Finalized Project Scope

The Beaumont blue ammonia production facility project goal is to construct a brand-new
ammonia manufacturing plant, so one can produce blue ammonia by taking pictures and storing
carbon emissions. The facility will have a production capability of one,000 metric heaps of
ammonia according day and could encompass several components, which include a carbon
capture device, an ammonia synthesis unit, and a strong technology unit. The challenge may
even contain building infrastructure for carbon dioxide transportation and garages, such as
pipelines, storage tanks, and wells. The scope of the project consists of the engineering,
procurement, and construction (EPC) of the ammonia production facility, the carbon seizes
system, and the electricity technology unit. The undertaking will even contain the installation of
equipment, piping, instrumentation, electric, and management structures required for the
operation of the facility. The scope additionally covers the development of infrastructure
required for carbon dioxide transportation and garage, inclusive of pipelines, garage tanks, and
wells. The undertaking can even encompass commissioning and begin-up sports and schooling
for plant employees.

WBS Structure

The Work Breakdown Structure (WBS) for the Beaumont blue ammonia manufacturing facility
project is supplied inside the chart underneath:
PART 2 BLUE AMMONIA PRODUCTION 3

The project control hierarchy includes 5 levels. At the pinnacle of the hierarchy is Level 1, which
encompasses the overall control of the assignment. Below Level 1 is Level 2, which is
answerable for the engineering factors of the mission. Level three is devoted to the procurement,
at the same time as Level 4 handles construction activities. Finally, Level Five offers
commissioning and start-up sports. Together, those levels ensure that the assignment is
controlled successfully from theory to crowning glory, with every level responsible for a
particular factor of the venture.

At Level 1, the Project Management stage consists of all venture control sports, consisting of
venture-making plans, budgeting, scheduling, and chance control. Level 2 includes Engineering
sports, consisting of system layout, system design, and unique engineering. Level three includes
Procurement sports, which includes buying gadgets, materials, and offerings required for the
task. Level four consists of Construction sports, including civil works, gadget setup, piping,
electrical, and manipulation systems. Finally, at Level 5, Commissioning and Start-up sports
PART 2 BLUE AMMONIA PRODUCTION 4

include checking out, commissioning, and start-up of the plant, in addition to education for plant
employees. The WBS chart gives a visible representation of the venture structure, permitting
venture managers to pick out the important thing additives of the challenge and allocate sources
and duties for that reason. The WBS chart also enables us to discover the essential route of the
challenge, that is the sequence of activities that should be completed on time to keep away from
delays in the project timetable.

Develop Project Schedule

The task timetable for the Beaumont blue ammonia manufacturing facility assignment is
supplied within the chart beneath:

The venture will be accomplished in 4 phases, starting with Phase 1: Engineering, which will
take 365 days. This might be followed with the aid of Phase 2: Procurement, a good way to take
24 months. Phase 3: Construction will then begin and remain for 36 months. Finally, Phase four:
Commissioning and Start-up will take region, to be able to take 6 months to complete. Together,
PART 2 BLUE AMMONIA PRODUCTION 5

those four stages will ensure that the undertaking is completed effectively and in a well-timed
way, assembly of all vital requirements and necessities.

The undertaking timetable follows a sequential order, with each segment constructed on the
completion of the preceding phase. The Engineering segment will take 365 days to complete, in
the course of which the technique layout, system layout, and detailed engineering can be
finished. The Procurement section will take 24 months to complete, the duration of which
gadgets, substances, and offerings required for the task could be purchased. The Construction
segment will take 36 months to complete, during which civil works, equipment setup, piping,
electrical, and manipulation systems will be built. Finally, the Commissioning and Start-up phase
will take 6 months to finish, throughout which trying out, commissioning and start-up of the
plant might be conducted, and schooling for plant personnel can be supplied. The undertaking
schedule chart affords a visible representation of the assignment timeline, allowing assignment
managers to tune progress and perceive ability delays. It also helps to discover crucial paths and
dependencies between challenge activities, permitting task managers to prioritize sources and
make certain that the project stays on schedule.

Project Resources Tasks Chart

The project assets challenge chart gives a comprehensive breakdown of the sources required to
execute the Beaumont Blue Ammonia Production Facility challenge. The chart includes five
categories, namely human, economic, equipment, era, belongings, and contractors. The chart
goals are to make sure that all important resources are accounted for and that the task is
performed correctly and effectively.
PART 2 BLUE AMMONIA PRODUCTION 6

The Beaumont blue ammonia production facility venture would require numerous resources for
you to achieve success. Human sources might be critical and could encompass a challenging
manager, engineers, and skilled exertions. The economic assets wished for the task will consist
of capital funding, running prices, and contingency price range to make sure that the assignment
stays on budget. Equipment assets will also be required and will consist of gadgets inclusive of
ammonia synthesis reactors, heat exchangers, and gasoline scrubbers.

Technology resources will also be wished, such as ammonia production generation, automation
systems, and procedure control systems. Property resources can also be important, with a focus
on land acquisition, building production, and infrastructure development. Finally, contractor
assets can be required and will encompass an Engineering, Procurement, and Construction (EPC)
contractor, production control consultant, and commissioning and startup representative to
ensure that the task is finished successfully. With all of these assets in location, the Beaumont
blue ammonia production facility mission has a strong hazard of success.

The chart intends to provide challenge managers with clear information about the assets required
for the task and to make certain that these assets are to be had when wanted. The chart's
categories cover all factors of the mission, from the preliminary planning and design to the
development and operation of the ability. Additionally, the chart permits task managers to track
the development of every resource class, ensuring that the project stays on the right track and
budget.

Stakeholder Engagement
PART 2 BLUE AMMONIA PRODUCTION 7

For the Beaumont Blue Ammonia Production Facility, stakeholders include the local community,
government organizations, traders, and contractors. The engagement procedure will take area at
some point in the mission's lifecycle, from planning to commissioning. We will use various
channels to interact with stakeholders, such as meetings, newsletters, and social media. We may
even engage stakeholders thru public consultations and community events. The engagement
process can be ongoing, with normal updates supplied to stakeholders at the challenge's progress.

Communication Plan Chart

The communique plan chart outlines the communication sports so that will take region during the
task. The chart consists of dates/times, what will be mentioned, frequency, and the sort of
conversation. The chart's purpose is to ensure that every stakeholder is saved and informed
approximately the assignment's progress and that any troubles are addressed in a well-timed way.
PART 2 BLUE AMMONIA PRODUCTION 8

The assignment verbal exchange plan will contain 3 conferences. The first assembly is the
Project Kickoff Meeting, scheduled for June 1, 2023, at 10:00 AM. This may be an in-individual
assembly wherein the task evaluation, scope, and objectives will be mentioned. The second
assembly is the Monthly Progress Meeting, to be held on the primary Tuesday of each month at
2:00 PM, starting from July 2023. This might be a digital meeting in which the challenge repute
update, problems, and dangers could be discussed. The 0.33 and very last assembly is the Project
Completion Meeting, scheduled for October 1, 2026, at 11:00 AM. This might be an in-character
assembly where the final challenge evaluation, instructions learned, and next steps could be
discussed.

The communication plan chart guarantees that stakeholders acquire ordinary updates on the
project's progress and that any problems are addressed promptly. The plan also allows
stakeholders to offer comments and raise any issues they may have. Effective verbal exchange is
essential to the achievement of the challenge, and the verbal exchange plan chart ensures that all
stakeholders are kept informed and engaged through the project's lifecycle.