Shams Dubai

Consultants & Contractors Training


Day 2 – (05.10.2020) Summary Quiz
Time: 20 minutes
Answer the following questions in the table by choosing only one letter from available choice. Then write your
choice in the answers column, each question has only one correct answer.
Sr.
No. Question Answer
AM 1.5 is the term used for Air mass under which of the following consideration for the
solar light path:
1. a) The solar has 50% of light reflected into Air, hence considered at 1.5 times
b) The distance from atmosphere entry point to the tilted surface (37o) with zenith angle
at 48 o is 1.5 times
c) The distance from sun to the tilted surface (37o) with zenith angle at 48 o is 1.5 times
NOCT is the temperature reached by open circuited cell in an open- rack mounted PV
module under the following reference environment
2. a) irradiance 1000W/m2, cell temperature = 25°C, wind speed: 1 m/s
b) irradiance 1000 W/m2, ambient temperature = 25°C, wind speed: 1 m/s
c) irradiance 800 W/m2, ambient temperature = 20°C, wind speed: 1 m/s
As per DEWA connection standards, the support of reactive power from grid connected
inverters is required:-
3. a) PMC < 10 kW
b) From PMC = 10 kW and above
c) From PMC = 100 kW and above
Can the switches rated for AC circuits deployed in DC circuits?
a) Yes, Always
b) Yes, but only if declared possible by the manufacturer
4. c) No, Never
An interface protection unit provides:
a) Over and Under Voltage protection only
5. b) Over current protection only
c) A voltage and frequency protection (with further protections)
For a solar panel to be used in BAPV Shams Dubai project without any site specific safety
requirement, Standard IEC 61730 –2 Fire resistance class suitable:
6. a) Only Class A is acceptable to DEWA, Class B and Class C not suitable
b) Only Class C is acceptable to DEWA, Class A and Class B not suitable
c) All A, B, C Class are acceptable to DEWA
European Efficiency is calculated weighted average with measurement:
a) of efficiencies at various percentage of rated MPP voltage range
7. b) of efficiencies taken at different places in Europe
c) of efficiencies at various percentage of rated MPP power levels

Confidential Page 1 of 2
Shams Dubai
Consultants & Contractors Training
- 2 -

Sr.
No. Question Answer
As per DEWA requirement Loss of Mains (LOM) shall be realized by:
a) means of Rate of Change of Frequency (ROCOF) and Vector Shift to be used
8. alternatively at the instance of DEWA
b) means of Rate of Change of Frequency (ROCOF)
c) means of Vector Shift
Productivity of a 1KWp PV system, Enom [kWh] = PPV x PSH x 365.25 x PR with
5.8 hours peak sunshine and performance ratio 0.8
9. a) 1694.74 (~1700) KWh/year
b) 1394.74 (~1400) KWh/year
c) 1594.74 (~1600) KWh/year
An house hold has a consumption of 13600 k Wh/year. If we consider the installation of a
PV plant that produces 1700k Wh / k Wp/year, which is the maximum size to install that
makes the net-metering fully profitable
10. a) 1.7 k Wp
b) 8. 0 k Wp
c) 13.6 k Wp
The Bypass diodes are installed in each
a) PV module
11. b) String
c) In a PV plant
The blocking diode:
a) Avoids circulation of currents due to voltage mismatches
12. b) Allows to by-pass a shaded module
c) Blocks a string feeding power to the inverter
If a crystal silicon PV module has a voltage – Temperature coefficient of -100mV/°C and an
open circuit voltage of 40V, then:
13. a) The voltage will increase of 100mV/°C with the temperature
b) The voltage will decrease of 100mV/°C with the temperature
c) The voltage will decrease of 0.25V/°C with the temperature
Which of below single phase inverter based solar system is allowed to connect as per
DEWA standard:
14.
a) L1 = 8KW, L2 = 4KW, L3 = 9KW
b) L1 = 2KW, L2 = 6KW, L3 = 9KW
c) L1 = 8KW, L2 = 2KW, L3 = 5KW
***********

Confidential Page 2 of 2