatitis. Irritating to eyes and respiratory system. Inhalation of respirable quartz causes long term hazard.

Control Measures
Disposable face mask. Eye goggles. Rubber gloves and boots. Cover skin when using do not smoke, eat or drink. Wash
after contact. Damp down then sweep up.
Storage: Not applicable Disposal: Dispose of in accordance with Local Authority
Regulations
Spillage: Wear rubber gloves, boots protective over- alls. Do Fire Information: Non-combustible material
not dry sweep. Damp down and sweep or vacuum to clear

First Aid
Eye Contact: Irrigate with plenty of water for at least 15 Inhalation: Remove to fresh air and rest
minutes. If irritation persists seek medical advice.
Skin Contact: Wash with soap/cleanser and rinse with plenty Ingestion: Drink plenty of water
of water

Other Controls Monitoring Health Surveillance


Record Attached Not Applicable Record Attached Not Applicable
No No No No

Training / Instruction Required


Verbal Instruction x Written Instruction
Tool Box Talk Specialist Training

Assessed By: Ashish Sehdeva Designation: Building Surveyor Date: 10/04/18

Page 27 of 27

You might also like