Professional Documents
Culture Documents
1
Precompression
• Simply place a surcharge fill on top of the soil that requires consolidation
• Once sufficient consolidation has taken place, the fill can be removed and
construction takes place
• Surcharge fills are typically 10-25 feet thick and generally produces
settlement of 1 to 3 feet.
• Most effective in clay soil
Advantages of precompression
• Requires only conventional earthmoving equipment
• Any grading contractor can perform the work
• Long track record of success
Disadvantages of precompression
• Surcharge fill must extend horizontally at least 10 m beyond
the perimeter of the planned construction, which may not be
possible at confined sites
• Transport of large quantities of soil required
• Surcharge must remain in place for months or years, thus
delaying construction
5
6
EXAMPLE 1
• During the construction of a highway bridge, the average permanent load
on the clay layer is expected to increase by 115 kN/m2 . The average
effective overburden pressure at the middle of the clay is 210 kN/m2 . The
clay is normally consolidated. Determine the surcharge, ∆σ’(f) needed to
eliminate the entire primary consolidation settlement in 9 months by
precompression. Use Hc = 6 m, Cc = 0.28, e0 = 0.9, and Cv = 0.36 m2/mo.
SOLUTION
• Cv = 0.36 m2/mo
• H = 3 m (two – way drainage)
• t2 = 9 months
• Tv = (0.36)(9)/32
= 0.36
According to Figure
14.19, for Tv = 0.36, the
value of U is 47%
• Given;
– ∆σ’(p) = 115 kN/m2
– σ’0 = 210 kN/m2
– ∆σ’(p) / σ’0
= 115 / 210
= 0.548
According to Figure 14.17, for U = 47% and ∆σ’(p) / σ’0 = 0.548
∆σ’(f) / ∆σ’(p) ≈ 1.8, thus
• Example of methods:
i. Rotary drilling and then backfilling
ii. Drilling by continuous-flight auger with a hollow stem and
backfilling
iii. Driving hollow steel piles, soil jetted out and backfilling.
• After backfilling the drill holes with sand, a surcharge is applied
at the ground surface.
• The surcharge will increase the pore water pressure in the clay.
15
The figure below shows a schematic of a sand drain.
17
Preloading with vertical drains
19
To determine the surcharge that needs to be applied at the ground surface and the
length of time that it has to be maintained, see the figure below and use the equation
'
( p)
log 1
'
o
U v ,r
(' p ) (' f )
log 1 ' 1 '
o ( p )
20
During the installation of sand drains, a certain zone of clay surrounding
them is smeared, thereby changing the hydraulic conductivity of the clay.
rs is the radial distance from the center of the sand drain to the farthest
point of the smeared zone.
æ -8Tr ö
Ur = 1- exp ç ÷
è m ø
21
Where
n2 n 3 S
2
kh n2 S 2
m 2 ln 2 ln S
n S 2
S 4 4n k s n
2
de
n
2rw
= hydraulic conductivity of clay in the horizontal direction in the
rs
unsmeared zone
S
rw
= horizontal hydraulic conductivity in the smeared zone
C vrt 2
= nondimensional time factor for radial drainage only = de2
kh
e
= coefficient of consolidation for radial drainage =
'
(1 e )
av
22
EXAMPLE 2
• From previous example, recalculate with addition of some sand
drains. Assume rw = 0.1 m, de = 3 m, Cv = Cvr , and the surcharge is applied
instantaneously. Assume no – smear case.
SOLUTION
• Previously,
Tv = 0.36
4𝑇𝑉 (4)(0.36)
𝑈𝑉 𝑥 100 = 𝑥 100 = 𝟔𝟕. 𝟕%
𝜋 𝜋
𝑑𝑒 3
𝑛= = = 15
2𝑟𝑤 2 𝑥 0.1
𝐶𝑣𝑟 𝑡2 (0.36)(9)
𝑇𝑟 = 2 = 2
= 0.36
𝑑𝑒 (3)
the degree of consolidation 30 days after the surcharge is first applied. Also, determine
From figure, UV ≈ 9%
𝑑𝑒 1.83
𝑛= = = 10
2𝑟𝑤 (2) (0.091)
𝑛2 3𝑛2 − 1 102 3 10 2 − 1
𝑚= 2 ln 𝑛 − = ln 10 − = 1.578
𝑛 −1 4𝑛2 102 − 1 4 𝑛 2
2 2
𝐴= = = 1.267
𝑚 1.578
1
𝑇𝑟 − 𝐴 [ 1 − exp(−𝐴𝑇𝑟 )]
𝑈𝑟 =
𝑇𝑟𝑐
1
0.095 − 1.267 [ 1 − exp(−1.267 𝑥 0.095)]
𝑈𝑟 = = 0.03 = 3%
0.19
𝑈𝑣,𝑟 = 1 − 1 − 𝑈𝑣 1 − 𝑈𝑟 = 1 − 1 − 0.03 1 − 0.09 = 0.117 = 𝟏𝟏. 𝟕%
38