You are on page 1of 15

Success Story Collection

LNG Supply Chain

YOKOGAWA ELECTRIC CORPORATION


World Headquarters Represented by:
9-32, Nakacho 2-chome, Musashino-shi, Tokyo 180-8750, Japan
http://www.yokogawa.com/

YOKOGAWA CORPORATION OF AMERICA


12530 West Airport Blvd, Sugar Land, Texas 77478, USA
http://www.yokogawa.com/us/

YOKOGAWA EUROPE B.V.


Euroweg 2, 3825 HD Amersfoort, The Netherlands
http://www.yokogawa.com/eu/

YOKOGAWA ENGINEERING ASIA PTE. LTD.


5 Bedok South Road, Singapore 469270, Singapore
http://www.yokogawa.com/sg/

YOKOGAWA CHINA CO., LTD.


3F TowerD Cartelo Crocodile Building
No.568 West Tianshan Road, Shanghai 200335, China
http://www.yokogawa.com/cn/

YOKOGAWA MIDDLE EAST & AFRICA B.S.C. (c)


P.O. Box 10070, Manama
Building 577, Road 2516, Busaiteen 225, Muharraq, Bahrain
http://www.yokogawa.com/bh/

Trademarks
All brand or product names of Yokogawa Electric Corporation in this bulletin are trademarks or registered trademarks of Yokogawa Electric Corporation.
All other company brand or product names in this bulletin are trademarks or registered trademarks of their respective holders.

Subject to change without notice


All Rights Reserved. Copyright © 2016, Yokogawa Electric Corporation

[Ed:02/d] Printed in Japan, 910(KP)

Bulletin 00A01A54-01EN
■Contents

01│ South Hook LNG Terminal Ltd.

03│ MISC Berhad

05│ Korea Gas Corporation

07│ Oman Liquefied Natural Gas LLC


Success Story Collection 09│ Terminale GNL Adriatico Srl
LNG Supply Chain
11│ PT Badak

13│ Saibu Gas Co., Ltd.


This is a showcase of success stories from our customers worldwide.
17│ Shanghai LNG Company Limited
Many leading companies are using
19│ Skangass AS
Yokogawa products to manage their plants and processes.
21│ PTT LNG Company Limited

23│ Hazira LNG Private Limited


South Hook LNG Terminal Ltd. / UK
LNG Supply Chain
Plant Safety Operation State-of-the-art Training Facilitation
Owners of LNG terminals are subject to compliance with many In managing and operating LNG terminals effectively, terminal
laws, regulations, standards and guidelines which need to owners are frequently faced with the need to train and
be met to ensure that the health and safety and commercial refresher train staff in order to maintain competitiveness and
viability of all of its stakeholders are not compromised. maximise efficiency, process and safety knowledge. It can be
These comprehensive requirements influence the design, difficult for LNG owners to find experienced operators, and
construction, operation, and maintenance of an LNG facility. therefore need to train their own. An experienced operator may
Plant Information Yokogawa’s skills, expertise and experience is not just limited only require training on the specific system and not always on
to its product but recognises the importance of understanding the plants process. However, inexperienced operators may also
Location: South Hook, Milford Haven, UK the LNG process. In order to be able to implement a successful need to be trained in process behaviours and specific operator
Order date: March 2005 fully automated solution, Yokogawa utilises its experience and scenarios. In the South Hook LNG terminal’s case, Yokogawa’s
Completion: April 2010 specific knowledge of LNG terminal control system automation. OmegaLand plant operator training simulator (OTS) helps to
Yokogawa safety consultants are involved at the earliest stages reduce costs, optimize LNG terminal processes, and improve
of development and can participate, for example, in HAZOP reliability by training operator staff in trouble-free start-up and
studies and SIL studies. Yokogawa supported, designed and load operation, prior to real plant operation. By establishing a

South Hook LNG Terminal Ltd. supplied a full automation control system for this terminal,
which incorporated the DCS (distributed control system),
network connection between OmegaLand and an actual DCS
(the CENTUM CS 3000), it is possible for operators to receive
emergency shutdown (ESD) system, fire and gas (F&G) system, realistic training in a virtual environment.
fire and gas devices, asset management system, data historian Training is available for procedures such as plant startup and
Yokogawa Provides CENTUM CS 3000 and ProSafe-RS system and operator training simulator. The basis of this LNG load change, abnormal conditions such as an instrument or
terminal solution is Yokogawa’s CENTUM CS 3000 R3 DCS equipment failure, and exceptional emergency situations
for the Largest LNG Terminal in Europe system and ProSafe-RS safety instrumented system, which are
considered the most reliable process automation system on the
such as earthquakes, fires and runaway reactions. Because
the simulator uses exactly the same algorithms as the actual
market. control system, individuals can be fully trained to respond to
As LNG EPC projects have increased in size and complexity, emergencies, however rare, that could lead to a plant shutdown.

Executive Summary owners have increasingly employed Yokogawa during front


end engineering design (FEED) activities, utilising Yokogawa’s
The dynamic model not only facilitates the training of operators,
but also allows the designers to check the dynamic aspects of
The demand for natural gas is growing rapidly and at the same The South Hook re-gasification Terminal is the stage in the LNG extensive experience in LNG supply chain automation. the design. Having such a dynamic simulation environment
time indigenous gas production in European Union is going process which changes it back from the liquid to gaseous state. attached to the actual control and safety systems, additionally
down. Experts predict that the resulting import requirements in This is then delivered to the UK’s homes and businesses via the supports the validation of process operating procedures.
the European Union in 2030 will be between 1.5 and 2 times the UK’s national grid network.
import amount of 2007. One of the options to close the resulting
supply gap is through LNG imports. As a consequence, liquefied The LNG is delivered to South Hook by a state of the art fleet of
natural gas (LNG) facilities are under pressure to deliver not just double-hulled ships which brings the LNG from Qatar’s immense
now, but well into the future. Consequently, a requirement for North Field, to the safe, deep water in Milford Haven.
LNG terminals is that they have exceptionally reliable field proven The South Hook Terminal also plays a major role in the
process automation solutions that will be supported for at least 15 strengthening of the strategic partnership between the state of
years, and which in practical terms can be expected to be longer. Qatar and UK. LNG imports greatly increase the UK’s security and
diversity of gas supply while helping to ensure that natural gas
The South Hook Terminal provides the UK with a significant remains a competitive source of energy.
proportion of its natural gas requirements. It is an integral part of
the Qatargas 2 integrated value chain and is the largest Liquefied
Natural Gas re-gasification terminal in Europe.
The Challenges and the Solutions
Central control room
Yokogawa Europe successfully completed the implementation of
the full ICSS automation control system project which includes Operator training simulator
flagship products of distributed control system (DCS) CENTUM Data Management by Exaquantum
CS 3000, Yokogawa’s safety instrumented system ProSafe-RS CENTUM CS 3000 and ProSafe-RS were totally integrated
and Exaquantum - Yokogawa’s Plant Information Management
System (PIMS). For design and training purposes the Yokogawa
with 17 sub-vendor systems and all process operation data
needing to be visualised for efficient terminal operation.
Customer Satisfaction
scope also included an Operator Training System (OTS) based on The plant management team operates daily KPI reporting According to Maurice Khoury the SHLNG Facilities, Control &
the Visual Modeler dynamic simulation software. that the terminal utilises to monitor and continually improve Instrumentation Lead Engineer, “ We are very happy using
its efficiency. Yokogawa’s Exaquantum plant information Yokogawa’s DCS and SIS, as well as their software packages.
The South Hook Terminal facility comprises a ship unloading management system (PIMS) is the tool that South Hook utilise The South Hook LNG Terminal can provide up to 20% of UK gas
system, five dual containment 155,000 m3 LNG storage tanks, and to manage this important part of their operation. To ensure demand, so the plant runs 24 hours a day, 7 days a week, 365
duplicated re-gasification and gas send-out systems. operators can see their process information clearly, various days a year. Yokogawa’s highly reliable systems and products are
process information in real time data are always displayed on contributing to this continuous operation.” He added, “Yokogawa
their large operator screen. This enables the process situation to are a significant partner here and we will continue to work as one
be known in advance and ensures that the operator can always seamless team throughout the plant’s asset lifecycle.”
take any necessary proactive action. Finally, gas nomination and
allocation is smoothly executed by having Exaquantum provide
the required data to the Terminal Access System that handles .
The South Hook LNG terminal and jetty

1 Success Story Collection Success Story Collection 2


MISC Berhad / Malaysia
LNG Supply Chain

Plant Information
Location: Malaysia

Tenaga Class: 5 Ships


Capacity: 130,000 cbm per ship
Start: 2002

MISC Berhad Finish: 2006

Integrated Automation System (IAS) for MISC LNG


Carrier Tenaga and Seri ‘A’ Class Seri ‘A’ Class: 5 ships
Capacity: 145,000 cbm per ship
Start: 2005
Finish: 2007

Project Profile The Challenges and the Solutions Benefits Realized Customer Satisfaction
Yokogawa has been selected to supply the CS3000 for Integrated There was a requirement for an intensive site survey onboard With the completion of the retrofitting of the new CS 3000 IAS in One of the MISC engineer commented, “We want an idiot proof,
Automation System (IAS) and Boiler Integration as well selected of the Tenaga ships to ensure that the engineering and design Tenaga and new installation on  Seri ‘A’ Class LNG Carriers, MISC user friendly and reliable IAS system to ensure safe operations for
field instruments for MISC Tenaga and Seri ‘A’ Class of LNG works could be carried out successfully. A dedicated survey team could be ensured of better information visibility, performance our LNG carriers. Yokogawa CS 3000 system has proven in both
Carriers. comprises of Yokogawa global team with the assistance from the foresight, and operational agility to deliver overall operations the Tenaga and the Seri Class LNG carriers that their hardware
end-user did the onboard survey to map out all the necessary excellence, reliability, safety and on-time cargo deliveries to the is very reliable with very less problem. This means that we have
One of the tasks in the Tenaga Class project is to replace the engineering details. confidence of their charterers. fewer spare parts to purchase and hence a reduced maintenance
existing panel instrumentation and obsolete PLCs with the cost and a faster turn-around for the vessels.”
advanced CS 3000 IAS which partly will extend the service life of Part of the scope of work is to convert the existing panel MISC operation team could also benefit from the global Yokogawa
the ships built in the early 1980’s. Whereas in the Seri ‘A’ Class, the instrumentation made in the early 1980’s to accommodate the support around the world in all the destinations during the He further added, “Yokogawa CS 3000 software and operating
CS 3000 IAS will provide a reliable automation system onboard of latest in the DCS technology. These include the previous boiler Tenaga and Seri ‘A’ Class voyage. system proven to be most user friendly as almost any ship
all the newly build ships each with capacity of 145,000 cbm. The control which was based on obsolete PLC to be integrated into engineer can familiarise with the system in a very short time. The
certification bodies for the Tenaga and Seri ‘A’ class are from ABS the new DCS. With the Yokogawa capability in handling major To ensure the adherence to the highest safety standards, for all system is also very easy for our trouble shooting works.”
and BV respectively. project using the Main Automation Contractor (MAC) approach as periodic vessels’ inspection and audit conducted at the Malaysian
well as with existing close cooperation from Marine Boiler Maker
and Marine Consultant, the project was able to be successfully
dry docks, MISC will be guaranteed of Yokogawa support and
expertise from the Malaysian office. Because of similar operating
Customer Profile
completed even with a really tight yard schedule, all within a system the Tenaga and Seri ‘A’ Class ships’ crew could be MISC Berhad (MISC), a subsidiary of the PETRONAS Group
period of 2 months per ship on the average. interchangeable and hence optimise the cross-fleet integration of Companies, is a renowned leading international shipping
and operations. and logistics company with a formidable presence in energy
In the Seri ‘A’ Class ships, the challenge was in different nature transportation and marine engineering. With a fleet of 27 LNG
as these are newly build. With the knowledge gained and the MISC will also benefit from the training and process simulation at tankers, which is expected to expand to 29 by April 2009, MISC is
same dedicated team all the engineering, installation, testing and Yokogawa DCS Training Simulator Centre located at their world the world's single largest owner operator of LNG Carriers.
commissioning as well as during sea trial, the Seri ‘A’ projects have class Malaysian Maritime Academy to train sea personnel.
been successfully delivered to the satisfaction of customers. This
including the DCS integration of with Terasaki Power Management
System as well as integration of ship’s boiler system.

System Details
System: CENTUM CS 3000

3 Success Story Collection Success Story Collection 4


Korea Gas Corporation / South Korea
LNG Supply Chain

Plant Information
Location: Incheon, South Korea
First Installation: 1998
Current Migration: 2011 (plant 1)

Korea Gas Corporation


World’s Largest LNG Terminal Relies on CENTUM to
Maximize Safety and Reliability KOGAS Incheon LNG terminal

Executive Summary The Challenges and the Solutions Customer Satisfaction


Established by the Korean government in 1983, Korea Gas Safe operation Proactive maintenance for asset excellence People at the KOGAS Incheon LNG terminal, says, “With CENTUM
Corporation (KOGAS) is the world’s largest importer of LNG, and At LNG receiving terminals, safety is a paramount concern Systems from other vendors that control the plant’s offloading, and other systems, we have built an enterprise-wide operating
the country’s sole importer of this important resource. KOGAS is with the transfer and storage of LNG from carriers. It is very tank gauging, pipe line monitoring, metering, and other information system. The visualization of all process data allows
fully committed to providing clean, safe, and convenient energy important to maintain a constant pressure inside the storage processes are all integrated via a Modbus interface with each us to maintain a clear picture of the execution of our business
to the people of Korea. The company currently operates LNG tanks, which requires careful control of the operation of boil-off plant’s CENTUM production control system. The data from plans, create optimal LNG supply chain scenarios, and make quick
receiving terminals in Incheon, Pyeongtaek, and Tongyeong, gas (BOG) compressors, recondensors, and pumps. By means these processes is used to make production reports, calculate decisions and timely adjustments. With the CENTUM system,
and distributes natural gas and gas by-products via a 2,739 km of sequence functions, CENTUM operators can easily control plant efficiency, and analyze performance. For example, operability and safety are enhanced, and operators as well as
pipeline network to power plants, gas utility companies, and city the process from a remote location, starting and stopping operators use an accumulated running time report to track managers can maximize the effectiveness of their activities.” They
gas companies throughout the country. the BOG compressors depending on BOG temperature, gas how long each LNG pump, air compressor, and other rotating went on to say, “We appreciate the continual support and the
composition, and volume. In addition, KOGAS has a disaster equipment throughout the terminal has been operating. This solutions that Yokogawa Korea has provided us. Yokogawa is one
The Incheon LNG terminal is the world’s largest LNG receiving protection system for dealing with critical situations, and enables a proactive approach to the scheduling of inspections of our best partners.”
complex, and it supplies natural gas to the Incheon and Seoul personnel in the central control room can share information in to determine when repair or replacement will be necessary.
metropolitan areas, which account for 40% of the country’s natural real time with operators in plants 1 and 2, ensuring a timely and This puts the right information at the right time into the
gas demand. Built on a 990,000 m2 plot of reclaimed land 8.7 km well coordinated response if fire or a gas leak is detected. hands of the right operators and managers, so they can make
off the coast, the terminal has two plants with a jetty capable of timely and correct decisions. The system can also generate the
accommodating two ultra-large LNG carriers of up to 100,000 Steady gas supply following types of reports used by plant specialists to analyze
tons in size and a total of ten 100,000 m3 above-ground storage It is very important for KOGAS to be able to adjust flexibly to overall performance of the LNG terminal as well as individual
tanks, two 140,000 m3 underground tanks, and eight 200,000 m3 shifts in demand in the gas that it supplies to power plants, processes:
underground tanks, giving it a total storage capacity of 2,880,000 industrial companies, and residences. While seawater in an
m3 (Kl). The total gas send out capacity of the Incheon terminal is ORV is normally used to cool and vaporize the LNG, in periods 1. LNG cost analysis
4,350 tons per hour. of peak demand operation can be automatically switched over 2. Electric power consumption
to an SMV that relies on the combustion of BOG to vaporize the 3. Fuel gas consumption
In 1996, Yokogawa Korea installed a CENTUM CS production LNG. Every aspect of these vaporization processes, from the 4. Unit operation cost
control system at plant 1 of the Incheon terminal, and migrated switching on and off of pumps to the control of vaporization 5. Daily cost analysis
this system to CENTUM VP in 2011. With the construction by temperature and gas pressure, is carefully configured in the 6. LNG unloading
KOGAS of plant 2 in 2004, Yokogawa Korea installed a CENTUM CENTUM system. The adjustment to shifts in demand is fully 7. BOG treatment
CS system, and subsequently installed another CENTUM CS 3000 automated at this terminal, ensuring uninterrupted supply. 8. Odorant treatment
system in 2009. Engineering work is now underway at plant 9. Running time accumulation
2 for migration to CENTUM VP. The Incheon terminal utilizes 10. Yield accounting
Yokogawa’s CENTUM systems for the control and monitoring
of facilities throughout both plants, including unloading arms,
storage tanks, recondensors, open rack vaporizers (ORV),
submerged combustion vaporizers (SMV), and trunk lines with
metering stations.
CENTUM VP operator in central control room

5 Success Story Collection Success Story Collection 6


Oman Liquefied Natural Gas LLC / Oman
LNG Supply Chain
Saih Rawl Plant

Plant Information
Location: Qalhat, Sultanate of Oman
Order date: September 2012
Completion: December 2013
The Challenges and the Solutions gas liquid is made up mainly of pentane and hexane that are
Efficient upgrade from CENTUM CS to CENTUM VP removed by fractional distillation of the feed gas after treatment.
Yokogawa Oman office has been offering resident engineer
support to OLNG, since the plant has been operational. This has After the removal of condensates, the gas (mainly methane)

Oman Liquefied Natural Gas LLC helped to plan the system modifications, upgrades and life cycle
support.
is sent to the main cryogenic heat exchanger (MCHE). The
selected liquefaction process is the propane-pre-cooled mixed
refrigerant (C3-MR) process.
One of the criteria put forth by OLNG was to ensure minimum
Upgrade of PCS Brings Higher Operation Efficiency downtime for the upgrade work due to tight LNG carriers The liquefaction step is driven by two large turbine-driven
schedules. A phased upgrade approach was adopted for the compressors, which through a series of compression and
and Productivity at Gas Liquefaction Plant in Oman three trains and the common utility operation. The human
machine interface (HMI) upgrade was successfully completed
adiabatic and non-adiabatic cooling steps, cools the gas to
minus 162 degrees Celsius, where the gas turns into liquid. The
without any plant shutdown and the main CPU units of field LNG is sent to special storage tanks awaiting shipment by LNG
control station (FCS) were flawlessly upgraded. Various kind of vessels to customers in Asia and Europe.

Executive Summary information related to the HMI such as graphic displays, tag
list, control group displays were migrated from CENTUM CS to
Yokogawa CENTUM VP is fully used as PCS for both plant-wide
operations and specific control strategy and monitoring such as
Oman Liquefied Natural Gas LLC (OLNG) is a limited liability The LNG production trains 1 and 2 located at the OLNG plant have CENTUM VP using the Yokogawa conversion tool. compressor anti-surge control and start-up/shut-down control.
incorporated joint venture company established by a Royal been using Yokogawa CENTUM CS production control system The upgrade work is completed on schedule. This online Exasmoc multi-variable optimizing controller and Exarqe
Decree and operated under the laws of the Sultanate of Oman. It (PCS) since 2000, and train 3 has been controlled by CENTUM upgrade work was a considerable benefit to OLNG with no robust quality estimator packages are applied to maximize the
engages in the business of producing and selling liquefied natural CS since 2005. There have been no major issues in the process production loss. liquefaction. The collaboration usage of PCS and APC provides
gas (LNG) and byproduct natural gas liquids (NGLs). control systems over the course of these years. OLNG a smooth and efficient operation.
Enhanced operator work flow
The Company undertakes, directly or indirectly, project operations
and activities necessary to liquefy, store, transport and market
With the discontinuation of the UNIX OS system, OLNG decided
to take a phased approach to upgrade its systems from CENTUM
The operator logging and handover application had issues
and caused issues to maintain and upgrade the application to
Customer Satisfaction
Oman’s natural gas and to deliver LNG to customers in the global CS to CENTUM VP for all liquefaction trains, a common facility continue to meet OLNG’s latest operating requirements as well Mr. Fahad Al Kaabi, Instrument Engineering Manager of OLNG
markets. The Company operates three liquefaction trains at its upgrade involving other systems like Exaopc stations used for PI, as its compatibility with the latest Microsoft operating system. mentioned, “ We are very happy to complete this upgrade. All our
site in Qalhat near Sur with a capacity of 10.4 million tonnes per APC (Exasmoc, Exarqe), and metering. Yokogawa’s eLogBook, an Database corruption was the other issue. OLNG needed a rapid operators reap the benefits of the latest CENTUM VP system and
annum. electronic logbook, is now an integral part of the OLNG day-to- replacement that could meet the needs of the plant while with the change of the new operating system obsolescence issue
day operations. Operator logging and handover applications are maintaining the company’s high standards. also has been resolved.”
The produced gas at the Barik, Saih Nihayda and Saih Rawl gas easily handled by this eLogBook. In addition, the central control Yokogawa delivered an enhanced release of eLogBook product,
fields are gathered at the Saih Rawl Plant – a gas field complex room (CCR) renovation has been completed. meeting the specific OLNG’s needs. Yokogawa’s eLogBook
operated on behalf of the Government of Oman by Petroleum is now an integral part of OLNG’s day-to-day operations. The
Development Oman (PDO) - in Oman’s interior. From there, a eLogBook is configured to support specific customer tasks - a
gas pipeline approximately 360 kilometres long and 48 inches in minimum of 15 separate tasks and four instructions.
diameter with a gas capacity of 34 million cubic meters a day, is Each group of OLNG operators can be assigned read / write
delivered to OLNG where the gas is liquefied. access to a specific list of tasks. This enables operators to view,
review and analyze complete activities at any time and at any
location in the plant, which in turn enhances the total operator
workflow.
Double tiered console type HMI (CENTUM CS)
• Shift operation tasks
• Shift instruction tasks
• Shift cycle hand over
• Plant-field (process common facility/storage and loading)
tasks

Optimization of gas liquefaction operation


CPU card was upgraded Acid gas (mainly carbon dioxide), water, and mercury are
removed from the gas delivered to OLNG. This cleaning is a
necessary step to enable liquefaction of the natural gas and
a safe production for OLNG. Condensate which is a natural
CENTUM VP configuration upgraded Phase-wise upgrade completion Double tiered high density LCD HMI (CENTUM VP)

7 Success Story Collection Success Story Collection 8


Terminale GNL Adriatico Srl / Italy
LNG Supply Chain

The Challenges and the Solutions


Plant Information
Safe operation Visualization of terminal operations
Location: Porto Viro, Italy At the ALT, safety is the top priority. A robust and reliable Systems from other vendors such as the LNG unloading system,
Order: 2008 ICSS made up of the CENTUM CS 3000 DCS and the ProSafe- tank gauging system, pipeline monitoring system, metering
Operation: November 2009 RS SIS, together with a leakage detection system powered by system, and gas turbine system are all integrated through a
the STARDOM network-based control system, provide non-stop Modbus interface with the ALT’s main CENTUM control system.
disaster protection. Operation of the ICSS from the CENTUM The resulting ability to visualize process data from throughout
human machine interface is convenient and user friendly. the terminal allows the preparation of production reports,

Terminale GNL Adriatico Srl The SIS and DCS faceplates have the same look & feel, and
security measures are in place that restrict SIS faceplate access
calculation of plant efficiency, and analysis of the performance of
individual processes. Reports on the accumulated running time
to authorized individuals. In an emergency, operators have of rotating equipment such as LNG pumps and compressors are
all the information they need to take immediate and effective compiled, allowing operators to determine the optimum timing
World’s First Offshore Regasification Terminal Relies measures including the operation of safety valves. for equipment maintenance and replacement. The visualization
of data from throughout the terminal puts the right data in
on Yokogawa ICSS (CENTUM CS 3000, ProSafe-RS) Steady supply
Providing a steady supply to the national grid is another
from of the right person, enabling the right decision to be made
at the right time.
important role of the ALT. The terminal has two tanks that can
store up to 250,000 m3 of LNG, an amount sufficient for meeting

Executive Summary four days of demand, so punctual LNG carrier scheduling and
efficient LNG unloading and vaporization are required. The
Terminale GNL Adriatico Srl, commonly known as Adriatic LNG, Acting from the early stages of this project as main instrumentation gas quality is sampled by a GC1000 gas chromatograph and
was established in 2005 by Qatar  Petroleum, ExxonMobil, and and control contractor (MICC), Yokogawa Europe installed an controlled to meet the specifications of the national grid. Thanks
Edison for the purpose of designing, building, and operating the integrated control and safety system (ICSS). The individual in good part to the robust reliability of the integrated CENTUM
world’s first offshore regasification plant. Located in the northern components of this system are the CENTUM CS 3000 distributed CS 3000 and ProSafe-RS systems, the terminal has continued
Adriatic Sea, approximately 15 km off the coast from Porto control system (DCS) and the ProSafe-RS safety instrumented to operate 24 hours a day, 7 days a week, with an availability
Levante, Italy, the Adriatic LNG Terminal (ALT) is a huge state- system (SIS) for IPS/F&G, and it is supplemented by the STARDOM approaching 99.5%.
of-the-art gravity based structure* (GBS) with facilities for the network-based control system for pipeline monitoring & leak Asset Optimization
mooring and unloading of liquid natural gas (LNG) vessels, two detection at block valve and metering stations and an operator The ALT is located offshore, so maintenance of the facilities and
125,000 m3 LNG storage tanks, and an LNG regasification plant. training system (OTS) from Omega Simulation. the control system, instrumentation and equipment is essential.
Gas from this facility is shipped to the mainland via a newly built To maintain a stable operation, unexpected field device
pipeline that connects to the national gas distribution network. * A structure that sits on the ocean floor and is held in place by failures must be prevented. The ALT uses the Plant Resource
gravity Management package (PRM). Field digital technology allows an
Sitting in waters that are 29 meters deep, the ALT is 375 meters long operator to clearly see the status of field devices at any time.
and 115 meters wide, with a main deck that rises 18 meters above Operators and maintenance crews continuously monitor field
sea level and a flare tower that tops out at 87 meters above sea devices from the Control Room using the PRM. Maintenance
level. With its nominal 8 billion m3 per year regasification capacity activity is scheduled before predicted device failure. Yokogawa
(equivalent to 775 million cubic feet per day), approximately equal continuously supports the PRM in order to ensure optimized
to 10% of the country’s gas consumption, the ALT is making a Weekly demand pattern management of the asset.
significant contribution to the diversification of Italy’s energy
sources, and is thus contributing to the country’s energy security.
Customer Satisfaction
The LNG for this plant comes mainly from Qatar but also from Russell Golson, Operations Manager at the ALT, said, “We are
Egypt, Trinidad & Tobago, Equatorial Guinea and Norway. Edison confident in our ability to provide a steady supply of gas to the
has a 25 year contract for 80% of the gas from the ALT, and the national grid because our integrated control and safety system
remaining 20% is open to third parties. Of this latter amount, 12% is reliable. LNG carrier scheduling, unloading, tank storage, and
is allocated according to the procedures defined by the Italian vaporizing are all procedure based operations and are carried out
Ministry of Economic Development and the Regulatory Authority flawlessly. The terminal’s availability is about 99.5%. We strive to
Central control room
for Electricity and Gas. automate terminal operations as much as possible. All process
data is clearly visualized for optimum operation, maintaining a
clear gas business plan and creating optimal LNG supply chain
scenarios.”

9 Success Story Collection Success Story Collection 10


PT Badak / Indonesia
LNG Supply Chain

Plant Information
Location: Bontang,
Project Scope & Results
East Kalimantan, Indonesia On this project, Yokogawa’s scope was not limited to just the The results and benefits include:
Order date: December 1999 supply of the control system and the cutover work, but also • An increase of steam production from 6%-12% from original
Completion: September 2002 included responsibility for all of the major safety and electrical max load (total of 11 boilers rated 295t/h per boiler)
systems, playing an important role as a system integrator. • Improvement of boiler response time of 6.7 to 7.9 seconds for 1
ton of steam flow rate change
Now, all eight trains including the associated utilities and offsite • A decrease of production down time since the first two trains’

PT Badak facilities are controlled by the Yokogawa CENTUM, which are


integrated into one system consisting of approximately 100 man-
cutover in September 2001
• Allowed a supervisory computer system that enabled process
machine interfaces and 100 field control stations. As a result data from all eight trains, utilities and offsite facilities of Module
of the change from panel mounted single loop controllers to a I & II to be acquired and monitored at a single location
Trains A-D DCS Retrofit & Instrumentation Upgrade DCS on Module I, there was an increase in both productivity and
efficiency of plant operations. “We are very proud to have participated in this prestigious project,
at Natural Gas Liquefaction Plant and are appreciative of PT Badak, the LNG operators and Chiyoda
- the EPC contractor - for giving us this opportunity and their
strong support throughout this project.”

Background Project Schedule


PT Badak (a subsidiary of Indonesia’s National Oil & Gas Company, Although the project schedule was very tight, the project was
PERTAMINA) operates one of the largest LNG production complex completed ahead of schedule without any trouble. This greatly
in the world, having eight LNG process trains, associated utility owes to the way of working where PT Badak, Chiyoda and
plants and offsite facilities. The first four trains including the utility Yokogawa carried out the cutover work as one integrated team.
plant and offsite facilities (i.e. Module I), were commissioned in
1977 and 1983 respectively. They were being monitored and • The design, engineering and manufacturing were conducted in
controlled by panel mounted single loop controllers. In order to a very short time - seven months from kick-off meeting.
enhance the reliability and due to obsolescence of equipment of • The factory acceptance test including the system integration
the Module I plant facilities, an entire revamp / upgrade of the test with the sub systems was carefully conducted in four
control, safety and the electrical system took place, with Chiyoda months.
Corporation being the prime EPC contractor. • It took only 13 months after the kick-off meeting for the start of
the initial cutover work.
The remaining four trains including the associated utilities and • The cold and hot cutover work of 14,810 I/O points was
offsite facilities (i.e. Module II) were commissioned in 1989, 1993, completed in 13 months with no impact to normal plant Central control room (after)
1997 and 1999 and are being monitored and controlled by a operation.
Yokogawa control system, the CENTUM. During the past 15 years
of operation, the CENTUM system proved to operate without a
single shut-down and this high reliability was a key criteria to be
selected for this upgrade project.

Another criteria for the selection of Yokogawa as the control


system supplier for this project was the capability and experience
of cutover work – moving from the existing panel mounted single
loop controllers to the new distributed control system (DCS) with
no interruptions to the LNG production and minimal disturbance System Details System: DCS (CENTUM), Supervisory Computer System, Anti Surge Control,
to plant operation. The cutover work consists of both cold cutover Vibration & Temperature Monitoring, Hazard Monitoring & Control,
SER (Sequence of event recorder), Field Instruments, Analyzer System,
during a maintenance shut-down and hot cutover while the plant
ESD/EDP Valves, ESD (Emergency Shutdown System)/
and the control system were under normal operation. In both
EDP (Emergency Depressure System), Electrical Control, UPS, CCTV,
cases, expertise that can only be obtained through actual work
Telecommunication, Public Announcement, Fire Suppression System
experience is mandatory to minimize risks and to achieve smooth
Total I/O: 14,810
and successful project completion.
Yokogawa’s experiences and capability gained through System Configuration: Man-machine Interface x 47, Field Control Station x 49
successfully conducting such cutover type of projects around the (Four LNG Process Trains, Associated Utilities, Offsite)
world, was well recognized by the customer. Scope: System integration and cutover (hot & cold) work
Conventional analog control panel board (before)

11 Success Story Collection Success Story Collection 12


Saibu Gas Co., Ltd. / Japan
LNG Supply Chain

The Challenges and the Solutions


Plant Information
Scalable, flexible configuration with functions General-purpose communications network used
Location: Nagasaki, Japan distributed to multiple controllers on a facility basis for control bus
Order date: December 2001 The Nagasaki Works employs many cutting-edge technologies Controllers installed over a wide area spanning from the
Completion: March 2003 at its LNG receiving terminal facilities, which include a berth central control room (CCR) to the berth and shipping terminal
for arriving LNG tankers, an LNG regasification plant, and a communicate with each other through Ethernet and fiber-
terminal where LNG is reloaded onto tank lorries for shipping. optic cables. The cost of the new system is reduced by using
STARDOM controllers are assigned to the monitoring and general-purpose network cables and equipment, and reliability

Saibu Gas Co., Ltd. control of the individual facilities, each of which carries out a
different function.
is improved through the use of redundant control buses and
repeaters.

Redundant architecture optimally designed for Integrated operation environment through web-
Compact, Well-designed LNG Terminal Ensures Stable requirements of entire plant based HMI
Assigning controllers on a facility basis ensures each facility’s A SCADA system with a web-based HMI enables the same
Supply of Utility Gas independence, improving the reliability of the entire LNG
terminal. For greater safety, high priority facilities have
operation to be performed at the CCR and the berth control
room, which are 1 km away from each other and are connected
redundant controllers. Facilities with a redundant configuration by fiber-optic cables.
employ a single CPU, eliminating extra investment for higher

Executive Summary cost performance.

Saibu Gas Co., Ltd. built an LNG receiving terminal at its Nagasaki
Works to ensure a stable supply of clean-burning utility gas to its
customers in Nagasaki Prefecture. In a project that will serve as a
model for future terminals, Saibu Gas achieved a superb design
that fit all plant functions into a limited area. Yokogawa’s 30 years
of experience in providing control systems for LNG receiving
terminals was instrumental in ensuring a successful outcome for
this project.

- Scalable, flexible configuration with functions distributed to Mr. Hayakawa, Manager, Mr. Yamanaka Manager
Nagasaki Works, Saibu Gas Nagasaki Works
multiple controllers on a facility basis
- Redundant architecture optimally designed for requirements of
entire plant
- General-purpose communications network used for control bus
- Integrated operation environment through web-based human
machine interface (HMI)

“We are very satisfied with the STARDOM system as it has exactly
the kind of ultra-distributed configuration that we had in mind. Total process flow
The plant started up smoothly, and our operators are comfortable
working with this system.”
Mr. Murashima Leader Mr. Masumoto Leader
Nagasaki Works Nagasaki Works

13 Success Story Collection Success Story Collection 14


Saibu Gas Co., Ltd. / Japan
LNG Supply Chain

About Saibu Gas Co., Ltd.


Founded in 1930, Saibu Gas stably supplies gas to 16 cities and 16 System Details
towns (as of June 2007) in three prefectures of the Kyushu region. Controller: STARDOM FCN Autonomous Controller

Saibu Gas Co., Ltd.


Its business operations can be categorized into:
HMI: STARDOM SCADA VDS
- Production, supply, and sales of utility gas
- Heat supply
- LNG sales and cold energy utilization
- Production, sales, and installation of gas appliances, and related
construction work

The Site Configuration About the Nagasaki Works


The LNG receiving terminal at the Nagasaki Works was built in
2003 to facilitate the supply of gas to Nagasaki Prefecture. In
Berth control room (FCN autonomous Underground LNG tank
this rugged and confined coastal area, Saibu Gas succeeded in
controller)
The tank was built underground designing and constructing a berth, regasification plant, shipping
Displays are mounted next to the controller for aesthetic reasons. It has an terminal, and other facilities that enable the stable supply of gas
in the berth control room to enable monitor - internal diameter of 37 m and to 120,000 households in the Nagasaki area.
ing of the overall site status. A web browser can hold up to 35,000 kl. As LNG
displays the same information here and at is cooled to -162°C, the inside
the CCR, which is 1 km away. of the tank is lined with thermal
insulation and a cold-resistant
As the HMI information is transmitted via
stainless membrane.
the control bus, there was no need to install
a separate network.

Gas holder
Berth

In late September 2003, the


Nagasaki Works received its first
shipment aboard the tanker Aman
Hakata, which arrived from Malay -
sia with 18,800 ㎥ of LNG. This
was the ship’s first visit to Japan. CCR

All LNG terminal functions including gas


production and storage, maintenance,
and disaster prevention are centrally
Loading arm
controlled from the CCR. The two large
LNG is received through displays give an integrated overview of
the on-shore piping, which operating status, making it possible to
is connected through these deal with abnormal incidents quickly
loading arms to the tanker and operate the terminal safely.
moored at the berth.

15 Success Story Collection Success Story Collection 16


Shanghai LNG Company Limited / China
LNG Supply Chain

Steady gas supply


Shanghai relies on this LNG terminal for 40% of its natural gas,
with the remainder coming from the West-East Gas Pipeline and
Plant Information a coal gasification plant. The CS 3000 DCS is the terminal’s main
control system and its field control stations (FCS) are highly
Location: Shanghai, China reliable, with an availability of more than 99.99999% (seven 9s).
Order date: February 2008 The pipeline delivering gas to Shanghai is accurately monitored
Completion: December 2009 and controlled using Yokogawa’s STARDOM network-based
control system and the FAST/TOOLS SCADA monitoring
package. The terminal operates reliably around the clock, 365 Engineering room (DCS/ESD/FGS displays)
days a year.

Shanghai LNG Company Limited Maximum automation


A room with engineering workstations is located right next
to the central control room to facilitate the efforts of SHLNG’s
Yokogawa Provides CENTUM CS 3000 and ProSafe-RS engineers to automate the terminal’s control loops. Currently
more than 90% of the control loops have been automated,
for China’s Third LNG Terminal bringing tremendous benefits. SHLNG is now considering certain
procedural changes that will yield additional improvements in
this area, and is using the OmegaLand simulator to optimize
each loop’s control strategy.

Executive Summary Effective use of asset management system (PRM)


China is rapidly developing into a major global economic power. For this project, Yokogawa China successfully installed and Before plant start-up, each loop was checked to make sure that
To succeed in its drive to be the center of manufacturing for just commissioned Yokogawa’s CENTUM CS 3000 distributed control wiring had been done correctly, signals were being correctly Rack room (CENTUM FCS cabinets)
about everything, China has an ever growing need for energy. system (DCS), ProSafe-RS safety instrumented system (SIS), transmitted, field devices were healthy, and valves were
One of the big challenges is securing sufficient gas supplies for STARDOM network-based control system, OmegaLand operator responding accurately to controller output signals. By helping
the next 25-30 years. Like the country as a whole, Shanghai is training system (OTS), Exaquantum PIMS, and PRM asset to accurately check all these functions, PRM made it possible
undergoing a transformation into a major global economic center. management system as well as systems from other vendors. to complete the plant start-up ahead of schedule. And by
In January 2007 it was announced that CNOOC Gas and Power monitoring the status of all field devices and issuing an alarm
Limited, a subsidiary of China National Offshore Oil Corporation,
had signed an agreement with Shenergy Group Limited for the
The Challenges and the Solutions to maintenance engineers when preset conditions are reached,
PRM makes possible a proactive maintenance approach that
development of the Shanghai LNG terminal by Shanghai LNG Safety significantly reduces total cost of ownership.
Company Limited (SHLNG). The LNG is transported from Malaysia Safety is an absolute requirement for this LNG terminal. The
to Shanghai, the economic hub of east China. This is the third LNG
terminal in China, with the others being in Guangdong and Fujian.
ProSafe-RS SIS is fully integrated with the CENTUM CS 3000 DCS,
providing operators a unified operating environment in which
Customer Satisfaction
Its current gas production capacity is 3 million tons per year, and they can monitor all DCS and SIS loops from the same human Li Wen, Director of SHLNG’s Facility Equipment Department, said,
a second construction phase starting in 2011 will double that. machine interface (HMI). “We completed the first phase of this project and are supplying
The Shanghai LNG terminal is comprised of an LNG dock, three gas to Shanghai every day without any problems. We supply
160,500 m3 receiving tanks, regasification facilities, and a 40 km The layout of the central control room is designed with safety nearly 40% of the gas used by Shanghai. It follows that this role
subsea gas trunk line to Shanghai. in mind. The mimic panel consoles for the fire and gas system of providing a stable gas supply is a very important one. We ProSafe-RS SIS
and the emergency shutdown system follow the same design. A very much appreciate Yokogawa’s highly reliable systems and
large screen displays graphics of plant facilities as well as video products. We will continue to improve our operations and will
from CCTV cameras, so operators can easily spot problems work to make more effective use of the OmegaLand OTS, PRM,
and take quick action. All systems throughout the terminal are and Exaquantum. We plan on working with Yokogawa for a long
integrated with the CS 3000 DCS, allowing the Exaquantum time to come.”
PIMS to gather and process data from nearly 1,500 processes
and display this in 30 different management level screens
that provide information on plant performance, gas demand System Details DCS: CENTUM CS 3000 (I/O: 1,600 points)
scheduling, gas production, gas specification, and nomination ESD: ProSafe-RS (I/O: 700 points)
& allocation. Pipeline SCADA: STARDOM (I/O: 600 points)
OTS: Exatif & OmegaLand
For added safety, Yokogawa installed its OmegaLand OTS. This PIMS: Exaquantum (1,500 points of data on 30 pages)
simulator is used by both new and veteran operators to acquire Asset management system: PRM
and brush up on essential plant operation skills. Fire & gas system: GE-GMR (I/O: 1,200 points)
Fire & gas detector: CCTV flame, gas detector, beacon, MAC, etc/
Large screen: Planar
Central control room

17 Success Story Collection Success Story Collection 18


Skangass AS / Norway
LNG Supply Chain

System integration optimizes total plant GC1000 for LNG analysis


operation Yokogawa GC1000 gas chromatographs sample the LNG
Key to maintaining safe operations is for the operators to components and transfer their readings to the CENTUM DCS. With
know in real time what is happening throughout the plant. This this data, operators are able to adjust production specifications to
Plant Information has been made possible through the complete integration by meet the requirements of the company’s LNG storage terminal
Yokogawa of the plant’s CENTUM VP DCS, FAST/TOOLS SCADA customers throughout Scandinavia.
Location: Stavanger, Norway system, and ProSafe-RS SIS with other systems such as the tank
Order date: 2009 gauging system. At their control stations, operators can easily
Completion: 2010 call up and view trend chart, plant overview, alarm summary,
and operation guide graphics, giving them the right information
at the right time on processes throughout the plant.

Skangass AS For example, operators can confirm on screen the status and
operating sequence for the plant’s two drier absorbers, which
alternate on a 24 hour schedule, with one unit operating and
the other regenerating. To guard against thermal shocks during
Yokogawa’s Integrated Solutions Contribute to Safe and startup or shutdown, they also are able to monitor temperatures
in the coil-wound heat exchanger, whose operation is key to the
Steady Production at Gas Liquefaction Plant in Norway natural gas liquefaction process and which has been carefully
configured in the CENTUM VP system. In real time, operators ROTAMASS for coolant flow measurement
can monitor at their terminals remote terminal data that has A Yokogawa ROTAMASS Coriolis mass flowmeter is used to
been transferred via a general packet radio system link to measure flow in the lines that supply coolant to the plant’s

Executive Summary The Challenges and the Solutions the Yokogawa FAST/TOOLS SCADA system in the main office,
contributing to the overall efficiency of the Skangass facility and
refrigeration facility. Operators have come to depend on its high
accuracy and stability for determining whether sufficient coolant
Skangass AS, a joint venture of Lyse AS and Celcius Invest AS, OTS for familiarization of liquefaction processes ensuring increased safety and stable production. is being provided.
was established in 2007 with the aim of building and operating and operator training
medium-sized low carbon emission energy plants. The company Skangass needed to avoid any delays in getting this new plant With this integrated system, a single operator per shift can
recently completed construction of a natural gas liquefaction fully operational, and key to that was having all plant personnel control the entire plant from the central control room.
plant at Risavika in Sola municipality that produces 300,000 tons fully trained right from the start of operations. For the first
of LNG per annum. The plant receives natural gas from a field in time ever, and in a team effort with Skangass, Yokogawa
the North Sea via a 50 km high pressure pipeline from Kårstø that configured a full stimulation type operator training simulator
was built by Lyse. for a gas liquefaction plant, employing the same safety and
automation system (SAS) as the actual plant, with fully identical
This plant has all the facilities necessary for every phase of the operational functions. This high fidelity model of the natural .
natural gas liquefaction process, including CO2 removal systems, gas liquefaction process behaves exactly like the actual plant
a 30,000 m3 storage tank, a coil wound heat exchanger is used as and allows plant upsets and equipment malfunctions to be
main cryogenic heat exchanger, a Linde multi-refrigerant cascade simulated in a stimulative training environment. This makes it
process, and utilities for the generation of electricity and steam. To possible for operators at Skangass to undergo repeat training
ensure safe and efficient operations at this new plant, Yokogawa
Europe successfully installed an integrated plant process control
for a full range of situations.
Customer Satisfaction
system consisting of a CENTUM VP distributed control system Roy Kenneth Skar, Operation Team Leader, said, “Yokogawa
(DCS), FAST/TOOLS supervisory control and data acquisition has strong experience in LNG processes, and their engineers
system (SCADA), ProSafe-RS safety instrumented system (SIS), and understand our process. The project execution was done by
Omegaland operator training simulator (OTS). The plant has been engineers from Skangass and Yokogawa. The OTS really helped
running smoothly since becoming fully operational in 2010. us to know the process. We are very satisfied with Yokogawa’s
systems for our liquefaction plant. Though our liquefaction rate
is still a small portion of total gas supply from the North Sea gas
field, we are expanding this LNG business continuously to meet
market demand. A constant and steady operation and plant
availability are mandatory to expand our business.”

Plant process overview One operator per shift in the central control room
Mr. Skar

19 Success Story Collection Success Story Collection 20


PTT LNG Company Limited / Thailand
LNG Supply Chain

The Challenges and the Solutions


Plant Information Safe, uninterrupted operations and truck loading administration room as well as 10 other
Customers all over the country rely on receiving a regular subsystems via Modbus communications allows operators at
Location: Rayong, Thailand supply of gas from this LNG import terminal, which operates the CENTUM human interface stations (HIS) in the CCR complete
Order: 2010 24/7. It is thus absolutely essential to prevent any shutdowns real-time access to information on operations throughout
Completion: 2011 or other problems that would interrupt this supply. A key asset the terminal. This ensures that they have all the information
that makes this possible is the OmegaLand OTS. In preparation needed to make the right decisions at the right time. PTTLNG is
for the arrival of each LNG carrier, operators in the central thus able to make maximum use of all of this terminal’s assets.
control room (CCR) run simulations of all key terminal processes

PTT LNG Company Limited such as offloading and regasification on the OTS. This reduces Effective operator training
the likelihood of any mistakes and ensures smooth and safe As this LNG import terminal is the first of its type in Thailand, it is
terminal operations. absolutely essential from the safety and efficiency standpoints
for its operators and engineers to always be fully trained on all
DCS, SIS, PRM, FOUNDATION™ Fieldbus instruments, While configuring this fully integrated control system solution system operations and procedures. By using the OmegaLand
for PTTLNG, Yokogawa strictly followed the following safety OTS for its operation familiarization training programs, PTTLNG
and OTS Installed at Thailand’s First LNG Terminal standards:
- NFPA59A (National Fire Protection Association) standard on
is able to give its personnel repeated training for a full range
of operational procedures as well as all situations that they
production, storage, and handling of LNG can expect to encounter while operating and maintaining this
- EN1473 (European Norm) standard on onshore installation terminal.

Executive Summary and equipment design for LNG


- SIGTTO (Society of International Gas Tanker and Terminal Quality control
Natural gas is Thailand’s primary fuel source and is absolutely Gas also be transported via the PTT pipeline system to power Operations Limited) operating standard and best practices Quality control is also essential at this terminal. The results of
essential to the country’s industries, particularly the power sector: companies and other important industrial customers throughout for gas tanker and terminal operations gas quality analysis and all associated data are entered into the
two third’s of the country’s electricity is generated at gas-fired the country. laboratory instrument management system (LIMS) server in the
power plants. Much of Thailand’s natural gas comes from gas Once all personnel are all fully trained and gain sufficient laboratory room and all data are transferred to the CENTUM
fields in the Gulf of Thailand. It is transported throughout the Construction of the first terminal commenced in early 2008 and experience in operating this terminal, the plan is for it to operate system, which generates a laboratory report allowing each
country via a network of offshore and onshore pipelines built by was completed in 2011, and the terminal began commercial with just six personnel on each 12 hour shift: one supervisor, operator to confirm their operating procedures and make any
the national gas and oil company, PTT Public Company Limited operation later that year when it received its first shipment of one board operator, and four field operators. required adjustments to maintain high quality production.
(PTT PCL). In 2005, due to economic growth and the resulting LNG from Qatar. This terminal includes a jetty capable of receiving
shortfall in the supply of natural gas, the country’s National LNG carriers with capacities up to 264,000 m3, two 160,000 m3 Asset maximization Truck loading
Energy Policy Board resolved to begin importing LNG. full containment LNG tanks, a 5 million ton/year regasification The transmitters, flowmeters, and control valves throughout A portion of the LNG arriving at this terminal is transported in
(vaporizer) train, a boil-off gas recondensor, a sendout station, this terminal are all FOUNDATION™ Fieldbus enabled and can trucks to local LNG terminals. A terminal automation system
In anticipation of this policy shift, PTT PCL established PTT LNG and an LNG pump. be continually monitored using the PRM solution. Alarms are (TAS) keeps track of all essential custody transfer data such as
Company Limited (PTTLNG) in 2004 and tasked it with building issued before any device fails completely, enabling predictive the truck number, destination, LNG amount, date and time, and
and operating the country’s first LNG import terminal at Map Ta To control key terminal facilities, PTTLNG went with a Yokogawa maintenance that reduces maintenance costs throughout customer name, and this data is all recorded and fed back to the
Phut, a deepwater port 220 km southeast of Bangkok. They send solution consisting of the CENTUM VP production control system, the facility lifecycle. The complete integration of all systems production control system. So operators can recognize the total
out gas to the adjacent Map Ta Phut industrial estate, which is ProSafe-RS safety instrumented system, OmegaLand operator including those at the jetty substation, laboratory, fire station, LNG amount versus gasification amount and they can easily
one of Thailand’s most important industrial areas and home to a training system (OTS), asset management package - Plant visualize the total efficiency of this plant.
number of petrochemical, oil refining, steel, and fertilizer plants. Resource Manager (PRM), and FOUNDATION™ Fieldbus field digital
technology. Work on this project was executed by Yokogawa, which
functioned as main automation contractor (MAC).

PTT LNG terminal overview LNG import terminal Central control room

21 Success Story Collection Success Story Collection 22


Hazira LNG Private Limited / India
LNG Supply Chain
Network migration and integration with existing Maintaining the same hardware footprint
components Given the limited amount of space available in the control and
The key point was the need to replace just the SIS (ESD & F&G) rack room, HLPL stipulated that the ProSafe-RS system must
while keeping the existing PCS and F&G mimic panel as is. have the same footprint as the system that it replaced. It was
This involved the removal of the MULCOM interface unit and indeed a challenge to fit the ProSafe-RS terminal boards into
ProSafe-PLC components and their replacement with ProSafe- this space without compromising Yokogawa’s high engineering
RS components on a Vnet/IP control bus. To enable the use of standards.
the existing PCS network (V net), Yokogawa India installed an
Plant Information AVR10D V net router.
Customer Satisfaction
Location: Hazira, Gujarat, India The most challenging aspect of this migration was the software, Yet another primary criterion for this migration project was the
Order date: September 2012 which included special logic on the PCS for controlling the need to complete the entire migration during a planned eight
Completion: March 2013 MULCOM interface unit. To reduce network load, Yokogawa day shutdown. This was not an easy task considering the fact that
India conducted a thorough investigation and was able to Yokogawa India had to migrate the entire SIS at the main control
remove this logic without impacting the PCS logic. room and jetty, and hook this up with the original PCS.

Hazira LNG Private Limited In addition, the MULCOM interface unit had ISA-F3A alarm
indication logic for the F&G mimic panel.
Thanks to the integration of the PCS and SIS, HLPL personnel are
now able to use the same HMI for the PCS and SIS to operate the
All of this functionality was successfully embedded in the entire terminal. All the faceplates and other operation displays
ProSafe-RS system, and HLPL continues to use the mimic panel have the same design. This helps to eliminate operator errors
Legacy ProSafe-PLC SIS Replaced with ProSafe-RS to as an operation interface. and allows HLPL’s engineering team to use the same engineering
environment to make configuration changes to the PCS and SIS,
Improve Sustainable Lifecycle Support at LNG Terminal Continued operation of BOG and MSO
compressors during migration
reducing both engineering workload and maintenance costs.

For the project execution phase, HLPL inquired whether it A key factor in the success of this project was the micro level
would be possible for safety reasons to continue operating planning for the site erection and commissioning activities and

Executive Summary two boil off gas (BOG) compressors and a minimum send out
(MSO) compressor. Yokogawa India took up this challenge in
the clear definition of roles and responsibilities for each member
of multilevel teams that worked round the clock.
Hazira LNG Private Limited (HLPL), a joint venture between Shell PCS and SIS, and improved safety and integrity, HLPL opted to spite of the fact that the running/trip logic for this equipment
Gas B.V. and Total Gaz Electricite Holdings, operates an LNG go with Yokogawa India’s migration proposal. resided on the existing ProSafe-PLC system, which needed to As a testimony to Yokogawa India’s success in this endeavor, HLPL
receiving terminal in Hazira, which is a major port and industrial be disconnected as part of the migration. The company offered offered the following generous praise:
hub in India’s Gujarat state. Commissioned in 2005, the terminal
has two 160,000 m3 storage tanks along with re-gasification and
The Challenges and the Solutions an innovative workaround by implementing this logic on a
stand-in ProSafe-RS system that was temporarily hooked up “The Yokogawa team performed the engineering, design, pre-FAT,
auxiliary facilities that are capable of handling 3.6 million tons of Migrating application logic while keeping to the existing PCS for the duration of the migration process. and FAT so well that the site installation and commissioning were
LNG per year. This is the first LNG terminal in India to be built by existing engineering philosophy Following the completion of all migration activities, the data on flawlessly completed. This was an important aspect in ensuring
global energy companies. HLPL was specific in its requirement that the ProSafe-RS system the stand-in system was merged with that on the main ProSafe- that the installation and commissioning were completed by the
A 22 km pipeline connects the Hazira terminal to the national gas had to retain the same engineering philosophy used with the RS system. targeted completion date. The team’s excellent knowledge and
grid at Mora Station. The pipeline has sectionalizing valve (SV) and ProSafe-PLC system. HLPL also insisted that the migration commitment were also visible in pre-shutdown activities, where
LNG custody transfer metering (CTM) stations that are located 4 project should leverage the latest advances achieved in the Exhaustive planning coupled with clinically perfect execution many activities had risks of manual errors that could cause a
km and 14 km from the terminal, respectively. ProSafe-RS system software blocks. helped Yokogawa India meet this client’s demanding process shutdown; however all these activities were completed
The control systems for the Hazira terminal are installed in requirements with a minimum of disruption to terminal impeccably.”
its main control room (MCR), which handles all re-gasification Yokogawa’s PLC2RS tool for converting from ProSafe-PLC operations. As a result, both the BOG and MSO compressors
processes and utilities, and at the jetty facility, where arriving LNG to ProSafe-RS applications proved to be extremely effective were able to continue operating throughout the migration “The project was very challenging as it had to be completed
carriers are unloaded. in fulfilling the client’s requirement to retain the essential process. in eight days and had to be integrated well with other HLPL
engineering features of the terminal’s existing systems. The shutdown activities. The Yokogawa team’s meticulous planning
Original configuration base application output by the conversion tool implemented all and flexibility in making necessary schedule changes helped
The Hazira terminal’s process, utility, jetty, and pipeline the latest features of the ProSafe-RS software. The engineering a lot in preventing conflicts with other concurrent shutdown
operations were all originally automated with a Yokogawa output was a perfect blend of the original engineering activities. Yokogawa India’s customer focused approach is highly
CENTUM CS 3000 process control system (PCS), a ProSafe-PLC philosophy and the latest software features, and engineering appreciated.”
safety instrumented system (SIS) with emergency shutdown time was drastically reduced.
(ESD) and fire and gas detection (F&G) functionality. The HIS HIS (HMI)
F&G HIS HIS (HMI)
ProSafe-PLC was connected to the PCS via a MULCOM multiple F&G
protocol communication interface unit, an M-net bus (SIS mimic
mimic
V net
control bus), and a V net bus (PCS control bus), with all these
V net
systems sharing the same human machine interface (HMI). MULCOM
AVR10D
M-net
New configuration Vnet/IP

As the legacy ProSafe-PLC system was costly to maintain and CENTUM


CENTUM
was reaching its end of support date, Yokogawa India proposed (PCS)
(PCS)
that HLPL upgrade to Yokogawa’s latest SIS offering, ProSafe-
ProSafe-PLC ProSafe-RS
RS. After considering the merits of adopting the latest hardware (SIS) (SIS)
and software, which included the use of a single control bus for
all terminal facilities, the seamless use of the same HMI for both ProSafe-PLC system cabinet system cabinet ProSafe-PLC (before) (after)

23 Success Story Collection Success Story Collection 24


Success Story Collection
LNG Supply Chain

YOKOGAWA ELECTRIC CORPORATION


World Headquarters Represented by:
9-32, Nakacho 2-chome, Musashino-shi, Tokyo 180-8750, Japan
http://www.yokogawa.com/

YOKOGAWA CORPORATION OF AMERICA


12530 West Airport Blvd, Sugar Land, Texas 77478, USA
http://www.yokogawa.com/us/

YOKOGAWA EUROPE B.V.


Euroweg 2, 3825 HD Amersfoort, The Netherlands
http://www.yokogawa.com/eu/

YOKOGAWA ENGINEERING ASIA PTE. LTD.


5 Bedok South Road, Singapore 469270, Singapore
http://www.yokogawa.com/sg/

YOKOGAWA CHINA CO., LTD.


3F TowerD Cartelo Crocodile Building
No.568 West Tianshan Road, Shanghai 200335, China
http://www.yokogawa.com/cn/

YOKOGAWA MIDDLE EAST & AFRICA B.S.C. (c)


P.O. Box 10070, Manama
Building 577, Road 2516, Busaiteen 225, Muharraq, Bahrain
http://www.yokogawa.com/bh/

Trademarks
All brand or product names of Yokogawa Electric Corporation in this bulletin are trademarks or registered trademarks of Yokogawa Electric Corporation.
All other company brand or product names in this bulletin are trademarks or registered trademarks of their respective holders.

Subject to change without notice


All Rights Reserved. Copyright © 2016, Yokogawa Electric Corporation

[Ed:02/d] Printed in Japan, 910(KP)

Bulletin 00A01A54-01EN

You might also like