To,

Chief Engineer,

M.G.V.C.L.,

Baroda.

Subject: - Payment & Rates are not as per commitment.

Ref.:- NCD/Tech

Respected Sir,

With respect to above subject, We M/s Devendra Electricals, executed work to erection of HT/LT
Line & TC work at During “Tauktae Cyclone”.

As per discussion & commitment from higher authority i.e. Executive Engineer Nadiad City
Division & others they committed to give 120% Rates as per Line erection Schedule-B, But which is not
committed and Payment made as 100% Rates of schedule-B.

I would like to take action and request to company to fulfill commitment & make payment as
discussed.

Thanks & Regards.