Professional Documents
Culture Documents
3.1. Introduction
This week's emphasis is on scheduling, a key component of project management (PM) along with
planning. The second phase of project management includes scheduling as part of planning, which
includes establishing the project's goals and requirements, as well as estimating costs, scheduling
the activities, and determining the deliverables. Project scheduling fundamentals include critical
path analysis and precedence network analysis.
The work packages of the WBS produce activities (lowest level). In small projects activities are
typically established at the same time as the WBS. A work package is a deliverable that takes more
than one activity to produce it, which is how it differs from an activity.
The following are examples of the most typical logical dependence activities:
1. Finish-to-start (FS), i.e., “a logical relationship in which a successor activity cannot start
until a predecessor activity has finished”.
2. Finish-to-finish (FF), i.e., “a logical relationship in which a successor activity cannot finish
until a predecessor activity has finished”.
3. Start-to-start (SS), i.e., “a logical relationship in which a successor activity cannot start until
a predecessor activity has started”.
4. Start-to-finish (SF), i.e., “a logical relationship in which a successor activity cannot finish
until a predecessor activity has started”.
Each node box in the schedule has the notations ES (Early Start), LS (Late Start), EF (Early
Finish), LF (Late Finish), and DU (DUration of the task). Float is calculated by the equation
Float = Late start – Early start (Float = LS – ES). Total float is the amount of time an activity can
be delayed without delaying the overall project, whereas free float refers to the amount of time an
activity can be delayed without delaying its successor activity(ies).
Solution