Professional Documents
Culture Documents
Weeks PD 1 2 3 4 5 6 7 8 9 10 11 12
Quantity
15 5 7 10 15 20 10
produced
1
Weeks PD 1 2 3 4 5 6 7 8 9 10 12
1
1 1 1
Gross requirement 5 7 15 20 8 2 16
5 0 0
Scheduled receipt 5
Projected available
17 2 2
balance
1 1
Net requirements 5 15 20 8 2 16
0 0
Planned order 1 1
5 15 20 8 2 16
receipts 0 0
Planned order 1
5 10 20 10 8 2 16
releases 5
Gear Box
Input Shaft P
Weeks 1 2 3 4 5 6 7 8 9 10 11 12
D
4
Gross requirement 10 20 30 20 16 4 32
0
Scheduled receipt 22
Projected available
40 30 32 2
balance
3
Net requirements 20 16 4 32
8
3
Planned order receipts 20 16 4 32
8
1
Planned order releases 38 20 4 32
6
Question 2: Phil would like to consider the costs that his accountants are currently
using for inventory carrying and setup for the gear boxes and input shafts. These costs
are as follows:
Part Cost
Gear box setup = $90 / order
Inventory carrying cost = $2 / unit /week
Input shaft setup = $ 45/ order
Inventory carrying cost = $ 1/ unit/ week
Answer- Given the cost structure stipulated in question 1, the cost of the entire
schedule when the inventory is valued at the end of every week shall be;
Inventory = ending inventory x holding cost
4 x 2 = $8
Setup Cost = total inventories x setup
8 x 90 = $720
Gear Box cost = setup cost + inventory
Total = $720 + $ 8 =$728
Inventory = total ending inventory x holding cost
96 x 1 = $96
Setup Cost = planned inventories x setup
5 x 45 = $225
Input Shaft = setup cost + inventory
Total = $225 + $96 = $321
The total cost for the gear box and the input shaft = gear box cost + input shaft cost
Total Cost = $728 + $321 = $1,049
Question 3: Find a better schedule by reducing the number of orders and carrying some
inventory. What are the savings with this new schedule?
Answer- To derive a better and cost-effective method of production the Least total cost
method (LTC) will be used. The LTC is a dynamic sizing technique used lot sizing to
calculate the order quantity.
Weeks PD 1 2 3 4 5 6 7 8 9 10 11 12
Quantity produced 15 5 7 10 15 20 10 8 2 16
Weeks PD 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirement 15 5 7 10 15 20 10 8 2 16
Scheduled receipt 5 26
Net requirements 5 10 45 20 10 8 2 16
Weeks PD 1 2 3 4 5 6 7 8 9 10 1
Gross requirement 30 90 52
Scheduled receipt 22
Net requirements 58 52