FACSIMILE
Prior to the Boiler No.4 annual inspection early February 2021, we are pleased to
propose the following 4 weeks incremental dosage schedule as online cleaning
program. During the online cleaning period, pls ensure the blowdown is carried out
adequately to facilitate removal of dissolved particles.
Softener operation is important to control at zero all the times as leakage would
consume the cleaning chemicals. Follow the recommended dosage and make
adjustment whenever necessary depends on actual reserve obtained.
Dosage/shift
TDS
Boiler No.4 (60ton/hr) Advantage Adjunct Control
1400 SG Sulfite HLM Adjunct B
Thank you.
Yours Faithfully,
Haizad
Haizad
Area Engineer
H/P: 019-3561703