IE414 SUPPLY CHAIN MANAGEMENT: QUIZ ON MASTER PLANNING SCHEDULE
Provide a master planning schedule of the following data: Requirement – 300 units of Product 1 in week 10.

Product Label 1 2 3 4 5 6 7 8 9 10
Gross Requirements 300
Scheduled Receipts 10
Projected Available
100 100 100 100 100 100 100 100 100 100
1 Balance
Net Requirements 190
Planned order receipt 190
Planned order release 190
Gross Requirements 190
Scheduled Receipts 20
Projected Available
80 80 80 80 80 80 80 80
A Balance
Net Requirements 90
Planned order receipt 90
Planned order release 90
Gross Requirements 90 190
Scheduled Receipts 0 90
Projected Available
75 75 75 75 75 0
B Balance
Net Requirements 15 100
Planned order receipt 15 100
Planned order release 15 100
Gross Requirements 190
Scheduled Receipts 20
Projected Available
60 60 60 60 60 60 60 60
C Balance
Net Requirements 110
Planned order receipt 110
Planned order release 110
Gross Requirements 180
Scheduled Receipts 10
Projected Available
54 54 54 54 54
D Balance
Net Requirements 116
Planned order receipt 116
Planned order release 116
E Gross Requirements 45 300
Scheduled Receipts 5 0
Projected Available
50 50 50 50 10 10 10
Balance
Net Requirements -10 290
Planned order receipt 0 290
Planned order release 0 290
Gross Requirements 15 100
Scheduled Receipts 0 5
Projected Available
25 25 25 25 10 10 10
F Balance
Net Requirements -10 85
Planned order receipt 0 85
Planned order release 0 85