INTERNAL PUNCHLIST (QA/QC) LEVEL 21 - ROOM 2108

Item Target
Location Description of Non-complying items Photo Responsible Verified Date complied
No. date
1 LIVING ROOM LACKING FLUTTED PANEL/ WOODEN SLATS VSI
2 LIVING ROOM SPRINKLER TERMINATION VSI & PCCI
3 LIVING ROOM TELEPHONE WIRE NEAR WALL MIRROR TRENDS
4 LIVING ROOM UNEVEN CEILING PAINT FINISH VSI
5 LIVING ROOM UNEVEN CEILING PAINT SURFACE VSI
6 LIVING ROOM ALL WALLPAPER W/ BUBBLES, DENTS, SCRATCHES, TEAR ETC. VSI
7 LIVING ROOM ALL WALLCOVER/ WALLPAPER - REMOVE EXCESS PAINTS/ MARK UPS. VSI
8 LIVING ROOM CARPET FO FIX UHC
9 LIVING ROOM LOUVER ALIGNMENT VSI
10 BEDROOM SLIDING DOOR TRACK NOISE VSI
11 BEDROOM SLIDING DOOR PANEL FINISH - UNEVEN FINISH, ROUGH EDGES, DENTS VSI
12 BEDROOM CRUMPLED HEADBOARD FABRIC VSI
13 BEDROOM HEADBOARD VOID SURFACE - FOR IMPROVEMENT IMPROVE VSI
14 BEDROOM CAPPING AUSTPHIL
15 BEDROOM CARPET FOR CLEANING UHC & VSI
16 BEDROOM LOOSE FURNITURES - LAYOUT FOR VERIFICATION RLC
17 TOILET & BATH TB DOOR PANEL UNEVEN PAINT FINISH VSI
18 TOILET & BATH TB DOOR PANEL ROUGH EDGES VSI
19 TOILET & BATH DOOR STOPPER - VERIFY VSI
20 TOILET & BATH WALL TILES UNEVEN GROUT APPLICATION VSI
21 TOILET & BATH WALL TILES LIPPAGE VSI
22 TOILET & BATH FLOOR TILE UNEVEN GROUT APPLICATION MTEC
23 TOILET & BATH FLOOR TILE UNEVEN GROUT APPLICATION ESP AT ACCENT STRIP MTEC
24 TOILET & BATH FLOOR TILES WITH STAINS, DENTS, CRACKS, CHIPPED EDGES MTEC
INTERNAL PUNCHLIST (QA/QC) LEVEL 21 - ROOM 2108

Item Target
Location Description of Non-complying items Photo Responsible Verified Date complied
No. date
25 TOILET & BATH ALL PLUMBING FIXTURES - APPLY SEALANT PPCI
26 TOILET & BATH ALL TB ACCESSORIES - CHECK MUST BE OF GOOD INSTALLATION VSI
27 TOILET & BATH LOOSE TOWEL RACK INSTALLATION VSI
28 TOILET & BATH LAVATORY COUNTER TOP WITH SCRACTCHES, ROUGH EDGES, VSI
29 TOILET & BATH LAVATORY BACKSPLASH TERMINATION & SURFACE VSI
30 TOILET & BATH WALL ACCENT TILE (BLUE AGATHA) - UNEVEN GROUT APPLICATION VSI
31 TOILET & BATH UNEVEN GOLD PELMET FINISH PAINT VSI
32 TOILET & BATH IMPROVE PAINTING AT VANITY VSI
33 TOILET & BATH SHOWER HEAD - FIX INSTALLATION PPCI
34 TOILET & BATH BAL. LINEAR SHOWER DRAIN MTEC & PPCI
35 TOILET & BATH RUBBER SEAL VSI
36 TOILET & BATH WARDROBE ALIGNMENT VSI
37 TOILET & BATH LACKING GLASS AT WARDROBE DRAWERS VSI
38 TOILET & BATH WARDROBE DRAWER GUIDES MUST BE SOFT CLOSE VSI
39 TOILET & BATH PANEL BOARD TAGGING TORQUE
40 TOILET & BATH FLOOR TILE TO METAL INSERT TERMINATION MTEC
41 TOILET & BATH FLOOR TILE - IMPROVE GROUT APPLICATION & SURFACE POLISH MTEC
42 TOILET & BATH FLOOR STAIN MTEC
43 FOYER OSM - EVACUATION PLAN (ACTUAL ACRYLIC MATERIAL) NOT INSTALLED. RLC
44 QAQC NOTE: FOR OTHER BALANCES, DESIGN REVISIONS, ETC. - COORDINATE WITH RLC CCM
45 CHECK ALL ALIGNMENT, TESTING, ETC. FINISH ALL BALANCES.

Inspected by: Participated by:

Ar. Charra Olmos Sepe/ RLC-CCM QAQC Architect Mary Jean Paden/ VSI QAQC
Loucila Silvano/ VSI QAQC
Engr. Raymond Inoferio / RLC-CCM QAQC Engineer Ronald Medina/ PPCI
Lyana Kae Torrevillas/ MTEC
Ar. Anna Bandaleria / RLC-CCM CSA Kieth Pastiteo/ Million Lighting
Alin Pagopro/ Torque
Engr. Geian Maturan / RLC-CCM Office Engineer Daniel Conel/ QuestAir

Ar. Jessie Salinas/ RLC CCM - CM Architect