Daily Progress Report Jetty South Beach KMT 020423
Daily Progress Report Jetty South Beach KMT 020423
Weather Conditions
Cerah : 07.00 - 13.00 WIT Mendung : 00.00 - 00.00 WIT Hujan : 13.00 - 16.00 WIT
Work
Task Status
Work Permit Done
Pembersihan dan Pembongkaran Ongoing
Pek. Pemasangan dan Pengelasan Rangka Bracing Pipa 6" (28 Joint) Ongoing
Pek. Pengecatan anti karat Ongoing
Crew
Type Name Hours
Supervisor Haris Sutiyono 10,5
Safetyman/Assistant Coordinator Andar Sihombing 10,5
Foreman (Welder) Sonhadi 10,5
Welder Frejon Djelau 10,5
Welder Mustain 10,5
Tukang Yulstastus 10,5
Pengawas Petrogas Gunawan 3
JOB DESCRIPTION QTY UNIT BOBOT PROGRES S/D PROGRES TOTAL (%)
PROGRES HARI INI (%)
KEMARIN (%)
A PEK. PERSIAPAN / PEMBONGKARAN
1 Pembersihan/Pembongkaran 1,00 Ls 5,53 4,86 0,00 4,86
B PEK. BETON / BETON BERTULANG
1 Cor beton Pilecap K-300 31,59 m³ 26,10 26,10 0,00 26,10
2 Pembesian Tulangan Pilecap 734,34 Kg 5,63 5,63 0,00 5,63
C PEK. PLAT LANTAI
1 Cor Plat Lantai K-300 10 cm 18,14 m³ 14,98 5,39 0,15 5,54
2 Pembesian wiremesh Plat Lantai 181,35 m² 18,12 9,24 0,18 9,42
3 Bekisting Plat Lantai Bondex 181,35 m² 11,66 5,95 0,12 6,06
D PEK. STRUKTUR RANGKA JETTY
1 Pek. Pemasangan dan Pengelasan Rangka Bracing Pipa 6" (28 Joint) 110,00 Titik 4,62 3,60 0,05 3,65
2 Pek. Pengecatan anti karat 432,55 m² 13,37 10,16 0,00 10,16
100,00 70,93 0,49 71,43
Equipment
Type Status Hours
Molen mix Onsite 0
Gurinda Onsite 4
Mesin Bor Onsite 0
Mesin Las Onsite 0
Cutting Torch Onsite 0
Mobile Crane Onsite 6
Forklip Onsite 0
Materials
Type Used Remain
Pasir Beton Onsite
Batu Pecah Onsite
Wiremesh Onsite
Bondek Onsite
Besi 8 mm dan 6 mm Onsite
Semen Onsite
Progress Documentation
c. Kendala
- Pengisian Truk tangki SKP 15.00 - 17.00 WIT
- Hujan : 13.00 - 16.00 WIT Foto dokumentasi Foto dokumentasi
- Mobile Crane hanya 6 jam dilapangan