PENYEDIAAN 30 M
TAHAP 2 TAHAP
TAHAP
3.2
3.1 TAHAP 1
TAHAP 1
TAHAP 1
TAHAP 1
DINDING = 3 SET @ 20 M’
PT. Innotech Systems @2018
METODE DINDING UNDERPASS
POTONGAN
DINDING TEPI POTONGAN POTONGAN
PT. Innotech Systems @2018
DINDING TENGAH DINDING TEPI
METODE SLAB UNDERPASS
TAHAP 2 TAHAP 1
TAHAP 2
Double Timber Beam 160 mm 200 mm 1200 mm 93,91284 kg/cm² ≤ 125 kg/cm² OK 1,12695 mm ≤ 3 mm OK
DINDING = 2 SET @ 50 M’
PT. Innotech Systems @2018
METODE SLAB BOX CULVERT
BOX CULVERT
BASE SLAB
DINDING
SLAB
BASE SLAB (1 CYCLE 6 HARI)
BESI, BEKISTING,COR 5 HARI
BONGKAR BEKISTING 1 HARI DINDING (1 CYCLE 6 HARI)
BESI, BEKISTING,COR 5 HARI
BONGKAR BEKISTING 1 HARI SLAB (1 CYCLE 25 HARI)
BESI, BEKISTING,COR 14 HARI
BONGKAR BEKISTING 7 HARI
PT. Innotech Systems @2018 MOVING MATERIAL 4 HARI