YEAR - 2022

NO JOB DESCRIPTION JUN JULY AUGUST SEPTEMBER OCTOBER


20/06 27/06 04/07 11/07 18/07 25/07 01/08 08/08 15/08 22/08 29/08 05/09 12/09 19/09 26/09 03/10

1 FLOW PROCESS DIAGRAM

2 EQUIPMENT SELECTION/SPECIFICATION

3 DATA VENDOR (Chiller water, membrane filter, agitator, crystallizer, pompa, WTP and WWTP)

4 PRELIMINARY BUDGETTING

5 CIVIL AND STRUCTURAL DESIGN & DRAWING

6 MECHANICAL AND PIPING DESIGN & DRAWING

7 ELECTRICAL AND INTRUMENT. DESIGN & DRAWING

8 FINAL ESTIMATION (BUDGETING)

9 REPORTS