Squeeze Job Risk Assessment( without tool )

Job Type: squeeze Location: Date: NEW Yes REVISED

Country: Client: Contractor: Prepared By:

RISK CONSEQUENCE MITIGATION - REMARKS

1. Hole size determination. Potential Insufficient cement column. Attempt to pump carbide.
2. Cement contamination with mud. Cement plug failure. Pump spacer contain surfactants for oil based mud.
1) Place minimum 60m plug length to allow plug
3. Insufficient plug length Plug contamination. contamination.
2) Perform pre-injection test.
4. No support of cement plug. Resulting in poor plug placement or slumping. Spot a viscous pill as a base or use Cement Support Tool.

1) Test Cl concentraton<500ppm.
2) Thickening time safety margin 60~90min.
5. Cement flash set. Resulting in lost well. 3) Test cement slurries as per temperature given by client
with location water and wellsite chemicals batch number.
4) Follow recipe to prepare mixing water in sequence.

1) Provide lab testing to check compatibility between OBM


6. Incompatibility between OBM and Spacer Flocculation or sludge was formed.
and spacer and cement slurry.
1) Reciprocate(1~3ft) and rotate cement string after cement
come out of string.
7. Squeeze string is stuck. Squeeze failure. And lost well.
2) Control cement column maximum 300m. If workover rig,
maximum 200m.
8. POOH too quick after plug in place. Stripping plug and contamination. Pull tail pipe slowly (30 - 50 ft/min).
9.Residue of cement slurry inside drill pipe. String contaminated with debris. Pull up 100ft above plug and circulate with high rate.

1) wait until cement sample hard(put in water bath with


10. Insufficient WOC. Squeeze failure.
bottom hole temperature).
ueeze Job Risk Assessment( without tool )

MITIGATION - REMARKS

Attempt to pump carbide.


Pump spacer contain surfactants for oil based mud.
1) Place minimum 60m plug length to allow plug
contamination.
2) Perform pre-injection test.
Spot a viscous pill as a base or use Cement Support Tool.

1) Test Cl concentraton<500ppm.
2) Thickening time safety margin 60~90min.
3) Test cement slurries as per temperature given by client
with location water and wellsite chemicals batch number.
4) Follow recipe to prepare mixing water in sequence.

1) Provide lab testing to check compatibility between OBM


and spacer and cement slurry.
1) Reciprocate(1~3ft) and rotate cement string after cement
come out of string.
2) Control cement column maximum 300m. If workover rig,
maximum 200m.
Pull tail pipe slowly (30 - 50 ft/min).
Pull up 100ft above plug and circulate with high rate.

1) wait until cement sample hard(put in water bath with


bottom hole temperature).