Electrical works for

Method Statement for Tray / Ladder Installation


1 Preparation

1.1 Ensure that the materials to be used for installation are of the inspected and approved brands and type.

1.2 Ensure that the installation works procedures are fully comprehended by the supervisor and his workers.

1.3 Ensure that approved type of supports and anchors for tray/ladder support are used

1.4 Studied the planned cable routing layout from the latest shop drawings.

2 Tray / Ladder Installation

2.1 From the working drawings, locations of cable tray/cable ladder are marked on site taking reference from the column and /
or beam grid lines.

2.2 Ensure that location of support shall be 100mm (minimum) away from structural pre-stressed cables. (For Hollow Core Slab
Area.)

2.3 Position of pre-stress cables can be determined from drawings provided by builder and confirmed by structural engineer
prior to drilling.

2.4 Correct size of holes are then drilled, and approved type of metal expansion bolts are used to fix threaded rods / brackets /
Channels on ceilings / walls /columns.

2.5 Cable tray/cable ladder support / bracket shall be cut and install according to the required elevation, which can be checked