You are on page 1of 2

A Computational Fluid Dynamics (CFD) Analysis provides Data Center Managers with a clear

view of how the cooling system in their Data Center is performing. The CFD Analysis also provides
a better understanding of the mechanical systems capability to adequately support a variety of
conditions.
TSS uses the premier Data Center Simulator, 6Sigma™ by Future Facilities, to create a virtual ver-
sion of your data center.

A CFD Analysis allows clients to:

 Gain a better understanding of how to maxim-


ize their existing environment
1. Data Collection – Information related to
 Confirm the actual cooling (and power) limits
the IT & Facility infrastructure can be pro-
well before last-minute corrective measures are
vided by the client or TSS can conduct a
necessary
site survey to collect the required data.
 Plan future deployments around existing cool-
2. Modeling – TSS utilizes the collected data
ing availability to maximize current capacity
to build a model of the existing environ-
 Confirm where and how containment strate- ment. A CFD simulation is then generat-
gies will improve existing performance ed to reflect the existing conditions.
 Estimate the impact of energy efficient im- 3. Evaluation & Assessment – The resulting
provements such as fan speed control, air tem- CFD model is evaluated to identify prob-
perature reset or aisle containment doors lem areas. Suggested options for im-
 Validate the effect of simple performance en- provement can then be simulated in or-
hancements such as blanking panels or floor der to optimize the thermal conditions
and ceiling grille locations within the Data Center.
4. Report – A report with a summary of find-
ings is generated and presented.

Bridging the Gap Between IT and Facilities℠


CFD Modeling can be completed for existing or new facilities TSS creates a CFD model of the existing or new environment

Existing Facility Modeling the Existing Facility


 Inventory of IT Equipment and electrical load data  The collected IT and Facility data is used to build a model of
 Floor Plan of existing area inclusive of IT and mechanical/ existing environment utilizing 6Sigma software.
electrical support equipment  A CFD simulation is generated to reflect the existing thermal
 In environments utilizing raised floor as a plenum, location of conditions within the facility.
under floor distribution elements  The CFD simulation provides a clear understanding of how well
 Specifications of mechanical & electrical support infrastructure the mechanical systems are currently functioning
in the room
Modeling the New Facility
New Facility  The drawings and documentation provided by the client are
 Inventory of IT Equipment and electrical load data used to build a model of the new facility utilizing 6Sigma soft-
 Drawings and Specifications of IT & Facility Infrastructure ware.
 A CFD simulation is generated to reflect the thermal conditions
Data Gathering within new facility.
 Client provided data via as built drawings and other documen-  The CFD simulation provides a clear understanding of how well
tation including inventories, maintenance records, etc the design of the mechanical systems will function
 TSS reviews existing documentation and conducts detailed
survey

Utilizing the simulation model of the existing or proposed new 1. Simulation modeling provides a clear pic-
environment, an assessment is made to identify areas of con-
cern including: hot spots, improper distribution, and lack of re-
ture of temperature distribution at any cho-
dundancy. sen location within the space
Evaluate Current Facility Layout and Systems
 Review mechanical capability and capacity versus IT Load. 2. Provides evaluation of an optimal layout of
 Review physical characteristics impacting distribution. the space to maximize cooling capability
 Evaluate Floor Plan and Equipment Layout
and distribution of IT loads
Evaluate Alternative Performance Issues
 Analysis of future IT load growth 3. Conduct of a What-If analysis without any
 Evaluate different equipment outage scenarios
equipment downtime
Optimize the Thermal Environment
 Insure optimization of existing systems to support the current
environment
4. Enables intelligent decisions as to where ad-
 Develop and optimized model to support future growth and ditional capital expenditures will provide the
reliability requirements best result
Recommended alternatives and Budget
 Based upon the optimized model for the current layout, rec-
ommend modifications with implementation budget
 Provide recommendations with budget to improve reliability
and support future IT requirements.

Leadership in Mission Critical Environments


PLAN. DESIGN. BUILD. INTEGRATE. DEPLOY. MAINTAIN .

You might also like