Stab-in casing cementing calculation test

1. Basic data
Last casing: 30”, ID=28”, MD=80ft
Current casing: 20”, ID=19.124”, MD=1026ft
Open hole=26”, EOC=75%
Drill pipe: 5”, ID=4.276”
2. Pressure and temperature
Mud weight=9.2ppg
Surface temperature=80℉
Temperature gradient=2.1℉/100ft
BHCT=0.7BHST
3. Slurry report
Slurry weight=13.5ppg
Slurry yield=1.708ft3/sk
mixing water=9.214gal/sk
Fresh water=7.945gps
PC-X61L Defoamer=0.090gps
PC-G71L Fluid loss=1.073gps
PC-P50S Bentonite=2.5%
CaCl2=0.6%
4. Calculation
a) BHST and BHCT, BHP
b) Make slurry test consignment
c) Cement slurry volume(left 2bbl in drill pipe, why?)
d) Displacement
e) Chemical usage
f) Job pressure calculation