INSPECTION REPORT

First Piece Inspection Doc. Ref: FAB-FR-75-01-7-B


Qty: _____________
In Process Inspection Rev Date: 26-07-2016
Job No: Project Name:

Item Description Requested By

Result
Check points Remarks
Good Not Good

Machining of ACM PROFILE ALUMINUM SHEET OTHERS (Specify)


Free from damage
Cut o size
Thickness of Material
Grooving depth
Holes for rivets
Holes for screws
Drainage Holes
Notching
Degree
Bending / Rolling
Squareness of folds
Height of folds
Radius
Framework Assembly
Squareness of frame
Welding
Panel Assembly
Squareness of panel
Spacing of rivets
Spacing of screws
Fitting of ACM to frame
Free from damage
Silicone
Free from dirt
Free from damage
Properly filled up
Cleanliness
RESULT Remarks:
Accepted
Hold
Rejected
Inspected by: Approved by:
QC Inspector
Supervisor (Name over Signature) (Name over Signature)
Date: Date: