Waiting for hardening
3 B E of concrete I
3 7
7/ 2
5
C
BF
1 5
5 12/6
A) Using the AON network and calendar given above carry out necessary network calculations to answer
the below given questions.
Calculate the “finish date” of the project. Show all the Early and Late time calculations on the network.
Show the Critical path(s).
B) What happens to the project duration under the below given scenarios:
THE PROJECT IS DELAYED 1
DAY
Scenario 1: C is delayed by 1 day; I is delayed by 1 day