TOTAL CONTRACT PRICE: Php4,450,000.00 (Four Million Four Hundred Fifty Thousand Pesos)
TOTAL CONTRACT PRICE: Php4,984,000.00 (Four Million Nine Hundred Eighty-Four Thousand Pesos)
INCLUSIONS:
General Requirements Provided by Client
Mobilization 15.00 km
Deliveries 10.00 trip
Housekeeping (2 pax) 6.00 week
General Cleaning 1.00 lot
Temporary Door 2.00 set
Hauling of Debris 10.00 trip
Road User's Tax 10.00 trip
Building Permit Plans 1.00 lot by owner
Processing of Building Permit 1.00 lot by owner
As-Built Plans 1.00 lot by owner
Processing of Occupancy Permit 1.00 lot by owner
Architectural Provided by Client
Wall & Ceiling
Drywall - Standard 21.10 sqm
Drywall - Moisture-Resistant 8.00 sqm
Fixed Ceiling - Standard (Board Up) 72.10 sqm
Fixed Ceiling - Moisture-Resistant 2.20 sqm
Cornice 251.51 lm
Wainscoting 352.20 lm
Baseboard 105.90 lm
Curtain Cove 31.70 lm
Masonry
Pantry Floor Tilesetting 6.30 sqm
Powder Room Floor Tilesetting 5.22 sqm
Pantry Backsplash 17.22 sqm
Masonry Consumables
Tile Adhesive - Ordinary Thick Bed 4.00 25kg bag
Tile Adhesive - Ordinary Medium Bed 3.00 25kg bag
Tile Adhesive - Ordinary Thin Bed 4.00 25kg bag
Tile Grout 6.00 bag
Painting
PT-01 - Wall Paint - Semi-Gloss Crisp Linen 61YY 89/040 / Boysen Equivalent 274.04 sqm
PT-01B - Ceiling Paint - Flat Crisp Linen 61YY 89/040 / Boysen Equivalent 220.00 sqm
PT-02 - Wall Paint - Semi-Gloss Ral 7022 Umbra Grey / Boysen Equivalent 54.25 sqm
Doors, Glass & Aluminum Works
Single Leaf Solid Core Door - Varnished (Powder Room & Pantry) 2.00 set
Double Leaf Solid Core Door - Varnished (Main Office) 1.00 pair
Single Leaf Frameless Tempered Glass Door (Entrance & Conference Room) 2.00 set
Single Pane Tempered Glass 75.18 sqft
Frosted Sticker 101.01 sqft
Door Hardware
Leverset 3.00 set
Leverset - Dummy 1.00 set
Flush Bolt 1.00 set
Hinge - 3.5 × 3.5 2BB 16.00 piece
Door Closer 3.00 set
Door Stopper 3.00 set
Specialty Items
Wooden S4S Trellis 2"x6"x12' 20.00 set
Wooden S4S Trellis Finishing 20.00 set
Base Cabinet 1.90 lm
Overhead Cabinet 1.90 lm
Base Cabinet Stone Works 12.27 sqft
Reception Counter Carcass 1.00 lot
Reception Counter Stone Works 1.00 lot
Blinds - Blockout 1,364.86 sqft
Electrical Provided by Client
Roughing-Ins (Lighting)
1/2" Ø PVC Conduit 46.00 length
3/4" Ø PVC Conduit 20.00 length
1/2" Ø Flexible PVC Conduit 20.00 roll
1/2" Ø PVC Coupling 92.00 piece
3/4" Ø PVC Coupling 40.00 piece
1/2" Ø PVC Elbow 92.00 piece
3/4" Ø PVC Elbow 40.00 piece
Utility Box 95.00 piece
Junction Box 50.00 piece
Square Box - 4" × 4" 50.00 piece
Square Box - 4-11/16" × 4-11/16" 50.00 piece
Wiring (Lighting & Power)
#12 / 3.5 mm2 Ø THHN Wire 36.00 box
#10 / 5.5 mm2 Ø THHN Wire 4.00 box
#8 / 8.0 mm2 Ø THHN Wire 3.00 box
Wiring Devices
One-Way One-Gang Switch 2.00 set
One-Way Two-Gang Switch 3.00 set
One-Way Three-Gang Switch 12.00 set
Simplex Universal Duplex Convenience Outlet w/ Ground - set
Duplex Universal Duplex Convenience Outlet w/ Ground 58.00 set
Duplex Universal Duplex Convenience Outlet w/ Ground & Safety Shutter - set
GFCI Convenience Outlet 4.00 set
Twistlock Outlet - set
Lighting Fixtures
Pin Light 87.00 set by owner
Fluorescent Light 1.00 set by owner
Chandelier 1 6.00 set by owner
Chandelier 2 3.00 set by owner
Curved Linear Light 1.00 set by owner
T5 Tube 124.00 lm by owner
Lighted Mirror 1.00 set by owner
Lighted Exit Sign 4.00 set
Panels
Panel PP-1 1.00 set existing
Panel PP-2 1.00 set existing
Miscellaneous
Hangers & Supports 1.00 lot
Consumables 1.00 lot
Testing & Commissioning - Megger Test, Lux Test 2.00 test
Mechanical Provided by Client
Ducting
GI Sheet #24 34.20 sqm
Polyolefin Insulation 1" 34.20 sqm
Flexible Duct 300mm Ø 3.00 m
Equipment
2.0HP Wall-Mounted Split-Type - MITSUBISHI SRK18YL 2.00 set
3.0HP Wall-Mounted Split-Type - MITSUBISHI SRK71ZR-S 3.00 set
Exhaust Fan 2.00 set
Refrigerant Piping
Copper Pipe HD "L" 1/2" Ø 137.00 m
Copper Elbow LR 90° 1/2" Ø 100.00 piece
Copper Coupling 1/2" Ø 60.00 piece
Rubber Pipe Insulation 1/2" Ø 137.00 m
Rubber Pipe Insulation @ Fittings 1.00 lot
Drain Line
uPVC Conduit 137.00 m
Rubber Pipe Insulation 1/2" Ø 136.00 m
Miscellaneous
Hangers & Supports 1.00 lot
Consumables 1.00 lot
Testing & Commissioning - Air Balancing 5.00 test
Payment Schedule:
***Note:
Part of the Mobilization went to Lighting Fixtures of ID. Will Liquidate with receipts.
_______________________________
Ms. Maria Socorro Oca, ECSMI