KEMENTRIAN PERHUBUNGAN

DIREKTORAT JENDERAL PERKERETAAPIAN


BALAI TEKNIK PERKERETAAPIAN WILAYAH JAWA BAGIAN TIMUR
KANTOR PENGEMBANGAN PERKERETAAPIAN SULAWESI SELATAN
PEMBANGUNAN JALUR KA LINTAS MAKASSAR - PAREPARE KM 32+600 - KM 36+600 ANTARA MAROS-BARRU (MYC 2018 -2020) PAKET CT. 407
TIME SCHEDUL (KURVA-S)
2019 2020
BOBOT BOBOT BOBOT OKTOBER NOVEMBER DESEMBER JANUARI FEBRUARI MARET APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER
30-Sep-19 7-Oct-19 14-Oct-19 21-Oct-19 28-Oct-19 4-Nov-19 11-Nov-19 18-Nov-19 25-Nov-19 2-Dec-19 9-Dec-19 16-Dec-19 23-Dec-19 30-Dec-19 6-Jan-20 13-Jan-20 20-Jan-20 27-Jan-20 3-Feb-20 10-Feb-20 17-Feb-20 24-Feb-20 2-Mar-20 9-Mar-20 16-Mar-20 23-Mar-20 30-Mar-20 6-Apr-20 13-Apr-20 20-Apr-20 27-Apr-20 4-May-20 11-May-20 18-May-20 25-May-20 1-Jun-20 8-Jun-20 15-Jun-20 22-Jun-20 29-Jun-20 6-Jul-20 13-Jul-20 20-Jul-20 27-Jul-20 3-Aug-20 10-Aug-20 17-Aug-20 24-Aug-20 31-Aug-20 7-Sep-20 14-Sep-20 21-Sep-20 28-Sep-20 5-Oct-20 12-Oct-20 19-Oct-20 26-Oct-20 2-Nov-20 9-Nov-20 16-Nov-20 23-Nov-20 30-Nov-20 7-Dec-20 14-Dec-20 21-Dec-20 28-Dec-20
No URAIAN PEKERJAAN KONTRAK KONTRAK KONTRAK
AWAL ADD-01 ADD-02 6-Oct-19 13-Oct-19 20-Oct-19 27-Oct-19 3-Nov-19 10-Nov-19 17-Nov-19 24-Nov-19 1-Dec-19 8-Dec-19 15-Dec-19 22-Dec-19 29-Dec-19 5-Jan-20 12-Jan-20 19-Jan-20 26-Jan-20 2-Feb-20 9-Feb-20 16-Feb-20 23-Feb-20 1-Mar-20 8-Mar-20 15-Mar-20 22-Mar-20 29-Mar-20 5-Apr-20 12-Apr-20 19-Apr-20 26-Apr-20 3-May-20 10-May-20 17-May-20 24-May-20 31-May-20 7-Jun-20 14-Jun-20 21-Jun-20 28-Jun-20 5-Jul-20 12-Jul-20 19-Jul-20 26-Jul-20 2-Aug-20 9-Aug-20 16-Aug-20 23-Aug-20 30-Aug-20 6-Sep-20 13-Sep-20 20-Sep-20 27-Sep-20 4-Oct-20 11-Oct-20 18-Oct-20 25-Oct-20 1-Nov-20 8-Nov-20 15-Nov-20 22-Nov-20 29-Nov-20 6-Dec-20 13-Dec-20 20-Dec-20 27-Dec-20 31-Dec-20

(%) (%) (%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66

100 %
I. UMUM
1 Pengukuran, Pasang Patok Profil Track 0.112 0.112 0.112 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 Pembuatan Direksi Keet dan Gudang Material 0.030 0.030 0.030 0.01 0.01 0.01 0.01
3 Pembuatan Papan Nama Proyek 0.001 0.001 0.001 0.00 0.00
4 Penerangan Lengkap Peralatan Direksi 0.032 0.032 0.032 0.02 0.02 0.03
5 Mobilisasi Peralatan Kerja dan Sosialisasi 0.175 0.175 0.175 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 Gambar Shop Drawing dan As Build Drawing 0.009 0.009 0.009 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7 Penjagaan Keamanan Lingkungan Pekerjaan 0.187 0.187 0.187 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
8 Akses Road 0.779 0.779 0.779 0.39 0.39 0.140 0.140 0.140 0.140 0.140
9 Jembatan Sementara 1.605 1.605 1.605 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20
10 Peralatan K3 dan Papan K3 0.119 0.119 0.119 0.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11 Dokumentasi 0.022 0.022 0.022 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12 Dewatering 0.118 0.118 0.118 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13 Pemindahan Utilitas SUTM 0.087 0.087 0.087 0.09 0.09
14 Pemindahan Utilitas PDAM 0.087 0.087 0.087 ADDENDUM 1 0.09
ADDENDUM 2 0.09

II. SIPIL
II.1 PEKERJAAN BADAN JALAN KA
1 Sondir 0.242 0.242 0.242

rENCANA
0.0404 0.0404 0.0404 0.0404 0.04037 0.04037
75 %
2 Clearing & Grubing 1.999 1.999 1.080 0.072 0.072 0.072 0.072 0.072 0.072 0.072 0.072 0.072 0.072 0.072 0.072 0.072 0.072 0.072
3 Galian Tanah Biasa - - 0.789 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046 0.046
4 Dolken 0.676 0.676 0.073 0.015 0.015 0.015 0.015 0.015
5 Sesek Bambu 0.038 0.038 -
6 Geotextile 0.089 0.089 -
7 Pemasangan Geotextile Separator perkuatan 50x50 KN - 2.328 0.116 0.116 0.116 0.116 0.021 0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.116 0.095
8 Perbaikan Tanah Dasar dengan Situ dibungkus geotek (50/50 KN) - 0.585 0.073 0.073 0.073 0.073 0.073 0.073 0.073 0.073
9 Perbaikan Tanah Dasar dengan Situ dibungkus geotek (100/50)KN - 0.329 0.041 0.041 0.041 0.041 0.041 0.041 0.041 0.041
10 Perbaikan Tanah Dasar dengan Lime Stone - 4.040 0.162 0.162 0.162 0.162 0.162 0.202 0.202 0.202 0.202 0.202 0.202 0.202 0.202 0.202 0.202 0.202 0.202 0.202 0.202 0.202 0.202
11 Timbunan Tanah Badan KA termasuk Pemadatan 28.005 30.248 33.638 0.863 0.863 0.863 1.294 1.294 1.294 1.294 1.294 1.294 1.294 1.294 1.294 1.294 1.294 1.294 1.294 1.294 1.294 1.294 1.294 1.294 1.294 1.294 1.294 1.294 2.588
12 Sub Ballast 2.363 2.363 4.152 0.519 0.519 0.519 0.519 0.519 0.519 0.519 0.519
15 Biaya Pengujian Pekerjaan Plate Bearing Test 0.433 0.433 0.433 0.087 0.087 0.087 0.087 0.087
16 Pemasangan U-Ditch Precast K-350 7.241 7.241 -
17 Pemasangan Pagar Panel 4.950 4.950 -
18 Pengadaan dan Pemasangan Pagar Duri 1.033 1.033 -
19 Pengalihan Jalur Irigasi 0.433 0.216 0.216

II.2 PEKERJAAN RETAINING WALL


1 Galian Tanah Biasa 0.021 0.021 0.064 0.02 0.02 0.02
3 Pasangan Batu Kosong dibawah Konstruksi (Coble Stone) 0.015 0.015 0.053 0.05 50 %
5 Pasir Urug 0.002 0.002 0.007 0.01
7 Lantai Kerja K-175 0.021 0.021 0.082 0.08
8 Membuat Retaining Wall dari Beton K-300 0.255 0.255 0.978 0.33 0.33 0.33
10 Pembesian 0.246 0.246 0.568 0.15 0.15 0.15
11 Bekisting 0.144 0.144 0.444 0.15 0.15 0.15

III. TRACK
1 Pengadaan Balas kricak 3.252 3.252 3.193 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20
2 Mengerjakan balas kricak 0.798 0.798 0.784 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08
3 Muat, angkut, dan bongkar bantalan beton R.60 sampai lokasi. 0.374 0.374 0.374 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
4 Pemasangan bantalan beton beserta alat penambat 0.235 0.235 0.235 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
5 Muat, angkut, dan bongkar rel R.60 0.961 0.961 0.961 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10
6 Ecer dan stapling rel R.60 0.782 0.782 0.782 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08
7 Mengelas rel R.60 dengan flash butt menjadi panjang menerus. 0.393 0.393 0.393 0.06 0.06 0.06 0.06 0.06 0.06 0.06
8 Pemasangan Track 0.483 0.483 0.483 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05
9 Angkat listring dan Tamping awal dengan alat (HTT) 0.813 0.813 0.813 0.27 0.27 0.27
10 Angkat listring track dengan MTT+PBR (sampai kec. KA normal ) 0.938 0.938 0.938 0.31 0.31 0.31

IV. PEKERJAAN JEMBATAN


IV.1 Jembatan Km. 32+710 Panjang 60 m' 19.391 19.391 19.391 1.010 1.010 1.010 1.010 1.010 1.010 1.010 1.010 1.010 1.010 1.010 1.010 1.010 1.010 1.010 25 %
IV.2 Jembatan Km. 34+419 Panjang 40 m' 10.868 10.868 10.868 0.605 0.605 0.605 0.605 0.605 0.605 0.605 0.605 0.605 0.605 0.605 0.605 0.605 0.605 0.605

V.2 PEKERJAAN BOX CULVERT


Underpass 1.349 1.349 1.358 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08
1 Underpass 5 x 4.2 Tonasa
Underpass 6 x 4.2 Banggae
- Gali dan Bongkar Jalan aspal
- Galian tanah biasa
- Beton K 350
0.007
0.009
0.639
REALISASI 0.00 0.00 0.00
0.00 0.00
0.64
- lantai Kerja K.175 0.040 0.04
- Pembesian 0.780 0.78
- Bekisting 0.373 0.37
- urugan Pasir / sirtu 0.034 0.03
- Geotex LP 50x50 bungkus 0.019 0.01 0.01 0.01
- Detour / jalan pengalihan 0.038 0.01 0.01 0.01

Saluran Penyeimbang
Box Penyeimbang 2 x 2 7.528 3.294
Box Penyeimbang 2 x 2 (Precast) 1.991 3.808 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18 0.18
0%
JUMLAH NILAI PEKERJAAN (%) 100.00 100.00 100.00
KEMAJUAN PEKERJAAN MINGGUAN (%) 0.003 0.003 0.003 0.003 0.006 0.024 0.158 0.291 3.549 3.080 0.040 0.010 0.030 0.007 0.004 0.004 0.004 0.010 0.010 0.005 0.005 0.005 0.005 0.062 0.050 0.056 0.050 0.047 0.026 0.023 0.023 0.037 0.059 0.059 0.131 0.131 0.131 0.131 0.409 0.409 1.271 1.271 1.058 1.627 1.745 1.750 2.042 2.716 3.190 2.072 2.533 4.138 4.145 4.204 4.129 4.495 4.670 4.724 5.265 5.024 4.728 4.455 4.376 4.882 4.821 6.019
KEMAJUAN PEKERJAAN KUMULATIF MINGGUAN (%) 0.003 0.006 0.000 0.003 0.009 0.033 0.191 0.482 3.600 6.680 6.720 6.730 6.759 6.766 6.770 6.774 6.778 6.789 6.799 6.804 6.809 6.814 6.819 6.881 6.931 6.988 7.038 7.085 7.111 7.134 7.157 7.194 7.253 7.311 7.442 7.573 7.703 7.834 8.242 8.651 9.922 11.194 12.251 13.878 15.623 17.373 19.415 22.131 25.321 27.393 29.927 34.065 38.210 42.414 46.543 51.038 55.708 60.432 65.697 70.721 75.449 79.903 84.280 89.162 93.983 100.00
REALISASI KEMAJUAN PEKERJAAN MINGGUAN (%) 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.009 3.549 3.080 0.040 0.010 0.030 0.007 0.004 0.004 0.004 0.010 0.010 0.005 0.005 0.005 0.005 0.062 0.050 0.056 0.050 0.047 0.026 0.023 0.023 0.037 0.176 0.648 0.388 0.467 0.496 0.394 0.355 0.265 0.281 0.358 0.620
REALISASI KEMAJUAN PEKERJAAN KUMULATIF MINGGUAN (%) 0.006 0.012 0.018 0.024 0.030 0.036 0.042 0.051 3.600 6.680 6.720 6.730 6.759 6.766 6.770 6.774 6.778 6.789 6.799 6.804 6.809 6.814 6.819 6.881 6.931 6.988 7.038 7.085 7.111 7.134 7.157 7.194 7.370 8.017 8.405 8.872 9.368 9.762 10.117 10.382 10.662 11.020 11.640
DEVIASI (%) 0.003 0.006 0.018 0.021 0.021 0.003 -0.149 -0.431 3.118 5.758 5.777 5.766 5.780 5.771 5.767 5.762 5.758 5.760 5.762 5.759 5.756 5.752 5.749 5.803 5.845 5.807 5.808 5.807 5.665 5.636 5.380 5.103 0.117 0.706 0.963 1.299 1.664 1.928 1.874 1.730 0.740 -0.174 -0.612

Disetujui Oleh : Diperiksa Oleh : Dibuat oleh,


PEJABAT PEMBUAT KOMITMEN KONSULTAN SUPERVISI Kontraktor Pelaksana
PENGEMBANGAN PERKERETAAPIAN PT. LAUDZA ENGINEER CONSULTANT THAMRIN CITRA MULIA - TUJU WALI WALI, KSO
MAROS - PANGKEP

ARI WIBOWO, ST.MT. SUPARNA, SE. SUNALDI


Penata (III/c) DIREKTUR KUASA KSO
NIP. 19800309 200912 1 004