You are on page 1of 8

Project: CONSTRUCTION OF jacuzzi

Location: cavite
Subject: BILL OF QUANTITIES
Client: Mrs. Constant Cordial
Date: April 4, 2023

BILL OF QUANTITIES
ITEM NO. PARTICULARS QTY
I GENERAL REQUIREMENTS
a. Mobilization & Demobilization 1.00
b Temporary Facilities (House Rental) 1.00
c Transportation/Deliveries 1.00
d Supervision 1.00
e Water & Electrical Supply 1.00
SUB-TOTAL FOR GENERAL REQUIREMENTS
II SWIMMING POOL
2,0 1-A Siteworks
a. chipping works 4.30
b. Backfill and Compaction 0.30
c. Gravel Bed 0.80
d Rebar Works 136.00
e Formworks 21.00
f Concrete 3.60
g CHB Laying "4" 24.90
h Water Proofing 21.30
SUB-TOTAL
3.0 1-B Stair and Pathwalk/Pool Deck
a. Rebar 75.00
b Concrete 1.50
SUB-TOTAL
4.0 FINISHES
5-A Plaster
20*120 ceramic tiles wood finished 10.30
5-B Finishes
20x120 ceramic tiles wood finished 26.00
AQUASCAPE SWIMMING POOL ANDConsumables,
FOUNTAIN BUILDERS grout 1 of 8 36.00
Acid Washing 1.00
SUB-TOTAL
5.0 MECHANICAL
6-A Equipment and Accessories
jetflo Pump .75HP 1.00
emaux af100 1.00
cuetas heater 1.00
jetflo air blower 1.00
air control 1.00
hydrojets 4.00
Variflo Valve 1.00
Hydro Stream 3.00
Vacuum Fittings 2.00
Main Drain Cover 1.00
6-B Plumbing Works
Roughing Ins and Complete plumbing system and
accessories including interconnection of existing mains for 1.0
efficient filtration,drainage & water supply
Cleaning accessories consisting of vacuum head, vacuum
1.00
hose, telescopic handle, nylon brush and water test kit

SUB-TOTAL

AQUASCAPE SWIMMING POOL AND FOUNTAIN BUILDERS 2 of 8


6.0 ELECTRICAL
Electrical roughing-ins and Electrical works, PVC conduit,
a. wires and cable including fittings & consumables at 1.0
pumproom
b RGB Lights 1.00
c Transformer 1.00
d Junction Box 1.00
SUB-TOTAL
7.0 Pumproom
a. Construction of Pump Room 1.00
b Painting 32.00
SUB-TOTAL
8.0 TESTING & COMMISSIONING
a. Water Conditioning, Testing, Commissioning 1.0
b. Filling of Water 2,550.00
SUB-TOTAL
SUMMARY:
I GENERAL REQUIREMENTS
II SWIMMING POOL
III STAIR AND PATHWALK/POOL DECK
IV FINISHES
V MECHANICAL
VI ELECTRICAL
VII PUMP ROOM
VIII TESTING COMMISIONING

GRAND TOTAL

TERMS OF PAYMENT:
50% DP balance thru progress billing
WARRANTY:
Ten (10) years on Structural
Five (5) years on Waterproofing

COMPLETION: 35 working days with under normal weather condition.

Prepared: Checked/Noted:

WILLS LORILLA JAIME QUERUBIN


COST
AQUASCAPE SWIMMING ESTIMATE
POOL AND ENGR
FOUNTAIN BUILDERS 3 of 8 General Manager
AQUASCAPE SWIMMING POOL AND FOUNTAIN BUILDERS 4 of 8
ANTITIES
UNIT MATERIAL LABOR UNIT COST TOTAL BID COST

lot 10,000.00 10,000.00 10,000.00


lot 7,000.00 7,000.00 7,000.00
lot 5,000.00 3,000.00 8,000.00 8,000.00
lot 12,000.00 12,000.00 2,000.00
lot - BY THE OWNER
27,000.00

sqm 750.00 750.00 3,225.00


m3 500.00 500.00 150.00
m3 1,500.00 300.00 1,800.00 1,440.00
kg 46.00 15.00 61.00 8,296.00
sq.m. 750.00 350.00 1,100.00 23,100.00
m3 5,200.00 1,500.00 6,700.00 24,120.00
sq.m. 650.00 250.00 900.00 22,410.00
sq.m. 490.00 150.00 640.00 13,632.00
96,373.00

kg 46.00 15.00 61.00 4,575.00


m3 5,200.00 1,500.00 6,700.00 10,050.00
14,625.00

sq.m. 900.00 300.00 1,200.00 12,360.00

sq.m. 1,100.00 300.00 1,400.00 36,400.00


sq.m.
AQUASCAPE 150.00
SWIMMING POOL AND FOUNTAIN BUILDERS 40.00 5 of 8 190.00 6,840.00
lot 1,200.00 600.00 1,800.00 1,800.00
57,400.00

unit 13,000.00 5,000.00 18,000.00 18,000.00


pc 16,000.00 3,000.00 19,000.00 19,000.00
unit 28,000.00 3,500.00 31,500.00 31,500.00
unit 17,000.00 2,500.00 19,500.00 19,500.00
unit 3,500.00 900.00 4,400.00 4,400.00
pcs 2,500.00 900.00 3,400.00 13,600.00
pc 11,100.00 2,500.00 13,600.00 13,600.00
sets 520.00 150.00 670.00 2,010.00
sets 490.00 150.00 640.00 1,280.00
set 2,100.00 150.00 2,250.00 2,250.00

lot 11,300.00 4,500.00 15,800.00 15,800.00

set 11,200.00 2,500.00 13,700.00 13,700.00

154,640.00

AQUASCAPE SWIMMING POOL AND FOUNTAIN BUILDERS 6 of 8


lot 5,000.00 1,500.00 6,500.00 6,500.00

sets 9,500.00 1,500.00 11,000.00 11,000.00


unit 2,200.00 750.00 2,950.00 2,950.00
pcs 480.00 150.00 630.00 630.00
21,080.00

lot 11,000.00 3,500.00 14,500.00 14,500.00


sqm 110.00 40.00 150.00 4,800.00
19,300.00

lot 1,500.00 1,500.00 1,500.00


gals. 0.50 0.50 by owner
1,500.00

27,000.00
96,373.00
14,625.00
57,400.00
154,640.00
21,080.00
19,300.00
1,500.00

391,918.00

Six (6) months on Electromechanical Equipment


One (1) year on Finishes

UBIN
agerAQUASCAPE SWIMMING POOL AND FOUNTAIN BUILDERS 7 of 8
AQUASCAPE SWIMMING POOL AND FOUNTAIN BUILDERS 8 of 8