Professional Documents
Culture Documents
4. The following information is taken from the records of an engineering works in respect of
Job.No.444.
Materials Rs.16,000
Wages :
Department A- 150 hours at Rs.5 per hour
Department B- 120 hours at Rs.4 per hour
Department C- 60 hours at Rs.8 per hour
Work overheads are as follows:
Variable :
Department A- Rs.10,000 for 4000 labour hours
Department B- Rs.6,000 for 3000 labour hours
Department C- Rs.4,000 for 500 labour hours.
Fixed overheads – Rs.20,000 for 10,000 working hours.
Calculate the cost of Job No.444 and what price should be quoted for the job if a profit of
25% on selling price is maintained?
3. A Co. of builders having an authorized capital of Rs.1,00,000 divided into 1,000 ordinary
shares of Rs.100 each, commenced operations on 1st Jan.2022 and during the year was
engaged in a contract, the contract price being Rs.4,00,000. the Trial Balance extracted from
their books on 31st Dec. 2022 stood as follows:
Rs. Rs.
Share Capital being 80% paid up 80,000
Sundry Creditors 8,000
Land & Building at cost 34,000
Cash at bank 9,000
Materials 80,000
Plant 15,000
Wages 1,05,000
Expenses 5,000
Cash received being 80% of work certified _________ 1,60,000
2,48,000 2,48,000
Of the plant and materials charged to the contract, plant costing Rs.2,000 and material costing
Rs.2,000 were destroyed by an accident. On 31st December, 2022 plant which cost Rs.4,000
was returned to store, value of materials on site was Rs.4,000; cost of work done but not
certified was Rs.2,000. Charge depreciation at 10% on plant and carry to Profit and Loss
account 2/3 of profit. Prepare the contract Account for the year 2022 and the Balance Sheet
on 31ts Dec.2022 and show your calculations of the amount to be certified to Profit and Loss
Account.
4. A company of contractors began to trade on 1st January 2021. During 2021 the company was
engaged on only one contract of which the Contract price was Rs.5,00,000.
Of the plant and materials charged to the contract, plant costing Rs.5,000 and materials
costing Rs.4,000 were lost in accident.
On 31st December 2021, plant costing Rs.5,000 was returned to stores cost of work
uncertified, but finished Rs.2,000 and materials costing Rs.4,000 were in hand on site. Charge
10% depreciation on plant. Compile Contract A/c and Balance Sheet from the following:
Rs. Rs.
Share capital 1,20,000
Creditors 10,000
Cash received (80% of work certified) 2,00,000
Land and building 43,000
Bank balance 25,000
Charged to contract:
Materials 90,000
Plant 25,000
Wages 1,40,000
Expenses 7,000 ________
3,30,000 3,30,000
5. The Gujarat Engineering Company Limited has undertaken the construction of a bridge. The
following particulars relate this work for the year ended 31.12.2021.
Rs.
Materials :
Direct purchase 1,00,000
Issued from stores 20,000
Wages 90,000
General plant in use (written down value) 2,00,000
Depreciation thereon 20,000
Direct Expenses 7,000
Share of general overhead 4,000
Materials on hand (31.12.2021) 2,000
Materials lost by fire 1,000
Salvage value thereon 300
Wages accrued (31.12.2021) 10,000
Direct Expenses accrued 1,000
Value of work certified 3, 18,000
Value of uncertified work 9,000
The value of the contract was Rs.4,30,000 and it is a practice of the contractee, as per the
terms of the contract, to retain 10% of the work certified.
From the above particulars prepare the following:-
i) Contract Account
ii) Showing how the items would appear in the Balance Sheet.
Of the plant and materials charged to the contract, plant costing Rs.5,000 and materials
costing Rs.4,000 were lost by an accident. Some part of the materials costing Rs.2,500 were
sold at a profit of Rs.500. On 31-12-2021 plant which cost Rs.3,000 was transferred to
Contract No.761.
On 31-12-2021 the value of work certified was Rs.4,80,000 and 80% of the same was
received in cash. The cost of work done but not certified as on this date was Rs.3,000. Charge
depreciation on plant at 10%. You are required to prepare contract no.777 for the year ended
31-12-2021 by transferring to the profit which you consider reasonable. Also prepare the
balance sheet of the firm.
8. A company of contractors began to trade on 1st Jan. 2021. During the year 2022 it was
engaged on only one contract of which the contract price was Rs.20,00,000.
Of the plant and materials charged to the contract plant costing Rs.20,000 and materials
costing Rs.16,000 were lost in an accident.
On 31st Dec.2022 plant costing Rs.20,000 were returned to stores. Cost of work done but not
certified was Rs..8,000 and materials costing Rs.10,000 were in hand on site. Charge 10%
depreciation on plant and prepare Contract Account and Balance Sheet from the following.
Rs. Rs.
Share capital - 4,80,000
Creditors - 40,000
Cash received (80% of work cerified) - 8,00,000
Land and buildings 1,72,000
Bank Balance 1,00,000
Charged to contract:
Materials 3,20,000
Plant 1,00,000
Wages 5,60,000
Architects fees 10,000
Expenses 58,000 ________
13,20,000 13,20,000
9. The following is the summary of the entries in a contract ledger as on 31st Dec. 2021 in
respect of contract No.666
Rs.
Materials issued from stores 1,00,000
Materials purchased for the contract 90,000
Plant installed at cost 70,000
Wages 2,00,000
Direct Expenses 20,000
Central Office expenses 13,000
Contract price 10,00,000
Work certified 4,80,000
Cash received on contract 3,84,000
Work uncertified 2,000
Additional information:
1. Accruals on 31st Dec.2021 were wages Rs.80,000, direct expenses Rs.5,000.
2. Rs.4,000 worth plant and Rs.3,000 worth of material were destroyed by fire.
3. Some of material costing Rs.4,000 were sold for Rs.5,000.
4. On 31st Dec. 2021 the plant which cost Rs.1,000 was returned to stores. A
part of the plant which cost Rs.400 was damaged rendering itself useless.
5. Charge depreciation on plant at 10% p.a.
Prepare Contract Account and show the entries in the Balance Sheet as on 31 st. Dec. 2021
10. Following is the summary of the entries in a contract ledger as on 31st Dec. 2020 in respect of
contract No.51.
Rs.
Materials bought directly 35,000
Materials issued from stores 7,000
Wages 18,000
Direct expenses 7,000
Establishment Charges 8,000
Plant 34,200
Scrap sold 1,820
Sub Contracts cost 8,180
12. A Contractor secured a contract to supply and erect machinery for the sum of Rs.7,50,000. He
was to receive payments on account from time to time equal to 90% of work certified. He
commenced work on 1st January 2021 and incurred the following expenditure during 2021
Plant and tools Rs. 70,000
Machinery and stores Rs.2,00,000
Wages Rs.1,50,000
Sundry Expenses Rs. 30,000
Establishment Charges Rs. 40,000
A part of machinery costing Rs.20,000 was unsuited to the contract and was sold immediately
at a profit of Rs.5,000. the value of Plant and Tools on 31.12.2021 was Rs.40,000 and the
value of machinery & stores then in hand Rs.30,000 – Cash received was Rs.4,38,750
representing 90% of work certified. In order to calculate the profit made to the contract upto
31.12.2021 the contractor estimated the further expenditure that would be incurred for
completing the contract and took to the credit of Profit & Loss Account for the year that
proportion of estimated profit to be released to the contract which the certified value of work
done bore to contract price. He estimated:
II. That the contract would be completed in a further period of 6 months.
III. That plant and tools would have a residual value of Rs.10,000 upon the completion
of the contract.
IV. That the cost of machinery and stores required in addition to those in stock on
31.12.2021 would be Rs.1,00,000 and that sundry expenses Rs.20,000 would be
incurred.
V. Wages for the 6 months would be Rs.80,000.
VI. Establishment charges would cost the same per month as in the previous year.
VII. That 2 ½% of the total cost of the contract (excluding this %) should be provided for
contingencies.
Prepare Contract A/c. for the year ended 31.12.2021and show your calculation of profit to be
credited to P & L A/c. for the year.
************************************************************