Professional Documents
Culture Documents
School of Commerce
Group Members
April 2022
Table of Contents
When a project’s initial cost goes beyond the actual budget to finish the expected task is
called Project overrun. Project overrun is unexpected change which results increasing
the total amount and has the power to completely stop, or delay the project depending
on the amount (size). Cost overrun is a trait for a project success unless they are
properly identified and addressed.
According to CHRON study at least 85 percent of every project face project overrun to
some degree which some of this are beyond the project managers or the responsible
persons capacity since they often happen unexpectedly.
Yuvika Iyer, on his article what is cost overrun that was written in July 29, 2021 he
categorized the factors in to three main and common factors which are Economic
factors (caused by erroneous project budgeting and unclear scope),Technical reasons
(caused by inaccurate estimates or incorrect data gathering), Psychological (caused by
decrease in project commitment levels).
Another article that was published in 2017 by Samuel Famiyeh,
Charleseye Amoatey, Ebenezer Adaku, Collins Sena Agbenohevi titled as “Major
causes of construction time and cost overruns: A case of selected educational sector
projects in Ghana” found that the key factors for project overrun is a result of financial
problems both at national stage and on the stakeholder, poorly structure and seated
working schedule and contract duration, poorly stated project scope, change in interest
by the client, lack of clear task division with poor performance specially the supervisor,
complexity of the project, poor method and mechanisms to do the job, poor site and
project management, policies and regulations, and so on causes project overrun.
When a project is about to go project overrun it shows signs that needs to be addressed
immediately to avoid it. This signs can be grouped to initial signs and enduring signs.
When we say initial signs it includes also proper and well detailed budget outlet, not
reviewing past project experiences and historical data etc. and when we say enduring
signs unexpected costs, lack of proper project tracking tools, poor resource utilization
plan, poor work breakdowns, poor documentation. (Yuvika Iyer,July 29, 2021)
Project overrun can be solved to some extents depending on the causes. The project
manager is responsible to give major attentions to the phenomena that he/she can
control and this can be achieved by organizing a proper risk management system within
the organization that is able to analysis, justify, and give solution to the current and
future risks that the project might face. The other system that will help to avoid cost
overrun is properly estimated project cost hiring the a well-qualified and experienced
specialist along with different project participants and other professionals must engage
in the cost estimation to make it precise and feasible (the specialist needs to consider
any financial inflation at both national and global level). Controlling scope changes will
play a significant change in avoiding cost overrun understanding the complexity of the
project, meeting deadlines or working as per the schedule, proper documentation and a
great communication with every participant will fill the gap and to focus on finishing
projects on budget. Furthermore, a (5 Primary Causes of Cost Overruns)
In conclusion a Project success depends on the accurate cost estimation. Many projects
in the world are failing to meet their estimate initial budgets due to several factors that
mentioned on the above paragraphs therefore project manager must give high attention
and time to avoid cost overruns and he/she must be well organized in resource
coordination, introducing new technologies, hiring qualified employees, and must control
the performance of the project and are obligated to take rapid decisions.
2, Project analysis
-CHRON study
-Article “What is cost overrun?” by Yuvika Iyer, July 29, 2021
-Article “Major causes of construction time and cost overruns: A case of selected
educational sector projects in Ghana” by Samuel Famiyeh , Charlseye Amoatey,
Ebenzer Adaku and Collins Sena Agbenohevi 2017
- Article “5 Primary Causes of Cost Overruns”
-BKW C.A.P.E PLC (bkwarchitects@gmail.com)
-Architect Bisrat (bkwarchitects@gmail.com)
- Resident engineer Kassahun (bkwarchitects@gmail.com)