Professional Documents
Culture Documents
Trademarks
All brand or product names of Yokogawa Electric Corporation in this bulletin are trademarks or registered trademarks of Yokogawa Electric Corporation.
All other company brand or product names in this bulletin are trademarks or registered trademarks of their respective holders.
Bulletin 00A01A54-01EN
■Contents
South Hook LNG Terminal Ltd. supplied a full automation control system for this terminal,
which incorporated the DCS (distributed control system),
network connection between OmegaLand and an actual DCS
(the CENTUM CS 3000), it is possible for operators to receive
emergency shutdown (ESD) system, fire and gas (F&G) system, realistic training in a virtual environment.
fire and gas devices, asset management system, data historian Training is available for procedures such as plant startup and
Yokogawa Provides CENTUM CS 3000 and ProSafe-RS system and operator training simulator. The basis of this LNG load change, abnormal conditions such as an instrument or
terminal solution is Yokogawa’s CENTUM CS 3000 R3 DCS equipment failure, and exceptional emergency situations
for the Largest LNG Terminal in Europe system and ProSafe-RS safety instrumented system, which are
considered the most reliable process automation system on the
such as earthquakes, fires and runaway reactions. Because
the simulator uses exactly the same algorithms as the actual
market. control system, individuals can be fully trained to respond to
As LNG EPC projects have increased in size and complexity, emergencies, however rare, that could lead to a plant shutdown.
Plant Information
Location: Malaysia
Project Profile The Challenges and the Solutions Benefits Realized Customer Satisfaction
Yokogawa has been selected to supply the CS3000 for Integrated There was a requirement for an intensive site survey onboard With the completion of the retrofitting of the new CS 3000 IAS in One of the MISC engineer commented, “We want an idiot proof,
Automation System (IAS) and Boiler Integration as well selected of the Tenaga ships to ensure that the engineering and design Tenaga and new installation on Seri ‘A’ Class LNG Carriers, MISC user friendly and reliable IAS system to ensure safe operations for
field instruments for MISC Tenaga and Seri ‘A’ Class of LNG works could be carried out successfully. A dedicated survey team could be ensured of better information visibility, performance our LNG carriers. Yokogawa CS 3000 system has proven in both
Carriers. comprises of Yokogawa global team with the assistance from the foresight, and operational agility to deliver overall operations the Tenaga and the Seri Class LNG carriers that their hardware
end-user did the onboard survey to map out all the necessary excellence, reliability, safety and on-time cargo deliveries to the is very reliable with very less problem. This means that we have
One of the tasks in the Tenaga Class project is to replace the engineering details. confidence of their charterers. fewer spare parts to purchase and hence a reduced maintenance
existing panel instrumentation and obsolete PLCs with the cost and a faster turn-around for the vessels.”
advanced CS 3000 IAS which partly will extend the service life of Part of the scope of work is to convert the existing panel MISC operation team could also benefit from the global Yokogawa
the ships built in the early 1980’s. Whereas in the Seri ‘A’ Class, the instrumentation made in the early 1980’s to accommodate the support around the world in all the destinations during the He further added, “Yokogawa CS 3000 software and operating
CS 3000 IAS will provide a reliable automation system onboard of latest in the DCS technology. These include the previous boiler Tenaga and Seri ‘A’ Class voyage. system proven to be most user friendly as almost any ship
all the newly build ships each with capacity of 145,000 cbm. The control which was based on obsolete PLC to be integrated into engineer can familiarise with the system in a very short time. The
certification bodies for the Tenaga and Seri ‘A’ class are from ABS the new DCS. With the Yokogawa capability in handling major To ensure the adherence to the highest safety standards, for all system is also very easy for our trouble shooting works.”
and BV respectively. project using the Main Automation Contractor (MAC) approach as periodic vessels’ inspection and audit conducted at the Malaysian
well as with existing close cooperation from Marine Boiler Maker
and Marine Consultant, the project was able to be successfully
dry docks, MISC will be guaranteed of Yokogawa support and
expertise from the Malaysian office. Because of similar operating
Customer Profile
completed even with a really tight yard schedule, all within a system the Tenaga and Seri ‘A’ Class ships’ crew could be MISC Berhad (MISC), a subsidiary of the PETRONAS Group
period of 2 months per ship on the average. interchangeable and hence optimise the cross-fleet integration of Companies, is a renowned leading international shipping
and operations. and logistics company with a formidable presence in energy
In the Seri ‘A’ Class ships, the challenge was in different nature transportation and marine engineering. With a fleet of 27 LNG
as these are newly build. With the knowledge gained and the MISC will also benefit from the training and process simulation at tankers, which is expected to expand to 29 by April 2009, MISC is
same dedicated team all the engineering, installation, testing and Yokogawa DCS Training Simulator Centre located at their world the world's single largest owner operator of LNG Carriers.
commissioning as well as during sea trial, the Seri ‘A’ projects have class Malaysian Maritime Academy to train sea personnel.
been successfully delivered to the satisfaction of customers. This
including the DCS integration of with Terasaki Power Management
System as well as integration of ship’s boiler system.
System Details
System: CENTUM CS 3000
Plant Information
Location: Incheon, South Korea
First Installation: 1998
Current Migration: 2011 (plant 1)
Plant Information
Location: Qalhat, Sultanate of Oman
Order date: September 2012
Completion: December 2013
The Challenges and the Solutions gas liquid is made up mainly of pentane and hexane that are
Efficient upgrade from CENTUM CS to CENTUM VP removed by fractional distillation of the feed gas after treatment.
Yokogawa Oman office has been offering resident engineer
support to OLNG, since the plant has been operational. This has After the removal of condensates, the gas (mainly methane)
Oman Liquefied Natural Gas LLC helped to plan the system modifications, upgrades and life cycle
support.
is sent to the main cryogenic heat exchanger (MCHE). The
selected liquefaction process is the propane-pre-cooled mixed
refrigerant (C3-MR) process.
One of the criteria put forth by OLNG was to ensure minimum
Upgrade of PCS Brings Higher Operation Efficiency downtime for the upgrade work due to tight LNG carriers The liquefaction step is driven by two large turbine-driven
schedules. A phased upgrade approach was adopted for the compressors, which through a series of compression and
and Productivity at Gas Liquefaction Plant in Oman three trains and the common utility operation. The human
machine interface (HMI) upgrade was successfully completed
adiabatic and non-adiabatic cooling steps, cools the gas to
minus 162 degrees Celsius, where the gas turns into liquid. The
without any plant shutdown and the main CPU units of field LNG is sent to special storage tanks awaiting shipment by LNG
control station (FCS) were flawlessly upgraded. Various kind of vessels to customers in Asia and Europe.
Executive Summary information related to the HMI such as graphic displays, tag
list, control group displays were migrated from CENTUM CS to
Yokogawa CENTUM VP is fully used as PCS for both plant-wide
operations and specific control strategy and monitoring such as
Oman Liquefied Natural Gas LLC (OLNG) is a limited liability The LNG production trains 1 and 2 located at the OLNG plant have CENTUM VP using the Yokogawa conversion tool. compressor anti-surge control and start-up/shut-down control.
incorporated joint venture company established by a Royal been using Yokogawa CENTUM CS production control system The upgrade work is completed on schedule. This online Exasmoc multi-variable optimizing controller and Exarqe
Decree and operated under the laws of the Sultanate of Oman. It (PCS) since 2000, and train 3 has been controlled by CENTUM upgrade work was a considerable benefit to OLNG with no robust quality estimator packages are applied to maximize the
engages in the business of producing and selling liquefied natural CS since 2005. There have been no major issues in the process production loss. liquefaction. The collaboration usage of PCS and APC provides
gas (LNG) and byproduct natural gas liquids (NGLs). control systems over the course of these years. OLNG a smooth and efficient operation.
Enhanced operator work flow
The Company undertakes, directly or indirectly, project operations
and activities necessary to liquefy, store, transport and market
With the discontinuation of the UNIX OS system, OLNG decided
to take a phased approach to upgrade its systems from CENTUM
The operator logging and handover application had issues
and caused issues to maintain and upgrade the application to
Customer Satisfaction
Oman’s natural gas and to deliver LNG to customers in the global CS to CENTUM VP for all liquefaction trains, a common facility continue to meet OLNG’s latest operating requirements as well Mr. Fahad Al Kaabi, Instrument Engineering Manager of OLNG
markets. The Company operates three liquefaction trains at its upgrade involving other systems like Exaopc stations used for PI, as its compatibility with the latest Microsoft operating system. mentioned, “ We are very happy to complete this upgrade. All our
site in Qalhat near Sur with a capacity of 10.4 million tonnes per APC (Exasmoc, Exarqe), and metering. Yokogawa’s eLogBook, an Database corruption was the other issue. OLNG needed a rapid operators reap the benefits of the latest CENTUM VP system and
annum. electronic logbook, is now an integral part of the OLNG day-to- replacement that could meet the needs of the plant while with the change of the new operating system obsolescence issue
day operations. Operator logging and handover applications are maintaining the company’s high standards. also has been resolved.”
The produced gas at the Barik, Saih Nihayda and Saih Rawl gas easily handled by this eLogBook. In addition, the central control Yokogawa delivered an enhanced release of eLogBook product,
fields are gathered at the Saih Rawl Plant – a gas field complex room (CCR) renovation has been completed. meeting the specific OLNG’s needs. Yokogawa’s eLogBook
operated on behalf of the Government of Oman by Petroleum is now an integral part of OLNG’s day-to-day operations. The
Development Oman (PDO) - in Oman’s interior. From there, a eLogBook is configured to support specific customer tasks - a
gas pipeline approximately 360 kilometres long and 48 inches in minimum of 15 separate tasks and four instructions.
diameter with a gas capacity of 34 million cubic meters a day, is Each group of OLNG operators can be assigned read / write
delivered to OLNG where the gas is liquefied. access to a specific list of tasks. This enables operators to view,
review and analyze complete activities at any time and at any
location in the plant, which in turn enhances the total operator
workflow.
Double tiered console type HMI (CENTUM CS)
• Shift operation tasks
• Shift instruction tasks
• Shift cycle hand over
• Plant-field (process common facility/storage and loading)
tasks
Terminale GNL Adriatico Srl The SIS and DCS faceplates have the same look & feel, and
security measures are in place that restrict SIS faceplate access
calculation of plant efficiency, and analysis of the performance of
individual processes. Reports on the accumulated running time
to authorized individuals. In an emergency, operators have of rotating equipment such as LNG pumps and compressors are
all the information they need to take immediate and effective compiled, allowing operators to determine the optimum timing
World’s First Offshore Regasification Terminal Relies measures including the operation of safety valves. for equipment maintenance and replacement. The visualization
of data from throughout the terminal puts the right data in
on Yokogawa ICSS (CENTUM CS 3000, ProSafe-RS) Steady supply
Providing a steady supply to the national grid is another
from of the right person, enabling the right decision to be made
at the right time.
important role of the ALT. The terminal has two tanks that can
store up to 250,000 m3 of LNG, an amount sufficient for meeting
Executive Summary four days of demand, so punctual LNG carrier scheduling and
efficient LNG unloading and vaporization are required. The
Terminale GNL Adriatico Srl, commonly known as Adriatic LNG, Acting from the early stages of this project as main instrumentation gas quality is sampled by a GC1000 gas chromatograph and
was established in 2005 by Qatar Petroleum, ExxonMobil, and and control contractor (MICC), Yokogawa Europe installed an controlled to meet the specifications of the national grid. Thanks
Edison for the purpose of designing, building, and operating the integrated control and safety system (ICSS). The individual in good part to the robust reliability of the integrated CENTUM
world’s first offshore regasification plant. Located in the northern components of this system are the CENTUM CS 3000 distributed CS 3000 and ProSafe-RS systems, the terminal has continued
Adriatic Sea, approximately 15 km off the coast from Porto control system (DCS) and the ProSafe-RS safety instrumented to operate 24 hours a day, 7 days a week, with an availability
Levante, Italy, the Adriatic LNG Terminal (ALT) is a huge state- system (SIS) for IPS/F&G, and it is supplemented by the STARDOM approaching 99.5%.
of-the-art gravity based structure* (GBS) with facilities for the network-based control system for pipeline monitoring & leak Asset Optimization
mooring and unloading of liquid natural gas (LNG) vessels, two detection at block valve and metering stations and an operator The ALT is located offshore, so maintenance of the facilities and
125,000 m3 LNG storage tanks, and an LNG regasification plant. training system (OTS) from Omega Simulation. the control system, instrumentation and equipment is essential.
Gas from this facility is shipped to the mainland via a newly built To maintain a stable operation, unexpected field device
pipeline that connects to the national gas distribution network. * A structure that sits on the ocean floor and is held in place by failures must be prevented. The ALT uses the Plant Resource
gravity Management package (PRM). Field digital technology allows an
Sitting in waters that are 29 meters deep, the ALT is 375 meters long operator to clearly see the status of field devices at any time.
and 115 meters wide, with a main deck that rises 18 meters above Operators and maintenance crews continuously monitor field
sea level and a flare tower that tops out at 87 meters above sea devices from the Control Room using the PRM. Maintenance
level. With its nominal 8 billion m3 per year regasification capacity activity is scheduled before predicted device failure. Yokogawa
(equivalent to 775 million cubic feet per day), approximately equal continuously supports the PRM in order to ensure optimized
to 10% of the country’s gas consumption, the ALT is making a Weekly demand pattern management of the asset.
significant contribution to the diversification of Italy’s energy
sources, and is thus contributing to the country’s energy security.
Customer Satisfaction
The LNG for this plant comes mainly from Qatar but also from Russell Golson, Operations Manager at the ALT, said, “We are
Egypt, Trinidad & Tobago, Equatorial Guinea and Norway. Edison confident in our ability to provide a steady supply of gas to the
has a 25 year contract for 80% of the gas from the ALT, and the national grid because our integrated control and safety system
remaining 20% is open to third parties. Of this latter amount, 12% is reliable. LNG carrier scheduling, unloading, tank storage, and
is allocated according to the procedures defined by the Italian vaporizing are all procedure based operations and are carried out
Ministry of Economic Development and the Regulatory Authority flawlessly. The terminal’s availability is about 99.5%. We strive to
Central control room
for Electricity and Gas. automate terminal operations as much as possible. All process
data is clearly visualized for optimum operation, maintaining a
clear gas business plan and creating optimal LNG supply chain
scenarios.”
Plant Information
Location: Bontang,
Project Scope & Results
East Kalimantan, Indonesia On this project, Yokogawa’s scope was not limited to just the The results and benefits include:
Order date: December 1999 supply of the control system and the cutover work, but also • An increase of steam production from 6%-12% from original
Completion: September 2002 included responsibility for all of the major safety and electrical max load (total of 11 boilers rated 295t/h per boiler)
systems, playing an important role as a system integrator. • Improvement of boiler response time of 6.7 to 7.9 seconds for 1
ton of steam flow rate change
Now, all eight trains including the associated utilities and offsite • A decrease of production down time since the first two trains’
Saibu Gas Co., Ltd. control of the individual facilities, each of which carries out a
different function.
is improved through the use of redundant control buses and
repeaters.
Redundant architecture optimally designed for Integrated operation environment through web-
Compact, Well-designed LNG Terminal Ensures Stable requirements of entire plant based HMI
Assigning controllers on a facility basis ensures each facility’s A SCADA system with a web-based HMI enables the same
Supply of Utility Gas independence, improving the reliability of the entire LNG
terminal. For greater safety, high priority facilities have
operation to be performed at the CCR and the berth control
room, which are 1 km away from each other and are connected
redundant controllers. Facilities with a redundant configuration by fiber-optic cables.
employ a single CPU, eliminating extra investment for higher
Saibu Gas Co., Ltd. built an LNG receiving terminal at its Nagasaki
Works to ensure a stable supply of clean-burning utility gas to its
customers in Nagasaki Prefecture. In a project that will serve as a
model for future terminals, Saibu Gas achieved a superb design
that fit all plant functions into a limited area. Yokogawa’s 30 years
of experience in providing control systems for LNG receiving
terminals was instrumental in ensuring a successful outcome for
this project.
- Scalable, flexible configuration with functions distributed to Mr. Hayakawa, Manager, Mr. Yamanaka Manager
Nagasaki Works, Saibu Gas Nagasaki Works
multiple controllers on a facility basis
- Redundant architecture optimally designed for requirements of
entire plant
- General-purpose communications network used for control bus
- Integrated operation environment through web-based human
machine interface (HMI)
“We are very satisfied with the STARDOM system as it has exactly
the kind of ultra-distributed configuration that we had in mind. Total process flow
The plant started up smoothly, and our operators are comfortable
working with this system.”
Mr. Murashima Leader Mr. Masumoto Leader
Nagasaki Works Nagasaki Works
Gas holder
Berth
Skangass AS For example, operators can confirm on screen the status and
operating sequence for the plant’s two drier absorbers, which
alternate on a 24 hour schedule, with one unit operating and
the other regenerating. To guard against thermal shocks during
Yokogawa’s Integrated Solutions Contribute to Safe and startup or shutdown, they also are able to monitor temperatures
in the coil-wound heat exchanger, whose operation is key to the
Steady Production at Gas Liquefaction Plant in Norway natural gas liquefaction process and which has been carefully
configured in the CENTUM VP system. In real time, operators ROTAMASS for coolant flow measurement
can monitor at their terminals remote terminal data that has A Yokogawa ROTAMASS Coriolis mass flowmeter is used to
been transferred via a general packet radio system link to measure flow in the lines that supply coolant to the plant’s
Executive Summary The Challenges and the Solutions the Yokogawa FAST/TOOLS SCADA system in the main office,
contributing to the overall efficiency of the Skangass facility and
refrigeration facility. Operators have come to depend on its high
accuracy and stability for determining whether sufficient coolant
Skangass AS, a joint venture of Lyse AS and Celcius Invest AS, OTS for familiarization of liquefaction processes ensuring increased safety and stable production. is being provided.
was established in 2007 with the aim of building and operating and operator training
medium-sized low carbon emission energy plants. The company Skangass needed to avoid any delays in getting this new plant With this integrated system, a single operator per shift can
recently completed construction of a natural gas liquefaction fully operational, and key to that was having all plant personnel control the entire plant from the central control room.
plant at Risavika in Sola municipality that produces 300,000 tons fully trained right from the start of operations. For the first
of LNG per annum. The plant receives natural gas from a field in time ever, and in a team effort with Skangass, Yokogawa
the North Sea via a 50 km high pressure pipeline from Kårstø that configured a full stimulation type operator training simulator
was built by Lyse. for a gas liquefaction plant, employing the same safety and
automation system (SAS) as the actual plant, with fully identical
This plant has all the facilities necessary for every phase of the operational functions. This high fidelity model of the natural .
natural gas liquefaction process, including CO2 removal systems, gas liquefaction process behaves exactly like the actual plant
a 30,000 m3 storage tank, a coil wound heat exchanger is used as and allows plant upsets and equipment malfunctions to be
main cryogenic heat exchanger, a Linde multi-refrigerant cascade simulated in a stimulative training environment. This makes it
process, and utilities for the generation of electricity and steam. To possible for operators at Skangass to undergo repeat training
ensure safe and efficient operations at this new plant, Yokogawa
Europe successfully installed an integrated plant process control
for a full range of situations.
Customer Satisfaction
system consisting of a CENTUM VP distributed control system Roy Kenneth Skar, Operation Team Leader, said, “Yokogawa
(DCS), FAST/TOOLS supervisory control and data acquisition has strong experience in LNG processes, and their engineers
system (SCADA), ProSafe-RS safety instrumented system (SIS), and understand our process. The project execution was done by
Omegaland operator training simulator (OTS). The plant has been engineers from Skangass and Yokogawa. The OTS really helped
running smoothly since becoming fully operational in 2010. us to know the process. We are very satisfied with Yokogawa’s
systems for our liquefaction plant. Though our liquefaction rate
is still a small portion of total gas supply from the North Sea gas
field, we are expanding this LNG business continuously to meet
market demand. A constant and steady operation and plant
availability are mandatory to expand our business.”
Plant process overview One operator per shift in the central control room
Mr. Skar
PTT LNG Company Limited such as offloading and regasification on the OTS. This reduces Effective operator training
the likelihood of any mistakes and ensures smooth and safe As this LNG import terminal is the first of its type in Thailand, it is
terminal operations. absolutely essential from the safety and efficiency standpoints
for its operators and engineers to always be fully trained on all
DCS, SIS, PRM, FOUNDATION™ Fieldbus instruments, While configuring this fully integrated control system solution system operations and procedures. By using the OmegaLand
for PTTLNG, Yokogawa strictly followed the following safety OTS for its operation familiarization training programs, PTTLNG
and OTS Installed at Thailand’s First LNG Terminal standards:
- NFPA59A (National Fire Protection Association) standard on
is able to give its personnel repeated training for a full range
of operational procedures as well as all situations that they
production, storage, and handling of LNG can expect to encounter while operating and maintaining this
- EN1473 (European Norm) standard on onshore installation terminal.
PTT LNG terminal overview LNG import terminal Central control room
Hazira LNG Private Limited In addition, the MULCOM interface unit had ISA-F3A alarm
indication logic for the F&G mimic panel.
Thanks to the integration of the PCS and SIS, HLPL personnel are
now able to use the same HMI for the PCS and SIS to operate the
All of this functionality was successfully embedded in the entire terminal. All the faceplates and other operation displays
ProSafe-RS system, and HLPL continues to use the mimic panel have the same design. This helps to eliminate operator errors
Legacy ProSafe-PLC SIS Replaced with ProSafe-RS to as an operation interface. and allows HLPL’s engineering team to use the same engineering
environment to make configuration changes to the PCS and SIS,
Improve Sustainable Lifecycle Support at LNG Terminal Continued operation of BOG and MSO
compressors during migration
reducing both engineering workload and maintenance costs.
For the project execution phase, HLPL inquired whether it A key factor in the success of this project was the micro level
would be possible for safety reasons to continue operating planning for the site erection and commissioning activities and
Executive Summary two boil off gas (BOG) compressors and a minimum send out
(MSO) compressor. Yokogawa India took up this challenge in
the clear definition of roles and responsibilities for each member
of multilevel teams that worked round the clock.
Hazira LNG Private Limited (HLPL), a joint venture between Shell PCS and SIS, and improved safety and integrity, HLPL opted to spite of the fact that the running/trip logic for this equipment
Gas B.V. and Total Gaz Electricite Holdings, operates an LNG go with Yokogawa India’s migration proposal. resided on the existing ProSafe-PLC system, which needed to As a testimony to Yokogawa India’s success in this endeavor, HLPL
receiving terminal in Hazira, which is a major port and industrial be disconnected as part of the migration. The company offered offered the following generous praise:
hub in India’s Gujarat state. Commissioned in 2005, the terminal
has two 160,000 m3 storage tanks along with re-gasification and
The Challenges and the Solutions an innovative workaround by implementing this logic on a
stand-in ProSafe-RS system that was temporarily hooked up “The Yokogawa team performed the engineering, design, pre-FAT,
auxiliary facilities that are capable of handling 3.6 million tons of Migrating application logic while keeping to the existing PCS for the duration of the migration process. and FAT so well that the site installation and commissioning were
LNG per year. This is the first LNG terminal in India to be built by existing engineering philosophy Following the completion of all migration activities, the data on flawlessly completed. This was an important aspect in ensuring
global energy companies. HLPL was specific in its requirement that the ProSafe-RS system the stand-in system was merged with that on the main ProSafe- that the installation and commissioning were completed by the
A 22 km pipeline connects the Hazira terminal to the national gas had to retain the same engineering philosophy used with the RS system. targeted completion date. The team’s excellent knowledge and
grid at Mora Station. The pipeline has sectionalizing valve (SV) and ProSafe-PLC system. HLPL also insisted that the migration commitment were also visible in pre-shutdown activities, where
LNG custody transfer metering (CTM) stations that are located 4 project should leverage the latest advances achieved in the Exhaustive planning coupled with clinically perfect execution many activities had risks of manual errors that could cause a
km and 14 km from the terminal, respectively. ProSafe-RS system software blocks. helped Yokogawa India meet this client’s demanding process shutdown; however all these activities were completed
The control systems for the Hazira terminal are installed in requirements with a minimum of disruption to terminal impeccably.”
its main control room (MCR), which handles all re-gasification Yokogawa’s PLC2RS tool for converting from ProSafe-PLC operations. As a result, both the BOG and MSO compressors
processes and utilities, and at the jetty facility, where arriving LNG to ProSafe-RS applications proved to be extremely effective were able to continue operating throughout the migration “The project was very challenging as it had to be completed
carriers are unloaded. in fulfilling the client’s requirement to retain the essential process. in eight days and had to be integrated well with other HLPL
engineering features of the terminal’s existing systems. The shutdown activities. The Yokogawa team’s meticulous planning
Original configuration base application output by the conversion tool implemented all and flexibility in making necessary schedule changes helped
The Hazira terminal’s process, utility, jetty, and pipeline the latest features of the ProSafe-RS software. The engineering a lot in preventing conflicts with other concurrent shutdown
operations were all originally automated with a Yokogawa output was a perfect blend of the original engineering activities. Yokogawa India’s customer focused approach is highly
CENTUM CS 3000 process control system (PCS), a ProSafe-PLC philosophy and the latest software features, and engineering appreciated.”
safety instrumented system (SIS) with emergency shutdown time was drastically reduced.
(ESD) and fire and gas detection (F&G) functionality. The HIS HIS (HMI)
F&G HIS HIS (HMI)
ProSafe-PLC was connected to the PCS via a MULCOM multiple F&G
protocol communication interface unit, an M-net bus (SIS mimic
mimic
V net
control bus), and a V net bus (PCS control bus), with all these
V net
systems sharing the same human machine interface (HMI). MULCOM
AVR10D
M-net
New configuration Vnet/IP
Trademarks
All brand or product names of Yokogawa Electric Corporation in this bulletin are trademarks or registered trademarks of Yokogawa Electric Corporation.
All other company brand or product names in this bulletin are trademarks or registered trademarks of their respective holders.
Bulletin 00A01A54-01EN