1. FIRST LAYER OF INSULATION SET BACK FROM FLANGE 3". ALL OTHER LAYERS SHOULD
BE FLUSH WITH THE FIRST LINE OF STUDS.
D D
2. PROTECT ALL EXPOSED INSULATION USING PLASTIC WRAP.
IMPALE PLASTIC ON THE PERIMETER ROW OF BOLTS, PACK ALL LAYERS OF INSULATION
AND WRAP PLASTIC AROUND THE INSULATION AND IMPALE OVER THE LINER BOLTS
AGAIN.
REFER TO H-K QM-STD-1500 HANDLING, PACKING PRESERVATION AND DELIVERY 4.3.2
EXHAUST SYSTEM.
SEE NOTE #1
PLASTIC WRAP SEE NOTE #2
C
TYP. CHANNEL FLANGE C
FLANGES MAY VARY
WASHER
SEE NOTE #3
B B
Released
All information contained within this drawing is the exclusive property of
ATCO Structures & Logistics Ltd.
This design information is CONFIDENTIAL and must not be reproduced or distributed to outside parties without
consent of ATCO Structures & Logistics Ltd.
By using this drawing the user agrees to abide by these foregoing terms and conditions.
LINER DETAILS
A DRAWN PeterA 11/4/2004 DRAWING No. REV A
CHECKED VB 12/3/2004