Site: UMPHAKATHI MALL PHASE1 REV 1.

3
DATE 08/06/202 PAGES 2
Risk Assessment TASK INSTALLATION OF A PERIMETER FENCE

B RISK ASSESSMENT WRITTEN BY APPROVED BY


NUMBER
NAME BHEKI GUMPO

SIGNATURE

DATE WRITTEN 08/06/2021 REVIEW DATE

A INJURY SEVERITY B FREQUENCY/OCCURRENCE RATING LAST RATINGS


0 No injury 0 Has not occurred in last two years RISK CLASSIFICATION RISK VALUE HIGH
2 Minor Laceration, Wounds (First Aids Level) 2 Occurs very seldom LOW 0-6
4 More severe injury medical attention 4 Occurs occasionally MEDIUM 6 - 16
8 Serious injuries,broken bones,amputation,etc 8 Occurs often HIGH 16 - 32
10 Loss of life / fatality 10 Could/Has happen CRITICAL 32 - 40
C POTENTIAL DAMAGE/LOSS D ENVIRONMENT ACTION REQUIRED CONSIDER
0 No damage, minimal costs R10 - R100 0 No effect nm LOW Supervision, Training, Certificate, Risk Assessment, Safe work Good Instruction
procedures, Toolbox talk
2 Minor Damage, Small Cost of R100 - R1000 2 Minor effect
Spillage
MEDIUM Competent supervision, Training Certificate, Risk Assessment, Change method,
Safe work procedures, Toolbox talk Mitigate
Noise,Water
4 Med damage,(repair) medium Cost R1000 -5000 4 Serious effect (Short Term) HIGH Competent supervision, Training Certificate, Risk Assessment, Change method,
Dust / Safe work procedures, Toolbox talk Mitigate
Vapors
8 More serious damage/ Loss/ Delay - + R10 000 8 Very serious effect(Long Term) CRITICAL Close competent supervision, Training certificate, Risk Intolerable, Change
Fauna and Assessments, Safe work procedures, PJO, Work Permit, Training, method,Mitigate,
10 Severe damage, Long term stoppage, High costs 10 Catastrophic effect
flora Toolbox talks. Expose risk

ACTIVITY HAZARD RISK Risk Evaluation PREVENTATIVE CONTROL


A B C D R MEASURES
1. Preparation Underground services e.g. Employees may be electrocuted or 10 10 8 8 16 Employees to follow a drawing . risk assessment to be
Fence line to be set out Electricity cables , contact weils disease issued by an engineer/surveyor. communicated to employees
by an engineer or sewer /water pipes Injury to employees.
surveyor. fatality

Approved by Management Prepared by:


Site: UMPHAKATHI MALL PHASE1 REV 1.3
DATE 08/06/202 PAGES 2
Risk Assessment TASK INSTALLATION OF A PERIMETER FENCE
Unaware of hazards and site Employees may get injured or fail to 4 2 2 2 6 All persons entering the site An employer / safety rep to make sure
rules comply with site rules must receive site safety employees have medical fitness
2. Employees arriving on site
induction. certificates, ID copies & passports with
work permits.
Heavy material, sharp edges, Injuries or fractures to employees 4 2 4 4 6 Use of mechanical assistance DSTI / toolbox talk to be communicated
wrong lifting method i.e. back, cut on hands, legs and feet e.g. plant. to employees prior to commence the
3. offloading and handling of etc. Reduce loads by making them task.
material Injury through aggravation of smaller or lighter.
previous/ existing medical condition Ensure that individual is
Placing material to a
lifting correctly, maintains
working area good posture and lifts with
knees bent and kept back
straight.
Using damaged tools or blunt Injury to hands. 10 4 8 8 32 Employees to stick to surveyors DSTI and a Risk assessment to be
bars, buried objects e.g. Fatality may occur due to contact ‘s pegs always communicated.
broken bottles. with underlying services e.g.
Failure to follow surveyor’s electricity cables
4.Digging bars and spades to pegs may lead to tempering
plant post with underlying services
Using unsafe access to reach Buckets can break due to an 4 4 4 4 16 Employees to use ladders instead DSTI/ toolbox talk to be communicated.
5. planting poles and higher positions e.g. climbing excessive weight then employees of buckets.
positioning mesh fence on top of buckets instead of may fall and get injured. Supervisor to monitor
ladders employees
Unsafe drill machine/loose Employees may pinch their fingers 4 8 4 8 7 Only a competent personnel to DSTI to be communicated.
6. fastening mesh /fence against screw socket, blunt screw with a drill, unsafe drill cords may use a hand drill. Portable electrical tools inspector to be
post using screws and a hand point may cause a screw to electrocute employees. Tools to be inspected before use appointed.
drill slipper , exposed wires and unsafe tools must not be
used.
Dust and slashing of Contact with oxide/cement may 4 4 8 8 16 Employees to be issued with PPE to be worn at all times.
concrete/cement cause Dermatitis and or eye damage. overalls, gloves and goggles. DSTI/ Risk assessment to be
7. mixing concrete and pouring Environmental hazard i.e. Inhaling of cement dust may cause communicated.
concrete to support Posts ground pollution. lung infection. Mixing of cement direct Mixing area to be provided.
on the ground must be
avoided
8. Supporting posts using Stays not strong enough to Fence may fall and injure employees 2 2 2 2 2 Employees to make sure they Supervisor to instruct employees.
wooden stays sustain weight use strong stays.
9. Task completion Leaving a work area dirty Tripping hazard. 2 2 2 2 2 Housekeeping to be done on Offcuts/Stays to be taken to storage,

Approved by Management Prepared by:


Site: UMPHAKATHI MALL PHASE1 REV 1.3
DATE 08/06/202 PAGES 2
Risk Assessment TASK INSTALLATION OF A PERIMETER FENCE
i.e. loose material or Employees/clients may get injured. daily basis and after task unused material to be removed from a
unused stays after work is completion working area/site.
Housekeeping.
done and concrete rubble.

METHOD STATEMENT

1. Fence line to be set out by a surveyor


2. Employees arriving on site and receive induction
3. Offloading and handling of material by hands
4. Digging using bars and spades to plant posts
5. Planting posts and positioning mesh/fence
6. Fastening mesh / fence using screws and a hand drill
7. Mixing concrete and pouring concrete to support posts
8. Supporting posts using wooden stays
9. Task completion and housekeeping

Approved by Management Prepared by: