You are on page 1of 1

Appendix G: HSE Commencement Certificate

HSE COMMENCEMENT CERTIFICATE

Refer Article 4 C9

Contract Title:
Risk of Contract High Medium Low Management Mode 1 2 3
Contractor: Contract No:
Sub-Contractors:
Contract Plan Activity Date Completed Restrictions and Exceptions

HSE Management Plan Approved

HEMP Approved

HSE Monitoring Plan Approved

Kick Off Meeting Held

HSE Workshop Held

Residential Camp and Welfare facilities Accepted

Industrial Site Accepted

Sub Contractors audited and Approved

Vehicle/Plant Accepted
Training Completed: (refer Appendix 3)
Entry – E
C-Compulsory, shall be attended before being deployed to
carry out designated role i.e. immediately.
M-Mandatory-shall be attended within a maximum of 2
months of being given the designated role
R-Recommended – highly desirable event for a target
population.

Pre-Execution Audit Completed

Essential Audit Items Completed


Notes:

On behalf of the Contractor I confirm that the activities stated above have been carried out and we are capable of
performing the work in a healthy, safe and environmentally responsible manner.
Name Ref. Ind. Responsibility Signature
Contract
Manager
We hereby agree that the HSE status of this Contract allows work to proceed, subject to the above exceptions.
Name Ref. Ind. Responsibility Signature
PDO
Representative*
PDO Contract
Holder
* At Contract Holder's discretion