Professional Documents
Culture Documents
A PROECT REPORT
Submitted by
PARTHIBAN. S 822719103030
HARIHARAN. D 822719103304
of
BACHELOR OF ENGINEERING
IN
CIVIL ENGINEERING
MAY – 2023
`
BONAFIDE CERTIFICATE
supervision.
SIGNATURE SIGNATURE
ACKNOWLEDGEMENT
I reverently thank our Principal Dr. M. NATARAJ, M.E., Ph.D., for his
support and paving of proper infrastructural facility in the college.
Above all we thank our parents and members of family for their constant
support in the education travel.
`
ABSTRACT
TABLE OF CONTENTS
ABSTRACT III
LIST OF TABLES
LIST OF FIGURES
LIST OF SYMBOLS
1 INTRODUCTION 1
1.1 General 1
1.2 Objectives
2 LITERATURE REVIEW
3 PLAN
4 STORMWATER QUANTIFICATION
4.2 Quantification
5 SECTION OF DRAIN
`
6 GEOTECHNICAL DESIGN
7 STRUCTURAL DESIGN
7.3 Detailing
8 CONSTRUCTION
8.1.2. Excavation
`
8.1.6. Catchpit
9 CONCLUTION
10 REFERENCE
`
CHAPTER – 1
INTRODUCTION
1.1. GENERAL:
1.2. OBECTIVES:
Based on the stormwater runoff calculation, the design of the urban stormwater
management structure being carried out to manage the urban stormwater issues.
`
CHAPTER – 2
LITERATURE REVIEW
`
CHAPTER – 3
PLAN
`
CHAPTER – 4
STORMWATER QUANTIFICATION
Q=C. i. A / 360
C = Coefficient of runoff.
From the above formula, it is clear that for the application of rational method,
the section of coefficient C and the rainfall intensity I are required, which can be
obtained by correct judgement.
`
Table 4.1 gives the common values of runoff coefficient, which are
commonly used in determining the quantity of storm water reaching the sewer
lines.
VALUE OF RUNOFF
SI. NO TYPE OF SURFACE
COEFFICIENT
1 Forest and wooden area. 0.1 to 0.2
Open grounds, unpaved street and
2 0.1 to 0.3
railroad yards.
3 Parks, Lawns, meadows and gardens. 0.1 to 0.25
4 Gravel roads and walks. 0.15 to 0.3
5 Macadam roadways. 0.15 to 0.6
Inferious stone, brick or block pavements
6 0.4 to 0.5
with open joints.
Stone brick and block pavements with
7 0.5 to 0.7
open joints.
Good quality pavements of stones, bricks
8 0.75 to 0.85
or blocks.
9 Asphalt pavements in good condition. 0.85 to 0.90
10 Water-tight roof surfaces. 0.7 to 0.95
`
Where, A1, A2, A3… are the different types of area and C1, C2, C3, … are their
runoff coefficients respectively.
From the above expression, it is clear that for calculating runoff coefficient, area
of each type of surface is to be measured and then substituted in the formula.
The calculation of area of each type of surface is very tedious and
impracticable. Therefore, runoff coefficients are chosen by inspection of the
localities, which directly depends on the density of population. Table 4.2 gives
overall runoff coefficient for different types of localities.
`
The boundary of the design area was drawn around the area of interest,
which includes the catchment area for the proposed stormwater management
system. The area of the design area was calculated to be 10 hectares. The land
use within the area was predominantly residential, with some commercial
properties located along the perimeter.
4.2. QUANTIFICATION
`
The catchment area of the site is 10 hectares and the maximum intensity
of rainfall is 50mm/hr.
Assuming that the surfaces on which the rain falls is classified as follows:
Roofs 30 0.9
Q = C. i. A / 360
Q= 0.505 x 50 x 10 / 360
Q= 0.7 m3/sec.
The discharge of stormwater which will reach the drain is 0.7 m3/sec.
`
CHAPTER – 5
SECTION OF DRAIN
Rectangular by b + 2y b A/P
The provision of freeboard in open drains ensures enough room for wave
action and flow surges not to overtopping or overflow the drain. Many
uncontrolled causes may create wave action or water surface fluctuation, but
mostly because of changes in specific energy of the flow in a channel.
`
Therefore, a freeboard is provided to ensure the drain is not filled with water. In
addition, the calculated discharge rate does not consider deposited solids and
lack of maintenance, which will usually reduce the system’s efficiency.
It was estimated from quantification that the peak discharge from the
catchment area is 0.7 m3/sec. Using Manning’s equation, determining the best
hydraulic cross-section for a rectangular channel. Other assumptions for
computations are provided below.
Q = VA
Where,
Q = Discharge (m3/sec) A = Flow area (m2)
V = Allowable velocity (m/s) R = Hydraulic Radius (m)
From, Q = VA------(1)
For the best hydraulic section for rectangular drain b = 2y and R = y/2
CHAPTER – 6
GEOTECHNICAL DESIGN
= 5.88 kN/m2
Net pressure at base of the wall =9.702-5.88 =3.822 kN/m2
Wall 2
Active pressure at top of drain wall = qKa =5x0.33 =1.65 KN/m2
Active pressure at base of drain wall = qKa + Ka γ 2 =1.65+(0.33x18x0.8)
= 6.402 KN/m2
Passive pressure at top of drain wall = 0
Passive pressure at base of wall = γwZ
= 9.8x0.6 =5.88KN/m2
Net pressure at base of the wall = 6.402-5.88
= 0.522 kN/m2
Total vertical load (N)
Walls (WWS) =2 x (0.2 x 0.6 x 24) = 5.76 kN/m
Base (wb) =1x 0.2 x 24 = 4.8 kN/m
Wall (ww) = 0.3 x 0.6 x 9.8 = 1.764 kN/m
Total vertical load wws + wb + ww (N)
N = 5.76 + 4.8 + 1.764
N = 12.324 kN/m
CHAPTER – 7
STRUCTURAL DESIGN
Since the horizontal force due to surcharge load and backfill on wall 1 is
greater than wall 2, we adopt Wall 1 parameters for design. Using the centroidal
formula of parallelogram for the pressure diagram of wall 1 to determine the
distance (x) from the centroid to the base of the wall and distance (y) from the
centroid to the top of the wall.
Taking moment at the top of the drain wall due to the active force
M = 3.545 x 0.38 = 1.31kNm/m
Taking moment at the base of the drain wall due to the active force;
M = 3.545 x 0.41 = 1.45 kNm/m
At ultimate limit state;
M = 1.4 x 1.45 = 1.974 kNm/m
Water = 1.97kN/m
Base = 3.21kN/m
Earth pressure = (11.45 x 11.2 x (1.2x2) + (23.04-11.45) x 1.2 x 0.5 x
(2x1.2/3))
= 13.34kNm/m
Net moment = 13.34-1.97-3.21
=8.61kNm/m
Since net moment at B > moment at A, we adopt 8.61 kNm for design.
Calculating the maximum shear force at any section of the drain base;
Water = 1.4 x 9.8 x 0.3 x 0.8 = 3.29 kN/m
Base = 1.4 x 24 x 0.8 = 5.37 kN/m
Earth pressure = 0.5 x (23.04 -11.45) x 0.8 = 13.79kN/m
Net shear force = 13.796-3.29-5.37
= 5.136kN/m
Shear stress(v) = v/bd = (5.13 x 1000) / (100 x 155)
= 0.033 N/mm2
Shear strength vc = 0.632 x (100AS/bd)1/3 x (400/d)1/4 x (fcu x 25)1/3
= 0.632 x (100x420)/(100 x155))1/3 x (400x155)1/4 x (20/25) 1/3
=0.48N/mm2
v < vo; 0.33 < 0.48
Since v < vc , No shear reinforcement required.
`
7.3. DETAILING
[… detailing image insertion here…]