Fatality LEL% is to be checked at job location & surrounding area and must be Zero before
starting of hot job.
Proper shielding (leak proof booth at hot job location) should be prepared at
job location to arrest all the hot spatters inside the booth (Floor & side walls are
compulsory in booth construction). Booth must be prepared & should be checked
by Process & Maintenance representatives (own employee) before hot job
execution.
Good housekeeping is to be ensured before start the job by execution team at job
location. All combustible materials/flammables are to be removed from job
location before starting of hot job. Proper housekeeping should be done at
ground level also.
Fire Extinguishers & Running water hose connection should to be kept ready at
the cable tray fixing hot job location.
The job should be carried out in presence of competent job supervisor.
Close & continuous supervision is required by contractor job supervisor &
representatives from Process & Maintenance Dept. (Own employee)
SOP & SMP available with the executing department.
Rational or Comment:
Hot work permit procedures should be followed.
*** Tool Box Talk is to be carried out daily before starting the job by contractor job supervisor.
*** Nearby Fire extinguisher, PA system, MCP, Safety Shower and Assembly point location should be
known to all. Escape route must be kept clear from any obstruction and wind direction must be
considered during evacuation.
PPE compliance should be fulfilled during job execution.