506(1) Stone Masonry (Head Wall & Catch Basin) 57.40 cu.m. See Summary 0 0
612(1) Reflectorized Thermoplastic Pavement Markings White 460.00 sq.m. Inspection Report 1 1 0 1 0
SUMMARY OF TEST
a Cement 30620.00 bags Quality Test 16 1 15 16 0
b Sand (Item 404) 312.00 cu.m. Grading 1 0 1 1 0
Specific Gravity 1 0 1 1 0
Absorption 1 0 1 1 0
Unit Weight 1 0 1 1 0
Mortar Strength 1 0 1 1 0
c Sand (Item 311) 1,571.00 cu.m. Grading 21 1 20 21 0
Specific Gravity 1 1 1 0
Absorption 1 1 1 0
Unit Weight 1 1 1 0
Mortar Strength 1 1 1 0
d Gravel, 3/4" 189.50 cu.m. Grading 1 0 1 1 0
Specific Gravity 1 0 1 1 0
Absorption 1 0 1 1 0
Unit Weight 1 0 1 1 0
Abrasion 1 0 1 1 0
e Gravel, G-1 3,141.50 cu.m. Grading 42 1 41 42 0
Specific Gravity 3 1 2 3 0
Absorption 3 1 2 3 0
Unit Weight 3 1 2 3 0
Abrasion 3 1 2 3 0
f. 10mmØ x 6 m DSB 6,855.96 kgs. Quality Test 1 1 1 0
g. 12mmØ x 6 m DSB 6,675.00 kgs. Quality Test 1 1 1 0
h. 16mmØ x 6 m DSB 2,531.16 kgs. Quality Test 1 1 1 0
i 25mmØ x 6 m DSB 972.22 kgs. Quality Test 1 1 1 0
j. Embankment 1,232.00 cu.m. Grading 1 0 1 1 0
Liquid Limit 1 0 1 1 0
Plastic Limit 1 0 1 1 0
Compaction 1 0 1 1 0
FDT 12 12 12 0
l. Subgrade Preparation 12,095.00 sq.m. Grading 3 1 2 3 0
Liquid Limit 3 1 2 3 0
Plastic Limit 3 1 2 3 0
Compaction 3 1 2 3 0
FDT 25 25 0 25 0
m. Aggregate Subbase Course 4,928.00 cu.m. Grading 17 1 16 17 0
Liquid Limit 17 1 16 17 0
Plastic Limit 17 1 16 17 0
Compaction 4 1 3 4 0
Abrasion 4 1 3 4 0
CBR 2 0 2 2 0
FDT 50 36 14 50 0
INSPECTION: TOTAL 358 119 239 358 0
Continuous Quality Control Inspection on all Items of work should be done as construction of work progresss. Inspection Report to be submitted as required
Total No. of Test 119 239 Total Bal. 0
% Accomplish 33.24% 66.76% % Balance 0.00%
Materials Engineer
Materials Engineer Assigned Resident Engineer
Provincial Engineers Office Provincial Engineers Office