OWNER: MR. AND MRS.

NORJANAH ESCANDER
PROJECT NAME: TWO STOREY RESIDENTIAL BUILDING
PROJECT LOCATION: FUENTE DE VILLA-ABRILLE SUBD., MATINA, DAVAO CITY
SUBJECT: BILL OF MATERIALS (BUILDING)

UNIT COST AMOUNT TOTAL


ITEMS OF WORK UNIT Materials Labor Materials Labor AMOUNT
1 GENERAL REQUIREMENTS
a Mobilization/Demobilization / lot 1.00 60,000.00 10,000.00 60,000.00 10,000.00 70,000.00
Temprorary Facilities /
Processing of (DLPC & DCWD) /
Utilities (DLPC & DCWD)
b Processing of Occupancy Permit lot 1.00 15,000.00 15,000.00 - 15,000.00
75,000.00 10,000.00 85,000.00
2 SITEWORKS
a Batterboard & Lay-out lot 1.00 2,500.00 2,500.00 2,500.00 2,500.00 5,000.00
b Excavation cum 30.00 350.00 - 10,500.00 10,500.00
c Backfill & compaction cum. 30.00 500.00 350.00 15,000.00 10,500.00 25,500.00
d Disposal of waste lot 1.00 5,000.00 5,000.00 5,000.00 5,000.00 10,000.00
e Gravel Bedding cum 10.00 1,000.00 400.00 10,000.00 4,000.00 14,000.00
32,500.00 32,500.00 65,000.00

3 STRUCTURAL WORKS
3 Footing / Column cum 25.00 2,000.00 - 50,000.00 50,000.00
Cement bags 175.00 250.00 43,750.00 - 43,750.00
Sand cum 25.00 800.00 20,000.00 - 20,000.00
Gravel cum 25.00 1,000.00 25,000.00 - 25,000.00
16mm rebars kgs 1,514.88 42.25 16.90 64,003.68 25,601.47 89,605.15
10mm rebars kgs 1,110.60 42.25 16.90 46,922.85 18,769.14 65,691.99
Tie wire kgs 50.00 60.00 3,000.00 - 3,000.00
- - -
3 Roof beam cum 6.00 2,000.00 - 12,000.00 12,000.00
Cement bags 50.00 250.00 12,500.00 - 12,500.00
Sand cum 6.00 800.00 4,800.00 - 4,800.00
Gravel cum 6.00 1,000.00 6,000.00 - 6,000.00
12mm rebars kgs 266.40 42.25 16.90 11,255.40 4,502.16 15,757.56
10mm rebars kgs 370.20 42.25 16.90 15,640.95 6,256.38 21,897.33
Tie wire kgs 25.00 60.00 1,500.00 - 1,500.00
- - -
3 Slab & Beam cum 25.00 2,000.00 - 50,000.00 50,000.00
Cement bags 200.00 250.00 50,000.00 - 50,000.00
Sand cum 25.00 800.00 20,000.00 - 20,000.00
Gravel cum 25.00 1,000.00 25,000.00 - 25,000.00
16mm rebars kgs 1,420.20 42.25 16.90 60,003.45 24,001.38 84,004.83
10mm rebars kgs 1,851.00 42.25 16.90 78,204.75 31,281.90 109,486.65
Tie wire kgs 75.00 60.00 4,500.00 - 4,500.00

3 Slab on fill cum 15.00 2,000.00 - 30,000.00 30,000.00


Cement bags 150.00 250.00 37,500.00 - 37,500.00
Sand cum 15.00 800.00 12,000.00 - 12,000.00
Gravel cum 15.00 1,000.00 15,000.00 - 15,000.00
10mm rebars lgths 370.20 42.25 16.90 15,640.95 6,256.38 21,897.33
Tie wire kgs 25.00 60.00 1,500.00 - 1,500.00
- - -
573,722.03 258,668.81 832,390.84
4 FORMWORKS AND SCAFFOLDS
a Columns / Roof beam sq.m. 100.00 350.00 - 35,000.00 35,000.00
b 1/2" Ord. Plywood sheets 30.00 600.00 240.00 18,000.00 7,200.00 25,200.00
c Phenolic Board sheets 30.00 1,750.00 700.00 52,500.00 21,000.00 73,500.00
d Coco Lumber 2x2x12 lgths 400.00 80.00 32.00 32,000.00 12,800.00 44,800.00
e Coco Lumber 2x3x12 lgths 400.00 120.00 48.00 48,000.00 19,200.00 67,200.00
f CW Nails lot 1.00 10,000.00 10,000.00 - 10,000.00
160,500.00 95,200.00 255,700.00
5 MASONRY WORKS
5 CHB 4" Piling (Walls & Fence) sqm 500.00 200.00 - 100,000.00 100,000.00
CHB 4 pcs 6,000.00 12.00 72,000.00 - 72,000.00
Cement bags 250.00 250.00 62,500.00 - 62,500.00
Sand cum 20.00 800.00 16,000.00 - 16,000.00
10mm dia. RSB kgs 1,110.60 42.25 16.90 46,922.85 18,769.14 65,691.99
Tie Wire kgs 25.00 60.00 1,500.00 - 1,500.00

5 Plastering (Wall) sqm 750.00 200.00 - 150,000.00 150,000.00


5 Plastering (window edges) unit 50.00 100.00 - 5,000.00 5,000.00
Plastering (design / grooves / mouldings) lm 50.00 100.00 - 5,000.00 5,000.00
Cement bags 400.00 250.00 100,000.00 - 100,000.00
Sand cum 25.00 800.00 20,000.00 - 20,000.00
- - -
5.1 Septic Tank sqm 20.00 150.00 - 3,000.00 3,000.00
CHB 4 pcs 400.00 12.00 4,800.00 - 4,800.00
Cement bags 30.00 250.00 7,500.00 - 7,500.00
Sand cum 2.00 800.00 1,600.00 - 1,600.00
Gravel cum 3.00 800.00 2,400.00 - 2,400.00
12mm rebars kgs 133.20 42.25 16.90 5,627.70 2,251.08 7,878.78
10mm dia. RSB kgs 92.55 42.25 16.90 3,910.24 1,564.10 5,474.33
Tie Wire kgs 10.00 60.00 600.00 - 600.00
Plastering (Interior Wall) sqm 20.00 150.00 - 3,000.00 3,000.00
Cement bags 20.00 250.00 5,000.00 - 5,000.00
Sand cum 1.00 800.00 800.00 - 800.00
351,160.79 288,584.32 639,745.10
6 CARPENTRY WORKS / CEILING WORKS
CEILING WORK sqm 200.00 400.00 - 80,000.00 80,000.00
Ficem Board 3.5mm sqm 288.00 135.00 54.00 38,880.00 15,552.00 54,432.00
C-Channel Metal frames x 5m lgths 150.00 110.00 44.00 16,500.00 6,600.00 23,100.00
G-furring Metal frames x 5m lgths 250.00 110.00 44.00 27,500.00 11,000.00 38,500.00
Wall Angle Metal frames x 3m lgths 150.00 50.00 20.00 7,500.00 3,000.00 10,500.00
W-Clip sq.m 500.00 5.00 2.00 2,500.00 1,000.00 3,500.00
Consummables lot 1.00 5,000.00 2,000.00 5,000.00 2,000.00 7,000.00
MOULDINGS / CARPENTRY - - -
Cornice moulding x 8ft lgths 75.00 150.00 100.00 11,250.00 7,500.00 18,750.00
Baseboard moulding x 8ft lgths 75.00 150.00 100.00 11,250.00 7,500.00 18,750.00
Consummables lot 1.00 5,000.00 2,000.00 5,000.00 2,000.00 7,000.00
Closets units 5.00 25,000.00 5,000.00 125,000.00 25,000.00 150,000.00
250,380.00 161,152.00 411,532.00
7 PAINTING WORKS
Painting (Exterior wall) sqm 375.00 300.00 300.00 112,500.00 112,500.00 225,000.00
Painting (Interior wall) sqm 400.00 300.00 300.00 120,000.00 120,000.00 240,000.00
Painting (Ceiling) sqm 200.00 300.00 300.00 60,000.00 60,000.00 120,000.00
Painting (Doors - stained & varnished)) units 10.00 1,000.00 625.00 10,000.00 6,250.00 16,250.00
302,500.00 298,750.00 601,250.00
8 TILE WORKS
Kitchen, Dining, Living sqm 80.00 850.00 200.00 68,000.00 16,000.00 84,000.00
Tiles 60cm x 60cm - - -
Carport, laundry, maids room, entry porch sqm 40.00 750.00 200.00 30,000.00 8,000.00 38,000.00
Tiles 30cm x 30cm - - -
Toilet & Bath sqm 110.00 750.00 200.00 82,500.00 22,000.00 104,500.00
Tiles 30cm x 60cm Wall - - -
Tiles 30cm x 30cm Floor - - -
Bedrooms, family hall sqm 120.00 850.00 200.00 102,000.00 24,000.00 126,000.00
Tiles 60cm x 60cm - - -

Cement bags 60.00 250.00 15,000.00 - 15,000.00


Sand cum 6.00 800.00 4,800.00 - 4,800.00
Adhesives bags 145.00 250.00 36,250.00 - 36,250.00
Consummables lot 1.00 5,000.00 5,000.00 - 5,000.00

Pathwalk / lanai pcs 3,100.00 15.00 15.00 46,500.00 46,500.00 93,000.00


Paving Blocks 3"x 6" x 2" - - -
Sand cum 3.00 800.00 2,400.00 - 2,400.00
- - -
Balcony (60x60 non skid) sqm 25.00 850.00 200.00 21,250.00 5,000.00 26,250.00
Adhesives bags 12.00 250.00 3,000.00 - 3,000.00

Exterior accent stone sqm 25.00 1,500.00 500.00 37,500.00 12,500.00 50,000.00
Adhesives bags 12.00 250.00 3,000.00 - 3,000.00
Consummables lot 1.00 5,000.00 5,000.00 - 5,000.00
462,200.00 134,000.00 596,200.00
9 DOORS, WINDOWS & ACCESSORIES
DOORS & ACCESSORIES
Main Door (Hardwood) 0.90m x 2.10m unit 1.00 10,000.00 4,000.00 10,000.00 4,000.00 14,000.00
Panel Door 0.80m x 2.10m units 4.00 5,000.00 2,000.00 20,000.00 8,000.00 28,000.00
Aluminum Door 0.80m x 2.10m units 4.00 4,000.00 1,600.00 16,000.00 6,400.00 22,400.00
Sliding Glass Door 1.60m x 2.10m units 5.00 15,000.00 6,000.00 75,000.00 30,000.00 105,000.00
Grilles Door units 2.00 2,000.00 800.00 4,000.00 1,600.00 5,600.00
Steel Jamb units 5.00 2,000.00 800.00 10,000.00 4,000.00 14,000.00
Door Knob @ Aluminum Door sets 4.00 1,000.00 400.00 4,000.00 1,600.00 5,600.00
Door Knob @ Sliding Door sets 5.00 1,000.00 400.00 5,000.00 2,000.00 7,000.00
Door Knob @ Panel Door sets 4.00 1,000.00 400.00 4,000.00 1,600.00 5,600.00
Door Knob @ Main Door sets 1.00 5,000.00 2,000.00 5,000.00 2,000.00 7,000.00
Hinges pcs 15.00 100.00 40.00 1,500.00 600.00 2,100.00
Screen Door (Main and exit door) unit 2.00 7,500.00 3,000.00 15,000.00 6,000.00 21,000.00
WINDOWS WITH GRILLES & SCREEN
W1 1.20m x 1.60m (Aluminum) set 1.00 15,000.00 7,500.00 15,000.00 7,500.00 22,500.00
W2 1.00m x 1.60m (Aluminum) sets 4.00 10,000.00 5,000.00 40,000.00 20,000.00 60,000.00
W3 0.80m x 1.60m (Aluminum) sets 2.00 7,500.00 3,750.00 15,000.00 7,500.00 22,500.00
W4 0.70m x 1.20m (Aluminum) sets 6.00 7,500.00 3,750.00 45,000.00 22,500.00 67,500.00
W5 0.50m x 1.20m (Aluminum) set 1.00 7,500.00 3,750.00 7,500.00 3,750.00 11,250.00
W6 0.85m x 1.50m (Aluminum) set 1.00 7,000.00 3,500.00 7,000.00 3,500.00 10,500.00
W7 0.60m x 1.60m (Aluminum) sets 4.00 7,000.00 3,500.00 28,000.00 14,000.00 42,000.00
W8 0.50m x 0.50m (Aluminum) sets 5.00 4,000.00 2,000.00 20,000.00 10,000.00 30,000.00
W9 0.30m x 0.50m (Aluminum) set 1.00 4,000.00 2,000.00 4,000.00 2,000.00 6,000.00
351,000.00 158,550.00 509,550.00

10 PLUMBING WORKS
ROUGHING INS
PPR 1/2" lgths 30.00 300.00 125.00 9,000.00 3,750.00 12,750.00
PPR Fittings lot 1.00 2,500.00 1,000.00 2,500.00 1,000.00 3,500.00
PVC Pipe s.1000 4" s1000 lgths 50.00 650.00 260.00 32,500.00 13,000.00 45,500.00
PVC Pipe s.1000 2" s1000 lgths 30.00 350.00 140.00 10,500.00 4,200.00 14,700.00
PVC Pipe Fittings lot 1.00 8,500.00 3,400.00 8,500.00 3,400.00 11,900.00
Consummables lot 1.00 5,000.00 2,000.00 5,000.00 2,000.00 7,000.00
FIXTURES
Watercloset & Lavatory set (Semi-elegant) sets 3.00 15,000.00 6,000.00 45,000.00 18,000.00 63,000.00
Watercloset & Lavatory set (Ordinary) set 1.00 10,000.00 4,000.00 10,000.00 4,000.00 14,000.00
Shower with Faucet (Semi-elegant) sets 3.00 6,500.00 2,600.00 19,500.00 7,800.00 27,300.00
Shower with Faucet (Ordinary) set 1.00 6,500.00 2,600.00 6,500.00 2,600.00 9,100.00
Bedit pcs 3.00 1,000.00 400.00 3,000.00 1,200.00 4,200.00
Floor Drain pcs 8.00 500.00 200.00 4,000.00 1,600.00 5,600.00
Lavatory Faucet (Semi-elegant) sets 3.00 1,500.00 600.00 4,500.00 1,800.00 6,300.00
Lavatory Faucet (Ordinary) set 1.00 500.00 200.00 500.00 200.00 700.00
Kitchen sink (Single) set 1.00 5,000.00 2,000.00 5,000.00 2,000.00 7,000.00
Kitchen sink (Double) set 1.00 10,000.00 4,000.00 10,000.00 4,000.00 14,000.00
Hose Bib sets 4.00 500.00 200.00 2,000.00 800.00 2,800.00
Consummables lot 1.00 10,000.00 4,000.00 10,000.00 4,000.00 14,000.00
Water tank (rainwater) lot 1.00 15,000.00 6,000.00 15,000.00 6,000.00 21,000.00
Catch Basin units 10.00 1,500.00 200.00 15,000.00 2,000.00 17,000.00
218,000.00 83,350.00 301,350.00
11 ELECTRICAL WORKS
Pinlights 4" dia. With 7W LED Bulb sets 35.00 500.00 200.00 17,500.00 7,000.00 24,500.00
Minipinlights 2.5" dia. With Bulb sets 6.00 350.00 140.00 2,100.00 840.00 2,940.00
Spotlight 10W LED Bulb sets 3.00 2,500.00 1,000.00 7,500.00 3,000.00 10,500.00
Droplights with 5W LED Bulb sets 5.00 2,500.00 1,000.00 12,500.00 5,000.00 17,500.00
Post Lamp 10W LED Bulb sets 6.00 1,500.00 600.00 9,000.00 3,600.00 12,600.00
Wall Lamp 10W LED Bulb sets 5.00 1,500.00 600.00 7,500.00 3,000.00 10,500.00
Switch 1G pcs 10.00 100.00 40.00 1,000.00 400.00 1,400.00
Switch 2G pcs 10.00 150.00 60.00 1,500.00 600.00 2,100.00
Switch 3G pcs 15.00 200.00 80.00 3,000.00 1,200.00 4,200.00
Convenience outlet pcs 30.00 200.00 80.00 6,000.00 2,400.00 8,400.00
Aircon Outlet pcs 5.00 300.00 120.00 1,500.00 600.00 2,100.00
Telephone Outlet pc 1.00 300.00 120.00 300.00 120.00 420.00
Cable Outlet pc 1.00 300.00 120.00 300.00 120.00 420.00
THHN Wire 2.0mm2 rolls 5.00 2,000.00 800.00 10,000.00 4,000.00 14,000.00
THHN Wire 3.5mm2 rolls 5.00 3,500.00 1,400.00 17,500.00 7,000.00 24,500.00
THHN Wire 5.5mm2 rolls 2.00 5,500.00 2,200.00 11,000.00 4,400.00 15,400.00
Telephone Wire m 100.00 25.00 10.00 2,500.00 1,000.00 3,500.00
Cable Wire m 100.00 25.00 10.00 2,500.00 1,000.00 3,500.00
PVC Pipe 1/2 lgths 100.00 75.00 30.00 7,500.00 3,000.00 10,500.00
PVC Pipe 3/4 lgths 30.00 100.00 40.00 3,000.00 1,200.00 4,200.00
PVC Pipe 1 lgths 30.00 150.00 60.00 4,500.00 1,800.00 6,300.00
Mouldflex 1/2 rolls 5.00 1,000.00 400.00 5,000.00 2,000.00 7,000.00
Fittings lot 1.00 5,000.00 2,000.00 5,000.00 2,000.00 7,000.00
Utility Box pcs 50.00 30.00 12.00 1,500.00 600.00 2,100.00
Junction Box pcs 75.00 30.00 12.00 2,250.00 900.00 3,150.00
Electrical Tape pcs 10.00 50.00 20.00 500.00 200.00 700.00
Panel Board 16 branches unit 1.00 10,000.00 4,000.00 10,000.00 4,000.00 14,000.00
Breaker 60A pcs 1.00 500.00 200.00 500.00 200.00 700.00
Breaker 30A pcs 10.00 500.00 200.00 5,000.00 2,000.00 7,000.00
Breaker 20A pcs 5.00 500.00 200.00 2,500.00 1,000.00 3,500.00
Service Entrance lot 1.00 5,000.00 2,000.00 5,000.00 2,000.00 7,000.00
Entrada wire m 100.00 100.00 40.00 10,000.00 4,000.00 14,000.00
Consummables lot 1.00 5,000.00 2,000.00 5,000.00 2,000.00 7,000.00
180,450.00 72,180.00 252,630.00
12 KITCHEN CABINETS
a Kitchen Cabinets (Upper) lot 1.00 100,000.00 5,000.00 100,000.00 5,000.00 105,000.00
b Kitchen Cabinets (Lower) lot 1.00 100,000.00 5,000.00 100,000.00 5,000.00 105,000.00
c Consummables lot 1.00 5,000.00 5,000.00 5,000.00 5,000.00 10,000.00
d Granite slab lot 3.00 15,000.00 5,000.00 45,000.00 15,000.00 60,000.00
e Backsplash tiles lot 1.00 10,000.00 5,000.00 10,000.00 5,000.00 15,000.00
260,000.00 35,000.00 295,000.00

13 STEEL WORKS AND ROOFING


C-purlins 2x4x1.5mm lgths 60.00 450.00 225.00 27,000.00 13,500.00 40,500.00
C-purlins 2x3x1.5mm lgths 60.00 350.00 175.00 21,000.00 10,500.00 31,500.00
Tubular 2x3x1.5mm (Balcony) lgths 30.00 1,000.00 500.00 30,000.00 15,000.00 45,000.00
Tubular 2x2x1.5mm (Balcony) lgths 30.00 750.00 375.00 22,500.00 11,250.00 33,750.00
Tubular 1x1x1.5mm (Balcony) lgths 25.00 500.00 250.00 12,500.00 6,250.00 18,750.00
Flat Bar 2 x 1/4 (Stairs) lgths 5.00 500.00 250.00 2,500.00 1,250.00 3,750.00
Welding Rod kilos 60.00 150.00 75.00 9,000.00 4,500.00 13,500.00
Consummables lot 1.00 5,000.00 2,500.00 5,000.00 2,500.00 7,500.00
Paints lot 1.00 5,000.00 2,500.00 5,000.00 2,500.00 7,500.00
Roofing Rib type Roof GI Sheets lot 1.00 150,000.00 50,000.00 150,000.00 50,000.00 200,000.00
Insulation lot 1.00 10,000.00 5,000.00 10,000.00 5,000.00 15,000.00
Spandrel for Eaves lot 1.00 50,000.00 20,000.00 50,000.00 20,000.00 70,000.00
344,500.00 142,250.00 486,750.00

TOTAL PROJECT COST 3,561,912.82 1,770,185.13 5,332,097.94


Supervision / Contingency / Hauling of materials 5% 266,604.90
LESS: DESIGN SERVICE FEE 85,000.00
CONTRACT PRICE 5,513,702.84
lOMoARcPSD|24891340

Project Title: 2-STOREY RESIDENTIAL BUILDING


Proposed by: LOVENIA TRISHA G CASI ÑO
Location: BLOOMFIELDS CAGAYAN DE ORO CITY
Owner: ARCH’T. JOEL C. ENQUITO

SPECIFICATION
This set of Specifications shall administer the methods of construction
as well as the kinds of materials to be used for the proposed building shown
in the plans and detailed drawings.
The plans, detailed drawings and these Specifications shall be
complementing each other so that what is shown in one, although not shown
in the other, shall be considered as appearing on both.

GENERAL CONDITIONS
All parts of the construction shall be finished with first class
workmanship to the fullest extent of the meaning of plans and specification.
These specifications are intended to cover the construction of the proposed
Two-Storey Residential Building as shown on the plans and described in
these specifications.
The construction shall conform to all the requirements of the National
Building Code, as well as the local rules and regulations of the
Municipality/City of Cagayan de Oro, Philippines.

A. DIVISION 1 – GENERAL REQUIREMENTS

The contractor shall be responsible for securing all necessary


permits related to the project, which shall include but not limited to
building permits, occupancy permit, and etc.), Contractor’s All Risk
Insurance & Third Party Liability and Workman’s Compensation
Insurance (CARI), and other insurances required by the Local
Government Unit (LGU) and Eton Cyberpod Centris (ECC), among
others, including payment of assessed fees as may be required by the
LGU, ECC and/or Regulating Agencies before the implementation of the
project. All related documents shall be submitted to the PPP Center.
B. DIVISION 2 - SITE WORK

Downloaded by JEAN-YVES TRONCO (j.tronco.485390@umindanao.edu.ph)


lOMoARcPSD|24891340

1.0 CLEARING THE SITE


The building site shall be leveled according to the plans and
cleared of rubbish, roots and other perishable and objectionable
matters to a suitable subgrade.

2.0 STAKING OUT THE BUILDING LINES


The building lines shall be staked out and all lines and grades
shown in the drawing established before any execution is started.
Batter boards and reference marks shall be erected at such places
where they will not be disturbed during the construction of the
excavation.

3.0 EXCAVATION AND LEVELLING


Excavation shall be to the depths indicated bearings values.
Excavations for footings and foundations carried below required depths
shall be filled with concrete and bottom of such shall be leveled. Where
excavation for footings rest on fill, excavation shall be carried deeper
until the desired stratum is reached for safe bearing capacity of soil.
Whenever water is encountered in the excavation process it shall
be remove by paling or pumping. Care being taken that the surround
particles of soil are not disturbed or removed.

4.0 FILLING AND BACKFILLING


Backfill shall be placed in layers not exceeding six (6) inches in
thickness, each Layer being thoroughly wetted and compacted by
tamping or rolling. The top two (2) inches of backfill shall consist of
sand under gravel and other approved materials thoroughly compacted
by wetting and compacting. Backfill may only be done after forms have
been removed from footings, piers, foundation walls and hen concrete
is hard enough to resist pressure resulting from filling.

Downloaded by JEAN-YVES TRONCO (j.tronco.485390@umindanao.edu.ph)


lOMoARcPSD|24891340

C. DIVISION 3 - CONCRETE

1.0 CONCRETE WORKS


All concrete shall be mixed thoroughly until there is a uniform
distribution of cement and aggregates, and should be deposited as
nearly as practicable in its final position, being taken to avoid
segregation of the aggregates.
Water to be used for mixing shall be clean and free from
injurious amount of oil, acids, alkalis, salt and other organic
materials
All concrete shall be mixed thoroughly until there is a uniform
distribution of cement and aggregates, and should be deposited as
nearly as practicable in its final position, being taken to avoid
segregation of the aggregates.
Water to be used for mixing shall be clean and free from
injurious amount of oil, acids, alkalis, salt and other organic materials.
Proportioning of Concrete
All concrete works shall be done in accordance with the standard
specifications for plain and reinforced concrete as adopted by the
government. Cement to be used shall be HOLCIM Portland cement,
pozzolan cement or any other equivalent brands more readily available
in the locality. Alternative cements so selected must meet the
requirements of Portland and pozzolan cements, and approved by the
Architect or Engineer in charge of the construction

CLASS A.: 1:2:4 - for columns, beams, footings and tie


beams.
CLASS B.: 1:2:5:5 - for walks, driveways, hollow blocks
mortar, filler and plastering.
CLASS C.: 1:3:6 - for floor and slabs on fill.

Cement for the concrete shall conform to the requirement and


specifications for Portland cement. Before concrete is placed embedded
items shall have been inspected and tested, cleared and graded
washed gravel and sand for all concrete work. Portland cement shall be
Republic, Northern, Atlas or its equivalent.

Downloaded by JEAN-YVES TRONCO (j.tronco.485390@umindanao.edu.ph)


lOMoARcPSD|24891340

Class A concrete shall be a mixture of 1 part cement, 2 parts fine


aggregate and 4 parts coarse aggregate by volume, plus enough clean
water to make the mixture into a pliable paste.
Class B concrete shall be a mixture of 1 part cement, 2-1/2 parts
fine aggregate and 5 parts of coarse aggregate by a volume, plus
enough clean water to make the mixture into a pliable paste.
Class C concrete shall be a mixture of 1 part of cement, 3 parts
fine aggregate and 6 parts coarse aggregate by volume, plus enough
clean water to make the mixture into a pliable paste.
The fine aggregate for concrete shall consist of natural sand, or
inert materials with similar characteristics having clean, hard and
durable grains , free from organic matter or loam.
Coarse aggregate for concrete shall consist of crushed rock of
durable and strong qualities, or clean and hard gravel. Size of the
coarse aggregate to be used shall vary from 20mm to 40mm (3/4” to
1-1/2”),

2.0 REINFORCEMENT

• 16 mm diameter deformed bar


- to be used for beams, column reinforcement, and
footing reinforcement as well as for footing tie beam

• 12 mm diameter deformed bar


- To be used for beam mid span (top bars)

• 10 mm diameter deformed bar


- to be used for beams stirrups and lateral ties

• # 16 G.I Wire
- To be used for all steel bar intersections

Reinforcing steel bar shall conform to fire resistive requirements


of the ASTM Standard best known for building practices.

Downloaded by JEAN-YVES TRONCO (j.tronco.485390@umindanao.edu.ph)


lOMoARcPSD|24891340

D. DIVISION 4 - MASONRY

6 x 8 16 CHB - to be used for all lower and upper exterior walls.


4 x 8 16 CHB - to be used for all interior walls.

All exterior concrete hollow blocks to be used for exterior floor


walls shall be at least 150mm thick while the concrete hollow blocks
for interior walls unless otherwise indicated shall be 100mm thick. For
interior walls where plumbing pipes and fittings shall be located, the
thickness shall be at least 150 mm.

The concrete hollow block walls shall be laid, and the cells filled
with the cement mortar consisting 1 part of Portland cement and 3
parts sand by volume. They shall be reinforced with round deformed
bars with 10mm diameter, spaced not more than 0.80 on centers, both
ways.

All exposed surfaces of concrete hollow block walls shall be


finished with the specified materials indicated on the elevation
drawings.

The mixture of cement plaster for concrete hollow block wall


finished indicated in the drawing shall be 1 part cement, 1 part time
and 3 parts sand.

• CARPENTRY AND JOINERY WORK

Lumber shall be the approved quality of the respective kinds of


various parts of the work, well-seasoned, thoroughly dry and free from
large, loose or unsound knots, shakes and other imperfections shall be
coated with creosote or equivalent.
TANGUILE - for all exposed wood works such as door jambs, frames,
joists and cabinets.
APITONG - for all unexposed lumber for framings.
¼ THK HARDIFLEX BOARD - to be used for all types of ceiling finishes
including bathroom and toilets.
3/8 THK PLYWOOD - to be used for all formworks.
2x4x10 COCO LUMBER - for scaffoldings.

Downloaded by JEAN-YVES TRONCO (j.tronco.485390@umindanao.edu.ph)


lOMoARcPSD|24891340

3.0 REMOVAL OF FORMS


SUSPENDED SLABS - 21 DAYS
BEAMS - 21 DAYS
COLUMNS AND WALLS - 2 DAYS
FOUNDATIONS - 2 DAYS

E. DIVISION 5 - METALS

1.0 Stainless Steel


• For balcony and terrace railings, use 1.5mm thick 4” x 4” x
20’ tubular steel and install stated on the building document
and space 0.05m each tubular steel.
• For balusters, use use 1.50mm thick 2”x3”x20’ tubular steel
and place horizontally space 0.10m and the vertical is 0.90 in
height space 1.50m.
• For the roof support, the roof frame to use is 1.20mm thick
2”x6” C-Channel, 1.20mm thick 2”x4”’ C-Channel web
member, 1.20 mm thick 2”x4” C-Channel purlins.
• In forming the roof support the roof frame use 1.20mm thick
2”x6” C-Channel, 1.20mm thick 2”x4”’ C-Channel web
member, 1.20 mm thick 2”x4” C-Channel purlins.

F. DIVISION 6 – WOODS AND PLASTICS

1.0 For the ceiling material, use 4”x8”x1/4” Hardieflex. The


hardieflex is being hang by 10mm hanging rod to prevent and
hold any movement of the ceiling due to pressure. The ceiling in
ground floor had different ceiling elevation so use the stekwell
glue on it.
2.0 In the kitchen, the overhead cabinet and the cabinet on
the counter shall be ¾”x4”x8” marine plywood.
3.0 All the cabinet in bedroom and in drafting room shall use
the same marine plywood. In connecting each part of the cabinet
use the common wire nails namely #1 ½”, #1”, #2” and #3”, the
mechanism of the cabinet is a push type.

Downloaded by JEAN-YVES TRONCO (j.tronco.485390@umindanao.edu.ph)


lOMoARcPSD|24891340

G. DIVISION 7 – THERMAL AND MOISTURE PROTECTION

• Roofing materials specified herein shall be gauge 26 Long Span Pre-


Painted Rib-Type. Flashing, ridge rolls and valley roll shall be gauge
26 Pre-Painted. Gutter shall be pre formed Ga. 24 Pre-Painted and
design are shown on the plans. It shall have a minimum slope of
1/8” per foot.
• In the kitchen, use a 10mm double sided insulator especially in the
range hood area. Also use insulator in the ground floor ceiling
before the hardieflex board.

• Install a 10mm double sided insulator in the top cord of the roof
frame and in the ceiling area.

H. DIVISION 8 – DOORS AND WINDOWS

1.0 DOORS FRAMES

Doors and door frames shall conform to the sizes, design and
kind of materials shown in the schedule of doors and windows or as
per the bill of materials.

• Main entrance door - Panel door


• Service area & Office - Flush door
• T&B and powder room - Louvered PVC
• Terrace, pantry, & family area- Sliding door
• Bedrooms - Panel door

All wooden doors shall be hung on at least 3 pieces of 102mm x


102mm loose-pin bearing template hinges.

Door locksets to be used shall be ASSA-Abloy brand to be


installed 1024mm from the finished floor line. Rails and rollers for
the sliding door shall be ASSA-Abloy brand.

2.0 WINDOWS

Downloaded by JEAN-YVES TRONCO (j.tronco.485390@umindanao.edu.ph)


lOMoARcPSD|24891340

Steel casement windows for all window sets on sides and rear
with 3/16” thk. Glass to be provided with insect screen incorporated on
the window frame and fire escape. Size of bars to be used shall be ¼”
sq. bar. Verify also the design and sizes of windows reflected on
working drawings.
1.0

I. DIVISION 9 - FINISHES

1.0 WALL AND FLOOR FINISHES


• The floors for the living, dining and kitchen area shall be
finished with porcelain stoneware carrying the brand of
porcelanosa. The tile should be matte finished, having the
size of 59.6cm x 59.6cm with an appearance of stone look.
• The toilet and bathroom floors and walls shall be finished with
porcelain stoneware. It should have the size of 25 cm by 90
cm, with a plain pattern, polished finished, a non-slip tile, and
it should have the appearance of stone look carrying the
brand of agrob buchtal.
• The walls of the top of kitchen cabinets shall be wainscoted
with 200 x 200mm ceramic tiles.
• Interior and exterior corners of tiled floors and walls shall be
provided with the necessary tile mouldings.
• All tiles for floor, walls and mouldings shall be free from
laminations. Serrated edges, chipped-off corners and other
defects, which would adversely affect their appearance and
strength. All joints between tiles and mouldings shall be filled
with Cemex white cement and then carefully wiped.
• The kitchen counter, flash board and kitchen table shall use
40cmx40cm granite tiles. In installing use first tile adhesive
before putting the granite tile and next is install the aluminum
tile trim on each corner and edges.
• The tile adhesive to be used in all tiles should be Holcim tile
adhesive.
PAINTS
• In painting, the first thing to do is flatten the wall surface
apply by sand paper, second apply the concrete acid
neutralizer to kills the acid that is present in the concrete,
third start coating the primer to increase the durability of the
paint and blocks the steel stains and hide a color when is

Downloaded by JEAN-YVES TRONCO (j.tronco.485390@umindanao.edu.ph)


lOMoARcPSD|24891340

painted over. Next add the lacquer to for hard and durable
finish and lastly apply the paints.
All paints to be used shall be Boysen or its equivalent and the
following shall be followed:
• Exterior masonry latex
- paint primer coat 2 final coats
• Interior masonry
- latex paint primer coat 2 final coats
• Exterior wood finished
- exterior house paint and 2 final coats
• Interior wood finished
- 2 coats flatwall enamel and must receive putty

Painting covers complete painting and finishing of wood,


plasters, concrete, metal or other surfaces, exterior or interior of the
building.
All paint materials shall meet the requirements of paint materials
under classification class “A”
All colors shall be in accordance with samples to be approved by
the Color choice shall be left to the Owner of the building with the
advice of the architect in charge of construction.

DIVISION 10 - SPECIALTIES

1.0 In the toilet and bath accessories use the FLOVA bathroom or its
equivalent.

• Water closets FLOVA Bathroom collection


• Lavatories FLOVA Bathroom collection
• Kitchen Sinks FLOVA Bathroom collection
• Shower heads FLOVA Bathroom collection
• Soap holder FLOVA Bathroom collection
• Toil paper holder FLOVA Bathroom collection
• Floor drain Size 100mm x 100mm Stainless steel

(List other materials if necessary)


J. DIVISION 11 - EQUIPMENT

Downloaded by JEAN-YVES TRONCO (j.tronco.485390@umindanao.edu.ph)


lOMoARcPSD|24891340

1.0 All kitchen equipment to be use shall be a Panasonic brand or its


equivalent. The sizes should be in accordance to the architectural
plans located at the construction drawing.

2.0 In service area, the equipment is a 1.0mx 0.75m washing


machine with quick dry option. The living area, family area and
drafting room shall have special modern type lamp.

K. DIVISION 15 - MECHANICAL

All plumbing works for this project shall be in accordance with


the approved plans and under the direct supervision and control of a
licensed Sanitary Engineer or Master Plumber.
Piping shall be properly graded or pitched to ensure easy
circulation, drainage and prevent water hammer and noise.
The plumbing installation shall conform to the provisions of the
National Plumbing Code and the rules and regulations enforced in the
locality.
Piping for drain, waste and vent shall be done using the Emerald
brand uPVC push-on-system. For the in-house water supply
installation, Neltex brand uPVC pipes and fittings shall be used.

L. DIVISION 12 - ELECTRICAL

The electrical installation shall be done in accordance with the


approved plans and under the direct supervision and control of a
licensed Professional Electrical Engineer or Master Electrician.
All electric works and materials shall conform to the provisions of
the latest edition of the Philippine or the National Electric Code.
The electrical wiring shall be installed thru Emerald brand
coilable PVC electrical conduit fittings and appurtenances that conform
to ISO dimensions.
Minimum size of wires shall be 2.0 mm2 TW for switch and
lighting line 3.5 mm2 for power line in 12mm diameter PVC conduit.
There shall be only be one service drop from the nearest CEPALCO
pole to the proposed building.

Downloaded by JEAN-YVES TRONCO (j.tronco.485390@umindanao.edu.ph)


lOMoARcPSD|24891340

Electrical materials to be used for the electric installation shall as


follows:
• Automatic Circuit breaker Meiji Electric
• Flush wall switches, convenience
Outlets other wiring devices
• Wires/Conductors

The spare circuit shall be provided with an empty PVC pipe, size
19mm diameter which should extend at least 300mm aboce the ceiling
line. The grounding wires shall be identified and all wires shall be
color-coded for easy identification.
The panelboard shall be provided with a circuit directory.

Downloaded by JEAN-YVES TRONCO (j.tronco.485390@umindanao.edu.ph)


Form Reference No: PM-NCR-03.08-F-04

NO FEES REQUIRED FOR THE FILING , EVALAUTION AND APPROVAL OF CSHP


Revised Form.: CSHP-DO13-98:
Date of Revision : June1, 2011 Page 1of 3

REVISED APPLICATION FORM for


Department of Labor and Employment EVALUATION/ APPROVAL OF
REGIONAL OFFICE NO. _NCR_ CONSTRUCTION SAFETY & HEALTH
PROGRAM (CSHP)

Legal Basis: Section 5 of Department Order No. 13 s 1998


(Guidelines Governing Occupational Safety and Health In Construction Industry)

Instructions: This form shall be duly accomplished and submitted by the MAIN/GENERAL
CONTRACTOR in applying for an approval of a Construction Safety and Health Program intended for
a specific construction project.

Note: A CHECKLIST OF REQUIREMENTS shall be used in receiving the application.

Only an application form with a complete requirements and attachments will be processed.
Application found with incomplete requirements will be given 15 calendar days to comply. Failure to
comply within the prescribed period, the application will be deemed disapproved.

A. Company Profile/License/Registration of Main/General Contractor


Complete Name of the Company/ Complete Address:
Main /General Contractor
Tel. No:

Fax No.
Name of Project Manager/Contact Person: Email:

Main Contractor PCAB License Main Contractor Total employment _______


No.______________ ___ Male _____ Female _____

Date of Validity:_______________________
DOLE Registration of Main Contractor ( Pls. attach photo copy of Registration forms received and approved by
the concerned DOLE Regional Office)
Date Registered/Approved DOLE-RO
a. per DO 18-02 ( requires yearly renewal) __________________ __________

b. per Rule 1020, OSHS (one time registration) __________________ ___________


Sub-contractors’ Profile/License
No. of PCAB Validity Date of
Name of Sub-contractors (If , any) Scope of Work and Workers License Date DOLE
Project Cost Registration
1.

2.

3.

4.

5.

(Use separate sheet , if necessary)


REVISED APPLICATION FORM for
Department of Labor and Employment EVALUATION/ APPROVAL OF
REGIONAL OFFICE NO. _NCR_ CONSTRUCTION SAFETY & HEALTH
PROGRAM (CSHP)

B. Project Profile/Description
Name of the Project: (Please attach copy of Invitation to Bid/other documents indicating name and details of the
project)

Complete Project Address/Location

Name of Project Owner


Tel. No: _____________

Fax No: _____________

Email : _____________

Project Classification: Date of Estimated Start/Execution of


Estimated No. of Workers to the project:
be deployed in the project: ________________________
Month Day Year
___________________
Duration of the project (Pls.
Total Project Cost:__________________ (Workforce of the project to state the number of calendar days
include workers of the sub-
contractor/s) _________________________

Brief Description of Activities/Work Flow (You may attach additional sheet, if necessary)

Revised Form.: CSHP-DO 13-98


Date of Revision: June1, 2011 Page 2of 3
Department of labor and Employment APPLICATION FORM for APPROVAL OF
REGIONAL OFFICE NO. _NCR_ CONSTRUCTION SAFETY AND HEALTH PROGRAM

OSH Personnel assigned to the project

Name of Appointed Safety Officer/s: Name of Appointed First-Aider/s:

____________________________________ ______________________________________

Date of his/her BOSH training: _________________ Date of First –Aid Training: _______________

(Pls. attach photo copy of Certificate of Completion on the Validity of ID: __________________
Basic OSH Course for Construction Site Safety Officers issued
by DOLE-BWC accredited Safety Training Organizations or (Pls. attach photo copy of Certificate of First-Aid Training
recognized institutions) and Valid First Aider ID from PNRC

Other OH personnel (if more than 50 workers will be deployed in the project)
Name Date of BOSH Training
OH Nurse

OH Physician

Dentist

(If Heavy Equipment will be used in the Project)


List of Heavy Equipment to be Used in the Project Name of Heavy Equipment Operator/s (To attach photo
(Please attach additional sheet, if necessary) copy of skills certification from TESDA)

Profile of the person who prepared the CSH Program for the abovementioned Project:
Name and Signature Educational Background:

___________________________ Work Experience in OSH:


Signature over printed name
Other Qualifications:

I HEREBY CERTIFY ON MY HONOR TO THE TRUTHFULLNESS OF THE ABOVEMENTIONED


INFORMATION. THE COMPANY HEREBY COMMIT TO STRICTLY IMPLEMENT THE ATTACHED
CONSTRUCTION SAFETY and HEALTH PROGRAM DESIGNED FOR THE ABOVEMENTIONED PROJECT.

Submitted By:

Signature Over Printed Name ______________________________________

Position: ______________________________________________________

Date: ______________________________________________________

Revised Form.: CSHP-DO 13-98


Date of Revision: June1, 2011 Page 3 of 3
Form Reference No: PM-NCR-03.08-F-03.R01
Regional Office: DOLE-NCR
Application No: ________

Application for
CONSTRUCTION SAFETY AND HEALTH PROGRAM (CSHP)
(Intended only for residential project/s (2 storey and below) or minor repair works with 15 workers or less or with
project cost of less than Php3,000,000.00.)

Project Name: ______________________________________________________________________


Project Complete Address/Location: ___________________________________________________________
_________________________________________________________________________________________
Project Duration: _____________ Project Start: ________________ Completion Date: _________________
(No. of Calendar days) (Date of estimated start) (Date of project completion)
Estimated Project Cost: ______________________ Number of Workers: _______________________
Name of Contractor (if any):___________________________________________________________________
Contractor’s Address: ________________________________________________________________________
____________________________________________________________ Fax No.:_______________________
PCAB License No.______________ Date of Validity: ____________ Email address: _______________________

Name of Project Owner: __________________________________ Fax No.:_____________________


Project Owner Address: ______________________________________________________________________
______________________________________________________ Email address: ____________________

Accomplished by: ____________________________________


Signature over Printed Name
of
OWNER / CONTRACTOR
**********************************************************************
COMMITMENT TO COMPLY on OSH

I/We __________________________________ and _________________________________


(Name of Contractor’s Authorized Official and/or Project Owner)
do hereby commit and bind ourself to comply with the applicable provisions of the
Occupational Safety and Health Standards (OSHS) and Department Order No.13 series of
1998 – Guidelines Governing Occupational Safety and Health in the Construction Industry.
I/We hereby commit to implement a suitable Construction Safety and Health Program
designed for the abovementioned project. I/We also acknowledge my/our responsibilities to
provide the appropriate Personal Protective Equipment (PPE) and job safety and health
instructions and training to all our workers during the duration of the project.

_____________________________________ ___________________________________
PROJECT OWNER CONTRACTOR
Signature Over Printed Name Signature Over Printed Name

(NOTE: NO FEES REQUIRED FOR APPLICATION, PROCESSING AND APPROVAL OF CSHP)


APPLYING FOR A NEW
CONNECTION

HOW TO APPLY FOR A NEW CONNECTION

Application Procedure for Residential and Small Commercial as easy as ABC:


Apply
1. Inquire about Davao Light's technical standards & requirements at our Service Centers in NCCC-
VP in Bajada, NCCC Panacan, MS Land in Matina and Rivera Medical Center Inc. in Panabo
City or hire an accredited electrician (optional). Below is the list of Association of Electricians
and their respective contact numbers:

DAPREA- 226-2004
UEMD- 224-6174
IEAD- 224-1529
DURPEES- 284-6793
IIEE- 305-5011

For Panabo customers, please contact our 24/7 Customer Contact Service at 229-3572, 655-3572
(Panabo), 0917-864-2793 (Globe) or 0920-970-1357 (Smart).

2. Withdraw Davao Light Meterbase by presenting the Approved Electrical Permit Application from
OBO or applicable endorsement from authorized agency (SBMA, HLURB)

Build
3. Construct the Service Entrace (SE) and complete all wiring installation
4. Install the Davao Light Meterbase
5. Request for Davao Light inspection of compliance to standards
6. Secure Certificate of Final Electrical Inspection/Completion from OBO

Connect
7. Submit the Certificate of Final Electrical Inspection/Completion and other requirements with proof
of identity at our Service Centers in SM City Ecoland and SM Lanang Premier
8. Pay the required bill deposit as reflected in the approved inspection sheet
9. Sign the Electric Service Agreement

Note: Service installation within 2 days.

Davao Light and Power Company ©2023 Privacy policy


1. New Service Connection Application –requested by the public to process the installation of water service

Office or Division: New Service Connection Division


Classification: T-Connection - Primary
Primary Connection - Complex
Type of G2C - Government to Citizen
Transaction: G2B - Government to Business
G2G - Government to Government
Who may Avail: General Public of Davao City within the service areas of DCWD
Requirements: 1. New Service Connection Application (NSCA) form
2. 1 photocopy (with 3 specimen signatures) of competent evidence of identity of account
holder, land owner/possessor (if applicable), and representative (if applicable)
a. Passport
b. LTO Driver's License
c. BIR Tax Identification
d. Voter's ID
e. PRC Professional ID
f. GSIS Membership ID
g. SSS Membership ID
h. Phil Health ID
i. OSCA ID
j. OWWA ID
k. OFW ID
l. Any government Issued ID
m. Company Issued ID
n. School ID
3. Proof of Possession of Property (bring original copy for verification)
3.1 For Private Property/Possession
a. Photocopy of Land Title
b. Photocopy of Notarize Deed of Absolute Sale/Deed of Conditional Sale/Deed of
Donation/Contract to Sell and Land Title, if necessary
c. Photocopy of Building Permit specifically describing therein the location of the lot
d. Original copy of Certificate from NHA/City Housing/Board of Liquidator or DENR
and Notarized Transfer of Rights, if necessary
e. Original copy of Certification from Housing Developer
f. Photocopy of Occupancy Permit
3.2 For Heir in a Privately-Owned Lot
a. Photocopy of Extra-Judicial Settlement of Estate/Notarized Affidavit of Heirship,
and
b. Photocopy of Proof of Filiation (if necessary), and
c. Photocopy of Lot Title (if necessary)
3.3 For Renter/Lessee of a Privately-Owned Lot
a. Photocopy of Current and notarized Lease Contract, and
b. Photocopy of Land Title, if necessary
3.4 For Informal Settler on a Private Titled Land with Accredited Association
a. Original copy of Certification from the Association signed by the Association
President
3.5 For Informal Settler in the Government Property
a. Original copy of Barangay Certification signed by the Barangay Captain with Seal;
and
b. Letter of Undertaking
3.6 For Owner of a Property Acquired through Balikatan
a. Authenticated Notice of Approval from Balikatan or its equivalent
3.7 For Corporate/Business Establishments (any of the following)
a. Photocopy of Land Title (if owned) or
b. Photocopy of Current and notarized Lease Contract and Land Title, if necessary
3.8 For Owner of a Foreclosed Property
a. Original copy of Certification from the Bank, SSS, GSIS, PAG-IBIG or other housing
institutions
3.9 For Government Institutions
a. Certification with letterhead signed by its Head of Office
4. 1 photocopy of proof of filiation (if necessary)
a. Birth Certificate
b. Marriage Certificate/Contract
c. Death Certificate (if applicable)
d. Affidavit of Heirship

5. Proof of legal capacity of representative (if transacted by a representative)


5.1 FOR RESIDENTIAL/INDIVIDUAL:
Notarize Special Power of Attorney/General Power of Attorney/Authorization
Letter
5.2 FOR CORPORATION/GOVERNMENT AGENCIES:
Notarized Secretary's Certificate/Board Resolution/Certification or Authorization
issued by the General Manager/Administrator/ Regional Manager and the like, in
relation to the water service
6. Additional requirements for technical evaluation for properties that are two-storeys and
higher with a minimum demand of 25cu.m/day
6.1 Residential/Commercial Establishments or Condominium Buildings
a. Plumbing/Water lay-out Plan (reflecting water fixtures that needed water supply
for every storey/floor of the establishment), signed and sealed by a Registered
Master Plumber;
b. Isometric Plan (reflecting the sizes of the water supply pipelines), signed and sealed
by a Registered Master Plumber;
c. Details of Complementary Facilities signed and sealed by a Registered Master
Plumber:
➢ Dimension and Capacity of Cistern Tank
➢ HP Rating, Discharge (gpm) and Total Dynamic Head (TDJ of the
Booster/Transfer Pump)
➢ Dimension and Capacity of Elevated Water Tank
d. Approved Annual Projection of Occupancy Schedule/Projection of Water
Connection Schedule
e. Approved Site Development Plan
f. Approved Vicinity/Location Map
g. Building's Water Supply System Design Report - indicating the number of fixture
units and water demand for every storey/floor, design guidelines and parameters,
analysis,conclusions and recommendations, signed and sealed by a Registered
Master Plumber
6.2 Bulk water with required minimum demand of 25 cu.m./day
a. Plumbing/Water lay-out Plan, signed and sealed by a Registered Master Plumber
(reflecting water fixtures that needed water supply for every storey/floor of the
establishment);
b. Isometric Plan, signed and sealed by a Registered Master Plumber (reflecting the
sizes of the water supply pipelines);
c. Details of Complementary Facilities, signed and sealed by a Registered Master
Plumber:
➢ Dimension and Capacity of Cistern Tank
➢ HP Rating, Discharge (gpm) and Total Dynamic Head (TDJ of the
Booster/Transfer Pump)
➢ Dimension and Capacity of Elevated Water Tank

d. Approved Projection of Water Requirement Schedule


e. Approved Site Development Plan
f. Approved Vicinity/Location Map
g. Approved Projected water demand of the establishment, signed and sealed by a
Registered Master Plumber
7. Installation of standard plumbing provision
8. Excavation Permit, if applicable
9. Conditional requirements as a result of the evaluation
a. Consent Form (if applicant is other than the lot owner/possessor except for Lease
Contracts)
b. Sketch Map (if lot description cannot be ascertained)
c. Registry of Deed Certified True Copy of Title (if title is in question)
d. Tax Declaration may be acceptable in the absence of all primary requirements as
mentioned in the list of proof of possession
e. If the identity of the person cannot be ascertained through the available ID:
- Barangay Clearance with applicant's signature or thumb mark and picture
integrated or attached thereto, or
- Police Clearance with applicant's picture integrated or attached thereto,
or
- NBI Clearance with applicant's picture integrated or attached thereto, or
- Alien certificate of registration/immigrant certificate of registration
- Seaman's book
f. Competent Proof of Identity of the signatory of the document (for verification
purposes)
g. Consent from Co-heirs (if applicant is one of the heirs and there is existing dispute
over the property)
h. Consent from all heirs (if applicant is not a heir)
i. Sworn Statement (if applicant is not heir and consent from all heirs is not
expressed in any legal document)
j. Letter request (if applicant opts for a different meter size or is willing to forego
availment of Resolution 296; application shall be subject to evaluation and
approval)
k. Agreement (in the absence of any legal instrument related to possession of
property, subject to evaluation)
l. Affidavit of Undertaking (in the absence of any legal instrument related to
possession of property, subject to evaluation)
m. If required with Pressure Sustaining Valve (PSV) Assembly resulting from the
Technical Evaluation (in addition to above-mentioned):
➢ Installation of PSV Assembly
➢ Manufacturer's Certificate, Plant Testing certificate, Warranty Certificate
and Operating Manual of PSV
➢ Approved Deed of Usufruct with the following Annexes:
i. Approved As-built Plan of PSV assemble
ii. Recent Community Tax Certificate (CTC) /Cedula of
Applicant/representative
iii. Approved Inspection Report from the Engineering and Construction
Department (ECD) of this office
iv. Hydrotest and Leak Test Report witnessed by DCWD representative
v. Mayor's Permit
vi. SEC Registration and Articles of Incorporation, if applicable
vii. General Information Sheet, if applicable
viii. Land Title
ix. Tax Declaration of Building and Land
n. If Association is not yet accredited with DCWD:
- Lot title (of the original Lot Owner)
- Notarized Deed of Sale/ Purchase Agreement/Memorandum of
Agreement (MOA- Agreement between Lot Owner & the Association)
- SEC Registration/ HLURB Certification/ HIGC Certification
- Articles of Incorporation
- List of Association Officers with specimen signature and its designation
or position
- Valid ID card o the Association President
- List of Bonafide members of the Association
o. If Accredited Association has new set of officers:
- Minutes of meeting/election with specimen signature of officers
- Competent Evidence of Identity of President
Process: First Visit (with filled-up form and requirements) 13 min.
1. Go to PADO for assistance and secure Priority
PADO
Number
2. Attend one-on-one orientation and submit NSCA
form and requirements. Receive inspection CSA - Frontline
schedule.
If not eligible to apply but qualified for mainline extension (ME), process ME application
from the ME Unit of the Engineering Department
After approval of inspector
Second Visit 13 min.
1. Go to PADO for assistance and secure Priority
Number
2. Provide details of request and receive Order of
CSA - Frontline
Payment for NSC fee.
3. Provide OP and pay NSC fee. Receive Official
Teller
Receipt (OR).
4. Present OR. Sign Service Connection Contract
(SCC) and Promissory Note (PN), if applicable. CSA – NSC
5. Receive copy of SCC and PN.
Installation After signing of contract
Tee connection Within 3 working days
Primary Line connection Within 7 working days
END OF TRANSACTION
Fees: a. Arrears or outstanding balance for delinquent accounts
b. NSC Fee
13mm (½”)-Php3,900 (if paid in full) 50mm (2”)-PhP42,250